Executive Summary
Chapter 1: 3C Transportation Planning in the Boston Region
Chapter 2: The TIP Process
Chapter 3: Highway and Transit Programming
Chapter 4: Performance Analysis
Chapter 5: Determination of Air Quality Conformity
Chapter 6: Transportation Equity Performance Report
Prepared by
The Central Transportation Planning Staff:
Staff to the Boston Region Metropolitan Planning Organization
Directed by the Boston Region Metropolitan Planning Organization,
which is composed of the
Massachusetts Department of Transportation
Metropolitan Area Planning Council
Massachusetts Bay Transportation Authority
MBTA Advisory Board
Massachusetts Port Authority
Regional Transportation Advisory Council
City of Boston
City of Beverly
City of Everett
City of Framingham
City of Newton
City of Somerville
Town of Arlington
Town of Acton
Town of Brookline
Town of Burlington
Town of Hull
Town of Norwood
Town of Wrentham
Federal Highway Administration (nonvoting)
Federal Transit Administration (nonvoting)
This document was funded in part through grants from the US Department of Transportation. Its contents do not necessarily reflect the official views or policies of the US Department of Transportation.
CIVIL RIGHTS NOTICE TO THE PUBLIC
Welcome. Bem Vinda. Bienvenido. Akeyi. ę¬¢čæ. ę”čæ
You are invited to participate in our transportation planning process, free from discrimination. The Boston Region Metropolitan Planning Organization (MPO) is committed to nondiscrimination in all activities and complies with Title VI of the Civil Rights Act of 1964, which prohibits discrimination on the basis of race, color, or national origin (including limited English proficiency). Related federal and state nondiscrimination laws prohibit discrimination on the basis of age, sex, disability, and additional protected characteristics.
For additional information or to file a civil rights complaint, visit www.bostonmpo.org/mpo_non_discrimination.
To request this information in a different language or format, please contact:
Boston Region MPO Title VI Specialist
10 Park Plaza, Suite 2150
Boston, MA 02116
Phone: 857.702.3700
Email: civilrights@ctps.org
For people with hearing or speaking difficulties, connect through the state MassRelay service, www.mass.gov/massrelay. Please allow at least five business days for your request to be fulfilled.
Boston Region MPO
MPO Activities Group, Central Transportation Planning Staff
10 Park Plaza, Suite 2150
Boston, MA 02116
857.702.3700 (voice)
For people with hearing or speaking difficulties, connect through the state MassRelay service:
Relay Using TTY or Hearing Carry-over: 800.439.2370
Relay Using Voice Carry-over: 866.887.6619
Relay Using Text to Speech: 866.645.9870
For more information, including numbers for Spanish speakers, visit
https://www.mass.gov/massrelay
tip@ctps.org
The Boston Region Metropolitan Planning Organization’s (MPO) five-year capital Ā plan, the Federal Fiscal Years (FFYs) 2025ā29 Transportation Improvement Program (TIP), is the near-term investment program for the region’s transportation system. Guided by the Boston Region MPO’s vision, goals, and objectives, the TIP prioritizes investments that preserve the current transportation system in a state of good repair, provide safe and reliable transportation for all modes, enhance livability, support clean air and healthy communities, promote equity, resiliency, and sustainability, and improve mobility throughout the region. These investments fund roadway and intersection improvements, maintenance and expansion of the public transit system, shared-use path construction, first-and-last-mile improvements for users of active transportation, and major highway reconstruction.
The Boston Region MPO is guided by a 22-member board with representatives of state agencies, regional organizations, and municipalities. Its jurisdiction extends roughly from Boston north to Ipswich, south to Marshfield, and west to municipalities along Interstate 495. Each year, the MPO conducts a process to decide how to spend federal transportation funds for capital projects. The Central Transportation Planning Staff (CTPS), which is the staff to the MPO, manages the TIP development process.
MPO staff coordinates the evaluation of project funding requests, proposes programming of current and new projects based on anticipated funding levels, supports the MPO board in developing a draft TIP document, and facilitates a public review of the draft before the MPO board endorses the final document.
