Draft Memorandum for the Record

Boston Region Metropolitan Planning Organization

Transportation Improvement Program (TIP) Process, Engagement, and Readiness Committee Meeting Summary

March 28, 2024, Meeting

1:00 PM–3:00 PM, Zoom Video Conferencing Platform

Jen Rowe, Chair, representing Mayor Michelle Wu, City of Boston and the Boston Transportation Department (BTD)

Meeting Agenda

1.    Introductions

See attendance on pages 9–12.

2.    Public Comments

Jim Nee (MetroWest Regional Transit Authority [MWRTA]) expressed support for the MWRTA Equitable Hub redesign and the Transit Transformation Low Emissions Bus Procurement project. These projects are important to lower the carbon footprint of the MWRTA.

State Representative Michael Soter spoke on behalf of the Town of Bellingham, sharing a project proposal for the Interstate 495 interchange. M. Soter expressed hope that the project would be a high priority due to degradation of the streets and infrastructure and asked the committee to help fix it as soon as possible.

Kristina Johnson, Town of Hudson, advocated for the Central Mass Rail Trail. The project has received substantial funding from a local community preservation committee. K. Johnson asked the committee to strongly consider this project for the design project pilot funding.

Marian Neutra, Town of Sherborn, advocated for funding for the improvement of Routes 27 and 16. Routes 27 and 16 briefly run close together in Sherborn, creating significant congestion. The application is for a complete redesign of the town center. This would allow for easier access to the town center, reduced congestion, and increased safety measures.

Jesse Riedle, Town of Bellingham, expressed support for the project proposal for the Interstate 495 interchange. John Morgan, CHA Consulting, reiterated the importance of the project due to improvements for those traveling through the region. J. Morgan also shared information regarding the timeline of the design.

Travis Ahern, Town of Holliston, spoke about a design project for Route 16. The project aimed to improve heavy industrial and freight traffic that was causing congestion in the area. In addition, the proposed Rail Trail would run through this area, resulting in increased pedestrian traffic.

3.    Recap of TIP Scenarios from March 21st MPO Meeting—Ethan Lapointe, MPO Staff

Documents posted to the MPO meeting calendar

1.    Scenario Parameters (pdf) (html)

2.    Scenario Three Project Adjustments (pdf) (html)

Ethan Lapointe, MPO staff, recapped recent MPO board and TIP Process, Engagement, and Readiness Committee meetings and a discussion of the project changes for FFY 2027. E. Lapointe shared that initially this meeting was to include a discussion about an amendment to the FFYs 2024–28 TIP that addressed the City of Newton’s difficulties with its micro transit services, but more significant changes needed to be made, which means the city will be unable to qualify for funding. The $210,000 is already accounted for in proposed scenarios for this TIP.

E. Lapointe reviewed committee meetings, beginning with the first meeting on October 18, 2023.This meeting noted a decreasing trend in applications for TIP projects. The MPO’s major capital projects would potentially impact not only the ability to fund new projects, but also impact the ability to maintain funding and support for projects over time. During the second meeting, on December 14, 2023, members discussed the decline of applications, the Community Connections Program, and the decline in project readiness. Most of the projects funded in FFYs 2025–26 were delayed into 2027–28, causing a deficit and spurring the creation of the committee.

The March 14, 2024, meeting focused on mitigating the deficit in FFYs 2027–28 and utilizing unspent funds in FFYs 2025–26. During the March 21, 2024, MPO board meeting, the MPO board could not agree on how to address the deficit. The MPO board discussed the following options:

·       Temporarily deprogramming projects from the FFY 2026 or FFY 2027 TIP

·       Delaying projects into FFY 2029

·       Taking projects that are currently using Advanced Construction or are funded across multiple years, and reducing their Advanced Construction

 

The committee asked for the following information: recent milestones attained in the design and submissions to MassDOT, the upcoming milestones and steps taken to reach the proposed readiness year, how old the current cost estimate is, and if the scope of work has changed.

The first two scenarios that are under consideration are 3A1 and 3A2, regarding Somerville McGrath Boulevard Construction and the Chelsea Broadway project, which have similar purposes. Tom Bent, Inner Core Committee (City of Somerville), stated that MassDOT had held a project information meeting on February 24, 2024, and that MassDOT anticipated achieving 25 percent design by late 2024.

E. Lapoint stated that the Chelsea project being discussed in this scenario had only recently been picked up by the MPO and had had less notice of potentially being deprogrammed than Somerville or MassDOT. In addition, committee members would not be voting to take any actions at this time, although members may make a recommendation to limit the number of scenarios being presented to the MPO board for consideration.

