MPO Meeting Minutes
Draft Memorandum for the Record
Boston Region Metropolitan Planning Organization Meeting
February 15, 2024, Meeting
10:00 AM–12:45 PM, Zoom Video Conferencing Platform
Steve Woelfel, Chair, representing Monica Tibbits-Nutt, Secretary of Transportation and Chief Executive Officer of the Massachusetts Department of Transportation (MassDOT)
The Boston Region Metropolitan Planning Organization (MPO) agreed to the following:
See attendance on page 15.
There was none.
T. Teich stated that the first meeting of the Vision Zero Task Force was held on February 13, 2024. This group will guide the development of the Vision Zero Action Plan, funded by the Safe Streets and Roads for All grant.
Robert Dolan, Town of Lynnfield, advocated for continued programming of the Wakefield Rail Trail.
Patrice Garvin and Glenn Clancy, Town of Belmont, advocated for continued programming of the Belmont Community Path.
Brad Rawson, Inner Core Committee and the City of Somerville, discussed the Vision Zero Task Force and provided project updates on the McGrath Boulevard project.
JR Frey, Town of Hingham, discussed the Vision Zero Task Force and stated that the Hingham Route 3A Improvement Project has submitted a 75 percent design.
Tom Bent, Inner Core Committee and the City of Somerville, stated that the Memorandum of Understanding Update Committee met to discuss regional transportation authority representation and review staff-led document updates.
Jen Rowe, City of Boston (Boston Transportation Department), stated that the TIP Process, Engagement, and Readiness Committee will meet following this meeting to further discuss readiness updates shared in this meeting.
L. Diggins stated that the previous meeting discussed the Learning from Roadway Pricing study and TIP development.
1. December 21, 2023, meeting minutes (pdf) (html)
1. Work Scope for Exploration of Bluebikes Transit Connections (pdf) (html)
T. Bonner stated that this project is funded with MassDOT-Directed PL funds for $65,401 and is expected to take seven months to complete. The objective of this project is to leverage available trip and survey data to identify existing Bluebike trip flows to transit and identify potential future locations of Bluebikes stations to improve transit connections, particularly in Environmental Justice communities. The project has four tasks: conduct a literature review, synthesize available Bluebikes data, conduct accessibility analyses, and communicate and document findings to stakeholders. The final work product will be a memorandum summarizing work efforts.
L. Diggins expressed interest in the findings of this study.
J. Alessi requested that any data that might be useful to municipalities be shared.
Seth Gadbois, Conservation Law Foundation, asked what assumptions will be made about the state of bike infrastructure in the analysis. T. Bonner stated that the bicycle level of traffic stress will be included in the analysis.
J. Rowe discussed bicycle level of traffic stress developed by the City of Boston.
David Koses, City of Newton, discussed opportunities to integrate the Bluebikes and MBTA fare systems.
Derek Shooster, MassDOT, stated that findings from the study could be beneficial for projects in design that are programmed in the TIP.
A motion to approve the work scope for Exploration of Bluebikes Transit Connections was made by the Regional Transportation Advisory Council (L. Diggin) and seconded by the MBTA (L. Gilmore). The motion carried.
1. Work Scope for Lab and Municipal Parking Phase II (pdf) (html)
S. Fox stated that this study is budgeted for $45,000 and is scheduled to take seven months after work commences. Objectives of the study are to use materials drafted in Phase I to measure the actual parking supply and utilization at lab and life sciences facilities and to synthesize the results of the analysis into recommendations to support a variety of stakeholders. Work is divided into four tasks: pilot data collection at lab facilities, expand data collection activities, analyze data, and synthesize this information into a technical memorandum, to be presented to the board.
A motion to approve the work scope for Lab and Municipal Parking Phase II was made by the Inner Core Committee (T. Bent) and seconded by the MBTA Advisory Board (Brian Kane). The motion carried.
1. Work Scope for FFY 2024 MBTA Count Program (pdf) (html)
R. McCarron stated that this work scope is supported by MassDOT-directed PL funds, is budgeted for $40,000, and will take seven months to complete. Manual counts will be taken at key MBTA locations where data is insufficient or not automated. Staff will conduct passenger counts on the Green Line and Commuter Rail. Staff will provide data to the MBTA.