The complete TIP project list is available in Chapter 3 of this document and online at bostonmpo.org/tip. The TIP tables provide details of how funding is allocated to each programmed project and capital investment program. These tables are organized by federal fiscal year and are grouped by highway and transit programs.
The Highway Program of the TIP funds the priority transportation projects advanced by the Massachusetts Department of Transportation (MassDOT) and the cities and towns within the Boston region. The program is devoted primarily to preserving and modernizing the existing roadway network by reconstructing roadways, resurfacing highways, and replacing bridges.
In Massachusetts, Federal-Aid Highway Program funding, which is apportioned by the Federal Highway Administration and distributed by MassDOT, goes toward projects within various statewide programs, Grant Anticipation Notes (GANs) payments, and Regional Targets for the state’s MPOs. In the FFYs 2025ā29 TIP, roadway, bridge, and bicycle and pedestrian programs account for nearly $2.37 billion in funding to the Boston region. The Regional Target funding provided to the MPOs may be programmed for projects at the discretion of each MPO, whereas MassDOT has discretion to propose its recommended projects for statewide programs, such as those related to bridge repairs and interstate highway maintenance.
The Transit Program of the TIP provides funding for projects and programs that address the capital needs prioritized by the three transit authorities in the region: the Massachusetts Bay Transportation Authority (MBTA), the Cape Ann Transportation Authority (CATA), and the MetroWest Regional Transit Authority (MWRTA). The Transit Program is predominantly dedicated to achieving and maintaining a state of good repair for all assets throughout the transit system.
The FFYs 2025ā29 TIP includes $4.05 billion in transit investments for the transit authorities in the Boston MPO region to support state of good repair, modernize transit systems, and increase access to transit. Additionally, beginning in FFY 2025, the MPO will allocate $2.5 million of its annual Regional Target funds to its new Transit Transformation investment program. This program aims to build on the investments made through the Transit Program by using a portion of Highway Program funding to fulfill unmet transit project needs in the region. The MPO is funding transit projects in FFY 2025 using the $2.5 million set-aside and a surplus of funds available in that year, as detailed in Table ES-1. For the following years, the MPO has reserved $5 million for FFY 2026 and $6.5 million annually in FFYs 2027 through 2029 for the Transit Transformation investment program.
During FFYs 2025ā29, the Boston Region MPO plans to fund 69 projects with its Regional Target funding. In total, 32 new projects were added to the MPO’s Regional Target Program during this TIP cycle. These 32 projects included ten in the Community Connections investment program; eight in the Transit Transformation investment program; six in a project design funding pilot in FFY 2025; and two projects listed in the MPO’s Long-Range Transportation Plan (LRTP), Destination 2050, that will receive initial design funding in FFY 2026. Six roadway projects were newly funded for construction in the FFYs 2025ā29 TIP Regional Target Program, including two projects previously listed under MassDOT’s Statewide Highway Program. Details on these projects are available in Table ES-1.