The next scenario is Scenario 3B, which concerns the Cambridge Street Bridge Preservation project in Boston. J. Rowe called on Benjamin Sun, City of Boston, to discuss this project. The Cambridge Street Bridge is a city-owned structure, and the original vision was to have the project implemented by the city, and the preservation design was at 100 percent. The project was then programmed into the TIP and adjusted to comply with MassDOT design protocol and standards. The repair portion is 100 percent complete, and the design percentages (25–100 percent) are planned to be submitted through 2026, with the final submission in January 2027. The latest cost estimate was created two years ago, but has been recently calibrated by a similar project, coming to $16 million. 

Next was Scenario 3C, which involves the Beacham Street project in Everett and the Central and South Main Street project in Ipswich. E. Lapointe asked if anyone from Everett or Ipswich would like to speak.

Stephen Crane, Town of Ipswich, spoke about how the Central and South Main Street project addresses a complicated and important intersection. The design is at 25 percent and moving forward as planned.

Jay Monty, City of Everett, explained that Beacham Street is one of the critical freight corridors and is in critical need of reconstruction and repair, and that the 25 percent design plan is about to be finished. Rich Benevento, Tighe & Bond, also agreed that the design was well underway and in fact could come in ahead of schedule.

Next was Scenario 3D, which refers to Weston’s Route 30 Reconstruction Project, which is a municipal project that has some connections into Statewide Highway funded projects. Laurie Bent, Town of Weston, said that the project is at 25 percent design and residents and the Town of Weston Select Board are in favor of this project. Tom Cullen, Town of Weston, stated that the 75 percent design would be ready by the end of 2024. T. Cullen also spoke about changes to the scope of the project.

The next scenario was Scenario 3E, which referenced Intersection Improvements at Woburn Common. John Cashell, City of Woburn, spoke about how the project has been delayed due to other projects. The 25 percent design stage has not been reached yet, but J. Cashell strongly requested that this project not be deprogrammed and restated Woburn’s commitment to the project. R. Benevento discussed the project’s readiness and what planning steps the city has already taken to move the project forward, including several public hearings.

The last scenario is Scenario 3X, which references Salem’s Boston Street Project. Based on recommendations from the MPO board, this scenario is not possible because moving the timeline forward to 2029 would incur inflation costs that exceed the project’s funding. The project is already at 75 percent design. Deb Duhamel, City of Salem, stated that this project is a top priority for the City of Salem and the right-of-way work is planned to begin in October 2024, with completion projected to July 2025.

E. Lapointe then shared some pre-discussion points. The committee was asked to recommend one scenario, or two if a decision could not be made, and consider some projects for “probationary” status.

Discussion

Eric Bourassa, Metropolitan Area Planning Council, asked for clarification about Somerville’s McGrath Boulevard Construction in Scenario 3A2, specifically regarding a complication that decreasing the budget would hinder the delivery of the project on schedule.

E. Lapointe responded that a reduction in funding in FFY 2027 would mean the city could not do the level of work intended in FFY 2027. The reduction in funding could also hinder a federal discretionary grant application that was made by the city, citing the original funding number.

E. Bourassa asked for additional information on the City of Chelsea project that is part of scenarios 3A1 and 3A2. E. Lapointe stated this project was new and had not been discussed yet. It is a Complete Streets project for Broadway, originally in the FFYs 2021–25 TIP, now recommended for delay. J. Bechard stated that this project had caused some difficulties for MassDOT.

E. Bourassa asked what would happen if Scenario 3B was enacted, and the possible disruptions it could cause.

B. Sun stated that because the Cambridge Street Bridge is within a busy area, surrounded by many different structures, stations, and roads, the project was proposed as a TIP project to coordinate among the many entities that manage the various surroundings. B. Sun stated the impact of the project would be very significant across roadways and public transit.

John Alessi, Town of Arlington, stated he was uncomfortable with Scenarios 3A1 and 3A2 due to the potential impacts. J. Alessi asked what impacts these delayed projects would have on FFY 2029 programming and how it would affect new projects in the same fiscal year.

E. Lapointe stated that if projects were delayed to FFY 2029 there would not be adequate funding for new projects during that year. E. Lapointe also stated that if the funding issues could not be resolved this year, then these issues would extend into FFY 2030 and beyond.

E. Bourassa asked about Scenario 3D, and for specifics of the scope change.

L. Bent stated that some abutters are opposed to the Weston project, but many more are in support. L. Bent stated most of the changes were made to ensure compliance with MassDOT for shared paths and will require extra funding.

Leon Gaumond, Town of Weston, agreed that there was some opposition, but spoke on how important the shared path would be for the town and interregional connection.

E. Bourassa asked about Scenario 3E, specifically about lack of readiness, and noted a point in the shared documents that suggests the Intersection Improvement project might not be ready for FFY 2029.