A motion to approve the work scope for FFY 2024 MBTA Count Program was made by the City of Boston (J. Rowe) and seconded by the MAPC (E. Bourassa). The motion carried.
1. Transit Safety Performance Targets Memo (pdf) (html)
2. Transit Safety Performance Targets Appendix (pdf) (html)
S. Taylor stated that performance metrics for transit safety fall under four categories: fatalities, injuries, safety events, and system reliability. Measures in fatalities include the number of fatalities and the fatality rate per vehicle-revenue mile (VRM); injuries are the number of injuries and the injury rate per VRM; safety events are the number of safety events and safety event rate per VRM; and system reliability is measured in VRM per major mechanical failure.
MBTA calendar year 2024 safety targets are shown in Tables 1, 2, 3, and 4. The Cape Ann Transportation Authority and MetroWest Regional Transit Authority (MWRTA) safety targets are in Tables 5 and 6, respectively.
Table 1
MBTA 2024 Bus Safety Targets
Metric and Calendar Year |
Actual Performance 2020–22 |
2023 Target |
2024 Target |
Fatalities |
0.67 |
0.0 |
0.0 |
Fatality Rate (per one million VRM) |
0.03 |
0.0 |
0.0 |
Injuries |
257 |
286 |
252 |
Injury Rate (per one million VRM) |
11.53 |
12.23 |
11.3 |
Safety Events |
89 |
98 |
88 |
Safety Event Rate (per one million VRM) |
4.01 |
4.21 |
3.93 |
System Reliability |
27,358 |
29,500 |
28,500 |
MBTA = Massachusetts Bay Transportation Authority. VRM = Vehicle-revenue mile.
Table 2
MBTA 2024 Heavy Rail Safety Targets
Metric and Calendar Year |
Actual Performance 2020–22 |
2023 Target |
2024 Target |
Fatalities |
0.33 |
0.0 |
0.0 |
Fatality Rate (per one million VRM) |
0.02 |
0.0 |
0.0 |
Injuries |
173 |
180 |
170 |
Injury Rate (per one million VRM) |
8.3 |
7.99 |
8.13 |
Safety Events |
23 |
24 |
23 |
Safety Event Rate (per one million VRM) |
1.13 |
1.07 |
1.11 |
System Reliability |
46,335 |
44,500 |
49,000 |
MBTA = Massachusetts Bay Transportation Authority. VRM = Vehicle-revenue mile.
Table 3
MBTA 2024 Light Rail Safety Targes
Metric and Calendar Year |
Actual Performance 2020–22 |
2023 Target |
2024 Target |
Fatalities |
0.0 |
0.0 |
0.0 |
Fatality Rate (per one million VRM) |
0.0 |
0.0 |
0.0 |
Injuries |
180 |
79 |
79 |
Injury Rate (per one million VRM) |
14.33 |
14.35 |
14.04 |
Safety Events |
27 |
27 |
27 |
Safety Event Rate (per one million VRM) |
4.83 |
4.94 |
4.74 |
System Reliability |
7,680 |
7,650 |
7,900 |
MBTA = Massachusetts Bay Transportation Authority. VRM = Vehicle-revenue mile.
Table 4
MBTA 2024 Paratransit Safety Targets
Metric and Calendar Year |
Actual Performance 2020–22 |
2023 Target |
2024 Target |
Fatalities |
0.0 |
0.0 |
0.0 |
Fatality Rate (per one million VRM) |
0.0 |
0.0 |
0.0 |
Injuries |
24 |
27 |
23 |
Injury Rate (per one million VRM) |
2.58 |
2.27 |
2.53 |
Safety Events |
30 |
20 |
29 |
Safety Event Rate (per one million VRM) |
3.35 |
1.74 |
3.28 |
System Reliability |
N/A |
62,500 |
25,900 |
MBTA = Massachusetts Bay Transportation Authority. VRM = Vehicle-revenue mile.