Table ES-1
New Regional Target Projects Funded in the FFYs 2025ā29 TIP
Project Name |
Proponent |
MPO Investment Program |
FFYs of Funding |
Regional Target Dollars Programmed in FFYs 2025ā29Ā |
|||
---|---|---|---|---|---|---|---|
Arlington- Broadway Complete Streets Design |
Arlington |
Complete Streets |
2025 |
$1,395,000 |
|||
Arlington- Installation of 123 Bicycle Racks and Related Materials |
Arlington |
Community Connections |
2025 |
$90,878 |
|||
Arlington- Stratton School Improvements (Safe Routes to Schools) |
MassDOT |
Bicycle and Pedestrian |
2025 |
$2,133,673 |
|||
Boston- Bluebikes Station Replacement and Electrification, 12 Stations |
Boston |
Community Connections |
2025 |
$590,348 |
|||
Boston- Repurposing Single Space Parking Meter Poles for 1,600 Bicycle Racks |
Boston |
Community Connections |
2025 |
$379,470 |
|||
Brookline- Bluebikes State of Good Repair, 3 Stations and 62 Pedal Bikes |
Brookline |
Community Connections |
2025 |
$200,000 |
|||
Cambridge- Bluebikes State of Good Repair, 8 Stations and 65 Pedal Bikes |
Cambridge |
Community Connections |
2025 |
$385,456 |
|||
CATA- CATA Gloucester Facility Modernization |
CATA |
Transit Transformation |
2025 |
$1,293,000 |
|||
CATA- Fare Upgrades for ADA and Dial-A-Ride Customers |
CATA |
Transit Transformation |
2025 |
$65,000 |
|||
CATA- Vehicle Replacement (4 Vehicles) |
CATA |
Transit Transformation |
2025-26 |
$2,460,000 |
|||
Chelsea-Revere- Regional On-Demand Microtransit Pilot Project |
Chelsea |
Community Connections |
2025-28 |
$1,413,735 |
|||
Framingham- Chris Walsh Trail, Phase 2 [Design Only] |
Framingham |
Bicycle and Pedestrian |
2025 |
$850,000 |
|||
Holliston- Intersection Improvements at Route 16 and Whitney Street [Design Only] |
Holliston |
Intersection Improvements |
2025 |
$250,000 |
|||
Malden- Canal Street Bicycle Lanes |
Malden |
Community Connections |
2025 |
$81,250 |
|||
Marlborough- Reconstruction of Granger Boulevard [Design Only] |
Marlborough |
Complete Streets |
2025 |
$1,215,000 |
|||
MBTA- Central Square Station Accessibility Improvements (Cambridge) |
MBTA |
Transit Transformation |
2025 |
$5,000,000 |
|||
MBTA- Nubian Square Accessibility and Operational Improvements (Boston) |
MBTA |
Transit Transformation |
2025 |
$5,000,000 |
|||
MBTA- Systemwide Pedal and Park Modernization (Alewife, Ashmont, Braintree, Davis Square, Forest Hills, Malden Center, Nubian, Oak Grove, Route 128, Salem, South Station, Wollaston, and Wonderland) |
MBTA |
Transit Transformation |
2025 |
$2,500,000 |
|||
Medfordā Shared-Use Path Connection at the Route 28/Wellington Underpass |
MassDOT |
Bicycle and Pedestrian |
2025 |
$6,061,917 |
|||
MWRTA- Blandin Hub Equitable Redesign Initiative |
MWRTA |
Transit Transformation |
2025-26 |
$2,500,000 |
|||
MWRTA- Procurement of Three 29-foot Buses |
MWRTA |
Transit Transformation |
2025 |
$1,980,000 |
|||
Norfolk-Wrentham-Walpole- Shared-Use Path Installation (Metacomet Greenway) [Design Only] |
Norfolk |
Bicycle and Pedestrian |
2025 |
$1,550,000 |
|||
Revere- Bluebikes Expansion to Northern Strand (Salem Street at North Marshall Street) and Griswold Park |
Revere |
Community Connections |
2025 |
$169,000 |
|||
Scituate- Installation of 25 Bicycle Racks |
Scituate |
Community Connections |
2025 |
$22,800 |
|||
Sherborn- Reconstruction of Route 27 and Route 16 [Design Only] |
Sherborn |
Intersection Improvements |
2025 |
$900,000 |
|||
Somerville- Bluebikes State of Good Repair, 13 Stations |
Somerville |
Community Connections |
2025 |
$278,127 |
|||
Framingham- Design of Intersection Improvements at Route 126/135/MBTA and CSX Railroad |
Framingham |
Major Infrastructure |
2026 |
$1,400,000 |
|||
Lexington- Design of Safety Improvements at the Interstate 95 and Route 4/225 Interchange |
Lexington |
Major Infrastructure |
2026 |
$1,650,000 |
|||
Quincy- Intersection Improvements at Willard Street and Ricciuti Drive |
Quincy |
Intersection Improvements |
2026 |
$1,885,352 |
|||
Bellingham- Roadway Rehabilitation of Route 126 (Hartford Road), from 800 feet north of the I-495 NB off-ramp to Medway town line, including B-06-017 |
Bellingham |
Complete Streets |
2029-30 |
$8,340,000* |
|||
Ipswich- Argilla Road Roadway Reconstruction |
Ipswich |
Complete Streets |
2029-30 |
$3,000,000* |
|||
Sudbury-Framingham- Bike Path Construction of Bruce Freeman Rail Trail, from the Sudbury Diamond Railroad Crossing to Eaton Road West |
Sudbury |
Bicycle and Pedestrian |
2029-30 |
$4,263,000* |
|||
Total |
N/A |
N/A |
N/A |
$51,107,417 |
|
Note: Funding amounts in this table include both federal and non-federal funds, including matching funds.