R. Benevento responded that the project was not ready, and it could be pushed further out in the timeline to FFY 2029. R. Benevento stated that most of the preliminary work had been done.

E. Bourassa highlighted a point in Scenario 3E stating that the estimate for the Intersection Improvements at Woburn Common project was old and might not reflect an FFY 2029 estimate. E. Bourassa stated that this project seemed to be the least ready, and Scenario 3E might be the easiest to implement.

J. Bechard asked R. Benevento for clarification on the readiness of the Intersection Improvements at Woburn Common project.

R. Benevento responded that the current timeline was 25 percent design by November 2023 and 75 percent design by October 2025, and noted it was an aggressive schedule.

Trish Domigan, VHB, asked about Scenario 3X and the available funding for FFY 2026. T. Domigan stated that the City of Salem’s Boston Street project will be ready in FFY 2025 at the end of the calendar year and noted that work was being done to resolve the right-of-way issue. T. Domigan stated that deferring the project could impact the process. T. Domigan asked if the project was underway during FFY 2026 and how that would impact the FFY 2027 budget.

E. Lapointe responded with an explanation of the funding that was available, and where the funding had ended up being distributed, and why it was impacting these projects.

Dennis Giombetti, MetroWest Regional Collaborative (City of Framingham), asked about Scenario 3E, and the abutters that opposed the project. T. Cullen stated there were easements for those properties and that the problems did not seem insurmountable, citing a town center project where easements had been quickly attained.

J. Rowe then asked for the members to begin proposing preferred scenarios.

E. Bourassa suggested Scenario 3E. E. Lapointe restated the potential outcomes of this scenario, referencing the shared document. J. Alessi stated that a condition should be added to this recommendation, that the committee would revisit the Weston project based on the results of the town meeting vote and the changes to the project scope, which could inform a decision on the Argilla Road project in Ipswich.

T. Bent expressed support for Scenario 3E based on project readiness and lesser impacts. John Romano, MassDOT, agreed with the recommendation of Scenario 3E but stated that a revised cost estimate would almost certainly be much higher than the current estimate, which would have a large impact on the FFY 2029 TIP. J. Romano asked if it was possible for the project funding to be split between FFY 2029 and 2030.

E. Lapointe responded that there was precedent for originally funding the project in one fiscal year and funding the cost increase in the next fiscal year. E. Lapointe also stated that FFY 2030 would likely not have a funding surplus.

S. Crane stated that the Argilla Road project was in an active preliminary design stage.

J. Rowe referenced a point on the shared document that asked the committee to consider putting some projects on a “probationary” status, giving advance warning to municipalities that if projects do not advance in a notable way, those projects could be deprogrammed.

E. Bourassa stated that there would need to be some kind of measurement for project advancement.

D. Giombetti responded that the measurement could be specific goals that the project would need to achieve within a specific timeframe, to show advancement.

J. Alessi stated that clear goals and achievements would allow the committee to fairly assess projects.

J. Monty supported the idea of using MassDOT’s standard for reviews of projects for this assessment.

Eric Johnson, City of Framingham, stated he could pass this idea for assessment to the City’s Highway Division. E. Johnson also stated that according to federal standards, funding should be allocated based on the construction schedule.

J. Rowe then stated that based on the discussion, the committee would be recommending Scenario 3E and discussing ways to assess the progress of projects in a fair way going forward.

J. Alessi stated that another item to bring to the board was the cost increase of the Woburn project.

L. Diggins stated that the cost will go up for almost every project as FFY 2029 approaches.

R. Benevento asked the committee to also be mindful of how cost estimates become more refined with every design percentage submission.

E. Lapointe then asked if anyone would like to make statements about their TIP projects.

Zack McKeever, Metacomet Greenway Association, stated support for the Metacomet Greenway project to be considered in the 2025 project design pilot. Z. McKeever discussed the specifics of the project and the nonprofit organization that supports it. Richard McCarthy, Town of Norfolk, discussed the municipality collaboration that supports this project.

Sheila Page, Town of Lexington, advocated for the Route 4 to Interstate 95 interchange design. S. Page discussed the importance of this project and some of its scope.

4.    Presentation on Final Scenario Elements—Ethan Lapointe, MPO Staff

This item was not discussed in consideration of time.

5.    Adjourn

A motion to adjourn was made by the MAPC (E. Bourassa) and seconded by the Inner Core Committee (Town of Somerville) (T. Bent). The motion carried.