Table 5
Cape Ann Transportation Authority 2024 Safety Targets
Metric and Calendar Year |
Fixed Route Actual Performance 2019–23 |
Fixed Route 2024 Target |
Demand Response Actual Performance 2019–23 |
Demand Response 2024 Target |
Fatalities |
0.0 |
0.0 |
0.0 |
0.0 |
Fatality Rate (per 100,000 VRM) |
0.0 |
0.0 |
0.0 |
0.0 |
Injuries |
0.2 |
1.0 |
0.2 |
1.0 |
Injury Rate (per 100,000 VRM) |
0.1 |
0.5 |
0.2 |
0.5 |
Safety Events |
2.4 |
2.5 |
1.2 |
1.5 |
Safety Event Rate (100,000 VRM) |
0.2 |
1.5 |
0.8 |
1.0 |
System Reliability |
119,622 |
115,000 |
154,352 |
135,000 |
VRM = Vehicle-revenue mile.
Table 6
MetroWest Regional Transit Authority 2024 Safety Targets
Metric and Calendar Year |
Fixed Route Actual Performance 2019–23 |
Fixed Route 2024 Target |
Demand Response Actual Performance 2019–23 |
Demand Response 2024 Target |
Fatalities |
0.0 |
0.0 |
0.0 |
0.0 |
Fatality Rate (per 100,000 VRM) |
0.0 |
0.0 |
0.0 |
0.0 |
Injuries |
0.8 |
10 |
1.0 |
8 |
Injury Rate (per 100,000 VRM) |
0.1 |
0.8 |
0.1 |
1 |
Safety Events |
1.2 |
10 |
1.6 |
8 |
Safety Event Rate (per 100,000 VRM) |
0.1 |
0.8 |
0.2 |
1.0 |
System Reliability |
149,558 |
75,000 |
79,358 |
75,000 |
VRM = Vehicle-revenue mile.
S. Taylor stated that the next steps, once safety targets are supported, are to incorporate them into the FFYs 2025–29 TIP and provide information about how planned investments impact safety performance measures.
Steve Olanoff, Three Rivers Interlocal Council, asked for clarification on what is considered a safety event. S. Taylor stated that safety events can include events where a fatality or injury takes place and refers to the event itself, such as crashes, derailments, or events at transit stations.
J. Rowe asked the MBTA for elaboration on how performance targets were set. Mike Catsos, MBTA, stated that performance targets are established with a methodology from the National Public Transportation Safety Plan and the three year rolling average can conceal month-to-month trends of particularly strong or weak performance, leading to some fluctuations in the annual targets.
J. Rowe asked the MWRTA for elaboration on how performance targets were set. Jim Nee, MWRTA, stated that performance targets have gotten more aggressive annually.
L. Diggins asked why safety, injury, and reliability metrics have more variability associated with them. M. Catsos stated that there are numerous factors that can impact the metrics, including location and vehicle age.
A motion to approve the transit safety performance targets was made by the MBTA Advisory Board (B. Kane) and seconded by the MAPC (E. Bourassa). The motion carried.
1. FFYs 2024–28 TIP Amendment Four (pdf)
E. Lapointe stated that the FFYs 2024–28 TIP Four proposes
· cost increases to one Regional Target and two Statewide Highway projects;
· acceleration of paving on Route 2 in Acton, Littleton, and Boxborough;
· cost revisions to the Interstate-90/I-495 project in Hopkinton and Westborough;
· funding adjustments to two MWRTA projects;
· carbon reduction funding for Quincy Bus Garage; and
· programming of FFY 2024 Community Transit Grants for operations.
E. Lapointe stated that one comment was received during the comment period from the I-495/MetroWest Partnership expressing support for changes to projects 609054: Littleton- Reconstruction of Foster Street, 605313: Natick- Bridge Replacement Route 27 over Route 9, and 610722: Acton-Boxborough-Littleton- Pavement Preservation on Route 2.
A motion to endorse the FFYs 2024–28 TIP Amendment Four was made by the Town of Brookline (Erin Chute) and seconded by the MBTA Advisory Board (B. Kane). The motion carried.