* These projects are funded starting in FFY 2029 of the TIP, with further funding expected to be programmed in FFY 2030 of the FFYs 2026ā30 TIP.
ADA = Americans with Disabilities Act. CATA = Cape Ann Transportation Authority. FFY = federal fiscal year. MassDOT = Massachusetts Department of Transportation. MBTA = Massachusetts Bay Transportation Authority. MWRTA = MetroWest Regional Transit Authority. N/A = not applicable. NB = northbound. TIP = Transportation Improvement Program.
Source: Boston Region MPO.
The signing of the Bipartisan Infrastructure Law (BIL), on November 15, 2021, increased the amount of Regional Target funding available to the Boston Region MPO in the previous FFYs 2024ā28 TIP cycle by approximately nine percent from the funding levels in the FFYs 2023ā27 TIP. This funding level was sustained in the development of this FFYs 2025ā29 TIP.
The majority of the funding available for allocation by the MPO during the FFYs 2025ā29 TIP cycle was in the fifth and final year of the TIP, FFY 2029. During the development of the FFYs 2025ā29 TIP, the MPO had significant amounts of funding available to program in FFYs 2025, 2026, and 2029.Ā However, there were shortfalls of funding in FFYs 2027 and 2028 as a result of delayed programming of 14 projects.
Projects already programmed in the TIP to receive Regional Target funds could not be accelerated to utilize surplus funding in FFYs 2025 and 2026, so the MPO worked with MassDOT, the MBTA, MWRTA, and CATA to identify other projects that could be funded in those years. Jointly, these agencies presented more than 13 projects to the MPO for consideration, from which the MPO selected 11 projects for funding in the Transit Transformation program in FFYs 2025 and 2026:
The MPO also voted to fund two projects in FFY 2025 that were previously incorporated into MassDOT’s Statewide Highway Program:
Because many of these projects were identified later in the project evaluation life cycleāthat is, months after the regular cycle of project submissionsāscoring information is included in the TIP with some delay compared to other project line items. While these projects were identified too late in the TIP cycle to be quantitatively evaluated using the MPO’s scoring criteria, these projects align well qualitatively with many of the MPO’s goals, including enhancing bicycle and pedestrian safety and access, and expanding the accessibility of and maintaining a state of good repair for the region’s transit system. These projects may be scored using the MPO’s scoring criteria in a later TIP cycle.
In addition to selecting projects, several other key decisions were made by the MPO in the drafting of the FFYs 2025ā29 Regional Target Program:
Figure ES-1 shows how the Regional Target funding for FFYs 2025ā29 is distributed across the MPO’s investment programs. As the chart shows, the Boston Region MPO’s Regional Target Program is devoted primarily to enhancing mobility and safety for all travel modes through significant investments in Complete Streets projects. A large portion of the MPO’s funding also supports the modernization of key regional roadways and transit infrastructure through investments in Major Infrastructure and Transit Transformation projects. The MPO also elected to leave approximately $4.8 million unprogrammed.
Figure ES-1
FFYs 2025ā29 TIP Regional Target Funding by MPO Investment Program
FFY = federal fiscal year. MPO = metropolitan planning organization. TIP = Transportation Improvement Program.
Source: Boston Region MPO.