 

Attendance

Members

Representatives

and Alternates

City of Boston (Boston Transportation Department)

Jen Rowe

Inner Core Committee (Town of Somerville)

Tom Bent

Massachusetts Department of Transportation

John Bechard

Derek Krevat

Metropolitan Area Planning Council

Eric Bourassa

MetroWest Regional Collaborative (City of Framingham)

Dennis Giombetti

Minuteman Advisory Group on Interlocal Coordination (Town of Acton)

Kristen Guichard

Regional Transportation Advisory Council

Lenard Diggins

Town of Arlington

John Alessi

Town of Brookline

Erin Chute

 

Other Attendees

Affiliation

Felicia Webb

Cape Ann Transportation Authority

Andrew Valcovic

CHA Consulting, Inc.

John Morgan

CHA Consulting, Inc.

Ben Sun

City of Boston

Jay Monty

City of Everett

Sarkis Sarkisian

City of Framingham

Eric Johnson

City of Framingham

Jack Witthaus

City of Malden

Deb Duhamel

City of Salem

Sarah Cahill

City of Salem

Zeke Mermell

City of Watertown

John Cashell

City of Woburn

Chuck Adelsberger

Environmental Partners Group, Inc.

Bridget Myers

HSH

Mark Gravallese

HSH

Julia Wallerce

MAPC

Travis Pollack

MAPC

Mike Soter

Massachusetts House of Representatives

Sarah Lee

Massachusetts Port Authority

Benjamin Muller

MassDOT

Chris Klem

MassDOT

John Romano

MassDOT

Raissah Kouame

MassDOT

Sandy Johnston

MBTA

Anne and Ken McKee

Metacomet Greenway Association

Ryan Norton

Metacomet Greenway Association

Zack McKeever

Metacomet Greenway Association

Joy Glynn

MetroWest Regional Transit Authority

Cam Sullivan

MetroWest Regional Transit Authority

Jim Nee

MetroWest Regional Transit Authority

Tyler Terrasi

MetroWest Regional Transit Authority

Steven Olanoff

Three Rivers Interlocal Council

Rich Benevento

Tighe & Bond

Amy Sutherland

Town of Bellingham

Jesse Riedle

Town of Bellingham

Robert Walker

Town of Holliston

Sean Reese

Town of Holliston

Travis Ahern

Town of Holliston

Kristina Johnson

Town of Hudson

Pam Helinek

Town of Hudson

Tom Green

Town of Hudson

Frank Ventimiglia

Town of Ipswich

Stephen Crane

Town of Ipswich

Sheila Page

Town of Lexington

Ned Codd

Town of Newton

David Turi

Town of Norfolk

Richard McCarthy

Town of Norfolk

Gil Hilario

Town of North Attleboro

Marie Clarner

Town of North Attleboro

Addie Mae Weiss

Town of Sherborn

Heidi Doyle

Town of Sherborn

Jeremy Marsette

Town of Sherborn

Marian Neutra

Town of Sherborn

Sean Killeen

Town of Sherborn

Marcia Rasmussen

Town of Sudbury

Gary Riggott

Town of Walpole

Sandhya Malur

Town of Walpole

Jason Lavoie

Town of Weston

Laurie Bent

Town of Weston

Leon Gaumond

Town of Weston

Tom Cullen

Town of Weston

Paul Arvidson

Town of Wrentham

Trish Domigan

Vanasse Hangen Brustlin, Inc. 

Alfredo

Bob Cote

Jeffrey Plympton

Steve Schwarm

 

 

MPO Staff/Central Transportation Planning Staff

Tegin Teich, Executive Director

Abby Cutrumbes

Annette Demchur

Dave Hong

Erin Maguire

Ethan Lapointe

Judy Day

Srilekha Murthy

 


 

CIVIL RIGHTS NOTICE TO THE PUBLIC

Welcome. Bem Vinda. Bienvenido. Akeyi. 欢迎. 歡迎.

https://gallery.mailchimp.com/947cd3931665a4ac4033565ea/images/bb14d00b-7e0e-4330-ac91-85d387945d95.png

 

You are invited to participate in our transportation planning process, free from discrimination. The Boston Region Metropolitan Planning Organization (MPO) is committed to nondiscrimination in all activities and complies with Title VI of the Civil Rights Act of 1964, which prohibits discrimination on the basis of race, color, or national origin (including limited English proficiency). Related federal and state nondiscrimination laws prohibit discrimination on the basis of age, sex, disability, and additional protected characteristics.

 

For additional information or to file a civil rights complaint, visit www.bostonmpo.org/mpo_non_discrimination.

 

To request accommodations at meetings (such as assistive listening devices, materials in accessible formats and languages other than English, and interpreters in American Sign Language and other languages) or if you need this information in another language, please contact:

 

Boston Region MPO Title VI Specialist

10 Park Plaza, Suite 2150

Boston, MA 02116

Phone: 857.702.3700

Email: civilrights@ctps.org

 

For people with hearing or speaking difficulties, connect through the state MassRelay service, www.mass.gov/massrelay. Please allow at least five business days for your request to be fulfilled.