B. Harvey stated that six disparate impacts and disproportionate burdens would likely result from the Long-Range Transportation Plan, Destination 2050. It was decided that Conveyal would be used to assess if any TIP scenarios mitigate disparities related to destination access and travel time. B. Harvey stated that Conveyal uses a multimodal network, builds detailed transportation scenarios and compares impacts, conducts regional or single-point analyses, and assesses impacts of different demographic groups.
S. Murthy stated that work has been coordinated with the Disparate Impact Mitigation work when selecting projects to study and add to Conveyal and when setting analysis parameters. Next steps are to run Conveyal with TIP scenarios and develop scoring recommendations. Projects added to Conveyal fall under seven categories: fixed route transit, microtransit, Complete Streets, off-street paths, bridge reconstruction, Intersection Improvements, and climate resilience improvements. Parameters needed to analyze destination access include travel mode, destinations, travel time cut offs, population data, and transportation projects.
B. Harvey reviewed findings related to Conveyal to date. Strengths include a fast run time, results by demographic group, and the use of small-scale and regional analyses. Limitations include not being able to measure everything important, only two levers are used to change access: speed and new connections, and there is difficulty in representing bikeshare and microtransit.
J. Rowe asked how quickly a Conveyal run can be set up and if it can be used to compare different scenarios to one another. Tanner Bonner, MPO Staff, stated that a run can take between five and 20 minutes.
Jim Fitzgerald, City of Boston (Boston Planning and Development Agency) asked how Conveyal calculates transit travel time improvements. T. Bonner stated that segments of routes can be scaled by a factor, depending on the improvements.
1. TIP Readiness Days Update (pdf) (html)
E. Lapointe reviewed the purpose of TIP Readiness Days and stated that the updates lay out and account for changes on current projects before considering new projects to fund in FFYs 2025–29. The draft financial outlook for the FFYs 2025–29 TIP are in Table 7.
Table 7
Draft Financial Outlook FFYs 2025–29 TIP
|
2025 |
2026 |
2027 |
2028 |
2029 |
Total available Regional Highway Target Funds |
$128,427,689 |
$125,285,687 |
$155,132,142 |
$158,052,175 |
$161,030,608 |
Draft total programmed Regional Highway Target funds |
$55,813,413 |
$90,610,293 |
$235,817,183 |
$184,091,988 |
$109,840,000 |
Regional Highway Target Funds unprogrammed |
$72,614,276 |
$34,675,394 |
-$80,685,041 |
-$26,039,813 |
$51,190,608 |
Percent unprogrammed |
56.5% |
27.7% |
-52.0% |
-16.5% |
31.8% |
FFY = Federal Fiscal Year.
E. Lapointe stated that 11 projects saw cost changes of 10 percent, 12 projects are at risk for future delay, and 14 projects recommended for delay.
There are two updates to the FFY 2024 program: a cost increase of 11 percent for project 110980: Newton-Weston-Bridge Rehabilitation, Commonwealth Avenue (Route 30) over the Charles River, flagged for medium risk due to National Environmental Policy Act permitting and a cost decrease of four percent for project 610544: Peabody-Multi-Use Path Construction of Independence Greenway at I-95 and Route 1, flagged for medium risk of delay due to Chapter 91 Massachusetts Public Waterfront Action environmental permits.
Information about delayed projects, projects with high delay risk, moderate delay risk, and projects with cost changes higher than 10 percent can be found in Table 8, 9, 10, and 11, respectively.