In addition to the distribution of funding across the MPO’s investment programs listed above, Table ES-2 further details the number of projects and the allocation of funds to each program in the FFYs 2025ā29 TIP. As noted in Figure ES-1, the MPO has programmed more than 99 percent of its available funding over five years. More details about every project funded through the MPO’s Regional Target Program are available in Chapter 3.
Table ES-2
FFYs 2025ā29 Boston Region MPO Regional Target Investment Summary
MPO Investment Program |
Number of Projects |
Regional Target Dollars Programmed |
Bicycle Network and Pedestrian Connections |
10 |
$69,238,369 |
Community Connections (allocated to projects) |
16 |
$5,154,222 |
Community Connections (not yet allocated to projects)* |
N/A |
$15,423,415 |
Complete Streets |
21 |
$334,236,398 |
Intersection Improvements |
8 |
$47,155,319 |
Major InfrastructureāRoadway |
4 |
$171,860,000 |
Transit Transformation (allocated to projects) |
11 |
$55,548,000 |
Transit Transformation (not yet allocated to projects) |
N/A |
$24,500,000 |
Unprogrammed |
N/A |
$4,812,578 |
Total |
70 |
$727,928,301 |
Note: Funding amounts in this table include both federal and non-federal funds, including matching funds.
* This figure includes $7 million in BikeShare Support funding starting in FFY 2026.
FFY = federal fiscal year. MPO = metropolitan planning organization. N/A = not applicable.
Source: Boston Region MPO.
When making decisions about which projects to fund, the MPO considers how the allocation of funds to each investment program compares to the funding goals outlined in the MPO’s current Long-Range Transportation Plan. The FFYs 2025ā29 TIP is the first to be informed by the LRTP Destination 2050, which was adopted by the MPO in 2023. The funding goals for investment programs set forth in the LRTP reflect the types of projects the MPO seeks to fund to help it achieve its goals and objectives for the region, from enhancing safety for all users to promoting mobility and accessibility across the region. More information on the MPO’s goals and objectives is available in Chapter 1, and a comparison between LRTP investment program goals and program funding levels in the FFYs 2025ā29 TIP is shown in Figure ES-2.
Figure ES-2
FFYs 2025ā29 TIP: Regional Target Funding Levels Relative to LRTP Investment Program Goals
FFY = federal fiscal year. LRTP = Long-Range Transportation Plan. TIP = Transportation Improvement Program.
Source: Boston Region MPO.
The investments made in the FFYs 2025ā29 TIP will be implemented in 48 cities and towns throughout the Boston region, ranging from dense inner core communities to developing suburbs further from the urban center. Figure ES-3 illustrates the distribution of Regional Target funding among the eight subregions within the Boston Region MPO’s jurisdiction, as defined by the Metropolitan Area Planning Council (MAPC). This figure also shows how the distribution of funds compares to key metrics for measuring the need for funding by subregion, including the percent of regional population, employment, and Federal-Aid roadway miles within each subregion.
Figure ES-3
FFYs 2025ā29 TIP: Regional Target Funding Levels Relative to Key Indicators
Note: Unprogrammed funds and funds held for the MPO’s Transit Transformation and Community Connections programs are not included in this figure.
FFY = federal fiscal year. MAGIC = Minuteman Advisory Group on Interlocal Coordination. MAPC = Metropolitan Area Planning Council. MetroWest = MetroWest Regional Collaborative. NSPC = North Suburban Planning Council. NSTF = North Shore Task Force. SSC = South Shore Coalition. SWAP = South West Advisory Committee. TIP = Transportation Improvement Program. TRIC = Three Rivers Interlocal Council.
Source: Boston Region MPO.
Additional information on the geographic distribution of Regional Target funding across the region, including a breakdown of funding by municipality, is included in Appendix D.
The TIP Highway Program was developed with the assumption that federal funding for the state would range between $818 million and $882 million annually over the next five years. These amounts include the funds that would be set aside initially by MassDOT as payments for the Accelerated Bridge Program and exclude required matching funds. The funding levels for the FFYs 2025ā29Ā TIP’s Highway Program represent an increase of approximately two percent over those in the FFYs 2024ā28 TIP.