Table 8
Delayed Projects
Project Name |
Current Year |
New Year |
Revised Budget |
606453- Improvements on Boylston Street, from Intersection of Brookline Avenue and Park Drive to Ipswich Street |
2025 |
2026 |
$9,011,654 |
609532- Chelsea- Targeted Safety Improvements and Related Work on Broadway, from Williams Street to City Hall Avenue |
2025 |
2026 |
$9,807,515 |
605168- Hingham- Improvements on Route 3A from Otis Street/Cole Road Including Summer Street and Rotary; Rockland Street to George Washington Boulevard |
2025 |
2026 |
$33,754,352 |
609257- Everett- Reconstruction of Beacham Street |
2025 |
2027 |
$11,392,842 |
609252- Lynn- Rehabilitation of Essex Street |
2025 |
2027 |
$21,274,531 |
605168- Ashland- Rehabilitation and Rail Crossing Improvements on Cherry Street |
2025 |
2028 |
$1,316,340 |
609204- Belmont- Community Path, Belmont Component of the Massachusetts Central Rail Trail (Phase I) |
2026 |
2027 |
$22,139,730 |
612989- Boston- Bridge Preservation, B-16-066 (38D), Cambridge Street over MBTA |
2026 |
2027 |
$17,297,280 |
609437- Salem-Peabody- Boston Street Improvements |
2026 |
2027 |
$26,122,722 |
608954- Weston- Reconstruction on Route 30 |
2026 |
2027 |
$20,740,442 |
610662- Woburn- Roadway and Intersection Improvements at Woburn Common, Route 38 (Main Street), Winn Street, Pleasant Street, and Montvale Avenue |
2026 |
2027 |
$18,077,904 |
605743- Ipswich- Resurfacing and Related Work on Central and South Main Streets |
2026–27 |
2027–28 |
$12,197,846 |
610932- Brookline- Rehabilitation of Washington Street |
2027 |
2028 |
$30,155,078 |
609246- Lynn- Rehabilitation of Western Avenue (Route 107) |
2027–29 |
2028–30 |
$45,897,600 |
MBTA = Massachusetts Bay Transportation Authority.
Table 9
Projects with High Delay Risk
Project Name |
Year |
Revised Budget |
608051- Wilmington- Reconstruction on Route 38 (Main Street), from Route 62 to the Woburn City Line |
2025 |
$22,818,682 |
613088- Malden- Spot Pond Brook Greenway |
2027 |
$4,684,622 |
608158- Westwood-Norwood- Reconstruction of Canton Street to University Drive |
2028 |
$22,854,846 |
613145- Wakefield- Comprehensive Downtown Transportation Improvement Project |
2028 |
$18,435,976 |
606226- Boston- Reconstruction of Rutherford Avenue from City Square to Sullivan Square |
2027–32 |
$197,759,449 |
Table 10
Projects with Moderate Delay Risk
Project Name |
Year |
Revised Budget |
608067- Woburn- Intersection Reconstruction at Route 3 (Cambridge Road) and Bedford Road and South Bedford Street |
2025 |
$3,438,311 |
608940- Weston- Intersection Improvements at Boston Post Road (Route 20) at Wellesley Street |
2026 |
$3,362,335 |
611983- Chelsea- Park and Pearl Street Reconstruction |
2027 |
$11,705,708 |
613121- Everett- Targeted Multi-Modal and Safety Improvements on Route 16 |
2027 |
$5,059,530 |
607981- Somerville- McGrath Boulevard Construction |
2027–29 |
$98,840,000 |
610666- Swampscott- Rail Trail Construction |
2028 |
$8,624,000 |
Table 11
Projects with Cost Changes Above 10 Percent
Project Name |
Year |
Current Budget |
Revised Budget |
610544- Peabody- Multi-Use Path Construction of Independence Greenway at I-95 and Route 1 |
2025 |
$15,777,132 |
$13,966,099 |
608045- Milford- Rehabilitation on Route 16, from Route 109 to Beaver Street |
2026 |
$9,758,201 |
$13,548,565 |
E. Bourassa stated that the amount of unprogrammed balance in FFY 2025 is among the greatest amount that the MPO has seen to date.
E. Chute asked how risk is established in the TIP Readiness Days. E. Lapointe stated that readiness is determined from input from MassDOT Highway districts, program managers, the Statewide Transportation Improvement Program manager, environmental division, right-of-way division, and director’s office, resulting in an ultimate readiness conclusion.
Ken Miller, Federal Highway Administration, discussed strategies to address funding discrepancies in the FFYs 2025–29 TIP.
J. Fitzgerald discussed the structure of TIP Readiness Days and opportunities to integrate the perspectives of municipal project proponents.
B. Kane asked what the mechanism would be to move funding from one federal fiscal year to the other. B. Kane asked about the process to update the formula to distribute Regional Target funds.
J. Rowe provided project updates on Rutherford Avenue.
A motion to adjourn was made by the MBTA Advisory Board (B. Kane) and seconded by the Regional Transportation Advisory Council (L. Diggins). The motion carried.