The process of deciding how to use this federal funding in the Boston region follows several steps. First, MassDOT reserves funding for Grant Anticipation Notes (GANs) debt service payments for the Accelerated Bridge Program; annual GANs payments range between $122 million and $134 million annually over the first two years of this TIP. GANs payments for the Accelerated Bridge Program are expected to conclude in FFY 2026 but will pick back up in FFY 2032 (in future TIP cycles) to provide debt service payments for MassDOT’s Next Generation Bridge Program.
The remaining Federal-Aid Highway Program funds are budgeted to support state and regional (i.e., MPO) priorities. In the FFYs 2025ā29 TIP, $1.09 billion to $1.18 billion annually was available for programming statewide, including both federal dollars and the local match. MassDOT customarily provides the non-federal match (which can also be provided by other entities); thus, projects are typically funded with 80 percent federal dollars and 20 percent state dollars, depending on the funding program. Required matching funds for project design, capital purchases, and municipally-initiated operating service projects are often borne by the proponent of the project.
Next, MassDOT allocates funding across the following funding categories:
After accounting for GANs repayments, planning adjustments, and several other line items, MassDOT allocates roughly one-third of the total core formula funding apportioned by the Federal Highway Administration (FHWA) among the state’s 13 MPOs for programming. This discretionary funding for MPOs is suballocated by formula to determine the Regional Target amounts. The Boston Region MPO receives the largest portion of MPO funding in the state, with approximately 43 percent of Massachusetts’ Regional Target funds allocated to the region. MassDOT develops these targets in consultation with the Massachusetts Association of Regional Planning Agencies (MARPA). This TIP was programmed with the assumption that the Boston Region MPO will have between $125 million and $161 million annually for Regional Target amounts, which consist of federal funding and state funding for the local match.
Each MPO may decide how to prioritize its Regional Target funding. Given that the Regional Target funding is a subset of the Highway Program, the MPO typically programs the majority of funding for roadway projects; however, the MPO has flexed portions of its highway funding to the Transit Program for transit expansion projects and through its Transit Transformation and Community Connections programs. The TIP Highway Program details the projects that will receive Regional Target funding from the Boston Region MPO and statewide infrastructure projects within the Boston region. Details on these investments are outlined in Chapter 3.
The Federal Transit Administration (FTA) allocates the funds programmed in the TIP Transit Program according to formula. The three regional transit authorities in the Boston Region MPO area that are recipients of these funds are the MBTA, CATA, and MWRTA. The MBTA, with its extensive transit program and infrastructure, is the recipient of the preponderance of the region’s federal transit funds.
The current federal transportation legislation, the BIL, allocates funding to transit projects through the following formula programs:
When determining which projects to fund through the Regional Target funding process, MPO members collaborate with municipalities, state agencies, members of the public, advocacy groups, and other stakeholders. The MPO board uses evaluation criteria in its project selection process to help identify and prioritize projects that advance progress across the MPO’s six goal areas:
More information on the MPO’s goal areas can be found on the Destination 2050 website at bostonmpo.org/destination2050
Additionally, the MPO has established investment programs, which are designed to direct Regional Target funding towards MPO priority areas over the next 20 years, to help meet these goals. The investment programs are as follows:
Projects that the MPO selects to receive Regional Target funding through the TIP development process are included in one of the six investment programs listed above. More information on and descriptions of the MPO’s investment programs are available in Chapter 2.
The MPO incorporates performance-based planning and programming (PBPP) practices into its TIP development and other processes. These practices are designed to help direct MPO funds towards achieving specific and measurable outcomes for the transportation system. MPO investments directly relate to the PBPP framework and further the MPO’s goals and performance targets.Ā With the development of the FFYs 2025-29 TIP, the MPO leveraged funding availability across all federal fiscal years to program new projects to address transit system reliability, traffic safety for all users, NHS bridge condition, and other priorities. The MPO will continue to closely link its performance targets, investment decisions, and monitoring and evaluation activities. More information on PBPP is available in Chapter 4 and Appendix A (Table A-2).
The outreach process begins early in the federal fiscal year. Cities and towns designate TIP contacts and begin developing a list of priority projects to be considered for federal funding, and the MPO staff asks the staff of cities and towns in the region to identify their priority projects. MPO staff compiles the project funding requests into a Universe of Projects, which is a list of all Bicycle Network and Pedestrian Connections, Complete Streets, Intersection Improvements, and Major Infrastructure projects identified as potential candidates to receive funding through the TIP. In the development of the FFYs 2025ā29 TIP, staff also began tracking potential Community Connections projects in the Universe of Projects.
Transit Transformation projects are not typically listed in the Universe of Projects as priority projects. Rather, projects from regional transit authorities are typically identified during their annual program development process. During the fall of this TIP cycle, the MPO invited the regional transit authorities to submit applications for funding from the new Transit Transformation program.Ā The MPO also solicited additional transit projects later during the development of the FFYs 2025ā29 TIP to utilize funding availability in FFYs 2025 and 2026.
The Universe includes projects at varying levels of readiness, from those with significant engineering and design work complete to those still early in the conceptual or planning stage. MPO staff collects data on each project in the Universe so that the projects may be evaluated.
MPO staff evaluates projects based on how well they address the MPO’s goals. For MPO staff to conduct a complete project evaluation, Bicycle Network and Pedestrian Connections, Complete Streets, Intersection Improvements, and Major Infrastructure projects must have a functional design report or the project plans must include the level of detail defined in a functional design report. A functional design report is usually prepared when a project nears the 25 percent design stage. To complete an evaluation for projects under consideration through the MPO’s Community Connections program, project proponents must submit a completed application to MPO staff.
In response to significant cost increases in recent TIP cycles for projects already programmed for funding, the MPO board created a committee in the wake of the FFYs 2022ā26 TIP cycle to further explore the causes of project cost increases and devise MPO policy changes to support more reliable project delivery. The TIP Project Cost Ad Hoc Committee began its work in June 2021 and advanced a set of policy recommendations to the full MPO board in September 2021. These changes were formally adopted by the MPO on November 4, 2021, and were in effect for the development of the FFYs 2025ā29 TIP.
Among other changes, the MPO elected to codify its policy of requiring that project proponents submit 25 percent designs and obtain an updated cost estimate for their projects prior to being programmed in the TIP. While this new policy was in effect for the FFYs 2025ā29 TIP cycle, the MPO desired to keep this threshold flexible; the design progress demonstrated by proponents of selected projects since their application for funding in the FFYs 2024ā28 TIP indicated sufficient readiness for programming in the outer years of the FFYs 2025ā29 TIP.
The evaluation results for all projects are presented to the MPO board members for their consideration for programming in the TIP. Draft scores are shared directly with project proponents, at which point proponents are encouraged to review the scores and provide feedback so that MPO staff may make any warranted adjustments to arrive at appropriate final results. Once proponents review their scores, final scoring results are posted on the MPO’s website where MPO members, municipal officials, and members of the public may review them.
An important step toward TIP programming takes place midway through the TIP development cycle at a meetingāreferred to as TIP Readiness Dayāthat both MassDOT and MPO staff attend. At this meeting, MassDOT project managers provide updates about cost and schedule changes related to currently programmed projects. These cost and schedule changes must be taken into account as MPO staff helps the MPO board consider updates to the already programmed years of the TIP, as well as the addition of new projects in the outermost year of the TIP.
Among the other new policies advanced by the TIP Project Cost Ad Hoc Committee, the MPO board adopted a policy requiring proponents of projects that experienced a cost increase of 25 percent or more (for projects costing less than $10 million) or $2.5 million or more (for projects costing more than $10 million) to present to the MPO board on the reasons for these cost increases. The MPO would then compare these projectsāat the new costsāto other projects and consider this cost-effectiveness evaluation when deciding whether or not to fund the projects at the higher costs. These cost changes are most often revealed through conversations between MassDOT staff and MPO staff during TIP Readiness Day, making this new policy especially relevant at this stage of TIP development.