Members |
Representatives and Alternates |
At-Large City (City of Everett) |
Eric Molinari |
At-Large City (City of Newton) |
David Koses |
At-Large Town (Town of Arlington) |
John Alessi |
At-Large Town (Town of Brookline) |
Erin Chute |
City of Boston (Boston Planning & Development Agency) |
Jim Fitzgerald |
City of Boston (Boston Transportation Department) |
Jen Rowe |
Federal Highway Administration |
Ken Miller |
Federal Transit Administration |
|
Inner Core Committee (City of Somerville) |
Tom Bent Brad Rawson |
Massachusetts Department of Transportation |
Steve Woelfel John Bechard |
MassDOT Highway Division |
John Romano |
Massachusetts Bay Transportation Authority (MBTA) |
Laura Gilmore |
Massachusetts Port Authority |
|
MBTA Advisory Board |
Brian Kane |
Metropolitan Area Planning Council |
Eric Bourassa |
MetroWest Regional Collaborative (City of Framingham) |
Dennis Giombetti |
Minuteman Advisory Group on Interlocal Coordination (Town of Acton) |
|
North Shore Task Force (City of Beverly) |
Darlene Wynne |
North Suburban Planning Council (Town of Burlington) |
|
Regional Transportation Advisory Council |
Lenard Diggins |
South Shore Coalition (Town of Hull) |
|
South West Advisory Planning Committee (Town of Wrentham) |
|
Three Rivers Interlocal Council (Town of Norwood) |
Tom O’Rourke Steve Olanoff |
Other Attendees |
Affiliation |
Sarah Bradbury |
MassDOT |
Mike Catsos |
MBTA |
Glenn Clancy |
|
Julie Dombroski |
MassDOT |
Daniela Espinosa |
BPDA |
JR Frey |
Town of Hingham |
Seth Gadbois |
Conservation Law Foundation |
Patrice Garvin |
Town of Belmont |
Anil Gurcan |
MassDOT |
Amy Ingles |
Town of Brookline |
Kristina Johnson |
Town of Hudson |
Raissah Kouame |
MassDOT |
Derek Krevat |
MassDOT |
Barbara Lachance |
MassDOT |
Owen MacDonald |
Town of Weymouth |
Jeremy Marsette |
|
John McQueen |
WalkMassachusetts |
Benjamin Muller |
MassDOT |
Jim Nee |
MWRTA |
Sheila Page |
Town of Lexington |
Allison Patton |
HEI |
Austin Sanders |
|
Cheryll-Ann Senior |
MassDOT |
Derek Shooster |
MassDOT |
Anson Stewart |
|
Tyler Terrasi |
MWRTA |
John Tomasz |
|
Frank Tramontozzi |
Quincy |
Megan Willis-Jackson |
MBTA |
MPO Staff/Central Transportation Planning Staff |
Tegin Teich, Executive Director |
Tanner Bonner |
Abigail Cutrumbes |
Judy Day |
Annette Demchur |
Sabiheh Faghih |
Sophie Fox |
Betsy Harvey |
Dave Hong |
Jia Huang |
Stella Jordan |
Ali Kleyman |
Ethan Lapointe |
Erin Maguire |
Rose McCarron |
Srilekha Murthy |
Gina Perille |
Sarah Philbrick |
Bradley Putnam |
Sean Rourke |
Roger Roy |
Samuel Taylor |
CIVIL RIGHTS NOTICE TO THE PUBLIC Welcome. Bem Vinda. Bienvenido. Akeyi. 欢迎. 歡迎.
For additional information or to file a civil rights complaint, visit www.bostonmpo.org/mpo_non_discrimination.
To request accommodations at meetings (such as assistive listening devices, materials in accessible formats and languages other than English, and interpreters in American Sign Language and other languages) or if you need this information in another language, please contact:
Boston Region MPO Title VI Specialist 10 Park Plaza, Suite 2150 Boston, MA 02116 Phone: 857.702.3700 Email: civilrights@ctps.org
For people with hearing or speaking difficulties, connect through the state MassRelay service, www.mass.gov/massrelay. Please allow at least five business days for your request to be fulfilled. |