Using the evaluation results and information about project readiness (i.e., the extent to which a project is fully designed and ready for construction), MPO staff prepares a recommendation or a series of programming scenarios for how to program the Regional Target funding in the TIP. Other considerations, such as whether a project was included in the LRTP, addresses an identified transportation need, or promotes distribution of transportation investments across the region, are also incorporated into these programming scenarios. The staff recommendation is always financially constrainedāmeaning, subject to available funding. There was approximately $723 million of Regional Target funding available to the Boston Region MPO for FFYs 2025ā29. In this TIP cycle, the MPO board members discussed several scenarios for the Regional Target Program for highway projects and selected a preferred program in April 2024.
In addition to prioritizing the Regional Target funding, the MPO board reviews and endorses the statewide highway program that MassDOT recommends for programming. The board also reviews and endorses programming of funds for the MBTA’s, CATA’s, and MWRTA’s transit capital programs.
After selecting a preferred programming scenario, usually in April, the MPO board votes to release the draft TIP for a 21-30 day public review period. The comment period typically begins in late April, and during this time the MPO invites members of the public, municipal officials, and other stakeholders in the Boston region to review the proposed program and submit feedback. During the public review period, MPO staff hosts public meetings to discuss the draft TIP document and elicit additional comments.
After the public review period ends, the MPO board reviews all municipal and public comments and may change elements of the document or its programming. The MPO board then endorses the TIP and submits it to the Federal Highway Administration (FHWA) and the Federal Transit Administration for approval. MassDOT incorporates the MPO-endorsed TIP into the State Transportation Improvement Program (STIP). The FHWA, FTA, and United States Environmental Protection Agency review the STIP for certification by September 30, the close of the federal fiscal year.
Even after the TIP has been finalized, administrative modifications, amendments, and adjustments often must be introduced because of changes in project schedules, project costs, funding sources, or available revenues. This may necessitate reprogramming a project in a different funding year or programming additional funds for a project.
Notices of administrative modifications and amendments are posted on the MPO’s website. If an amendment is necessary, the MPO notifies affected municipalities, stakeholders, and members of the public via email. The MPO typically holds a 21-day public review period before taking final action on an amendment. In extraordinary circumstances, the MPO may vote to shorten the public review period to a minimum of 15 days. Administrative modifications and adjustments are minor and usually do not warrant a public review period.
Public engagement is an important aspect of the transportation planning process. Please visit bostonmpo.org for more information about the MPO, to view the entire TIP, and to submit your comments. You also may wish to sign up for email news updates and notices by visiting bostonmpo.org/subscribe and submitting your contact information. To request a copy of the TIP in accessible formats, please contact the MPO staff by any of the following means:
Mail: Boston Region MPO c/o CTPS MPO Activities Group, 10 Park Plaza, Suite 2150, Boston, MA 02116-3968
Telephone: 857.702.3700 (voice)
For people with hearing or speaking difficulties, connect through the state MassRelay service:
Email: publicinfo@ctps.org
The Executive Summary of the FFYs 2025ā29 TIP is also available as a translation:
Chapter 1ā3C Transportation Planning in the Boston Region
Decisions about how to allocate transportation funds in a metropolitan area are guided by information and ideas gathered from a broad group of people, including elected officials, municipal planners and engineers, transportation advocates, and interested residents. Metropolitan planning organizations (MPO) provide a forum for this decision-making process. Each metropolitan area in the United States with a population of 50,000 or more is required by federal legislation to establish an MPO, which decides how to spend federal transportation funds for capital projects and planning studies in the area.
The Boston Region Metropolitan Planning Organization performs this function for the 97 municipalities in eastern Massachusetts that comprise the MPO’s planning area. This MPO develops plans for funding transportation projects and programs; maintains transportation models and data resources to support studies, system performance monitoring, and air quality determinations; and conducts an ongoing public engagement process.
The federal government regulates the funding, planning, and operation of the surface transportation system through the federal transportation program, which was enacted into law through Titles 23 and 49 of the United States Code. Section 134 of Title 23 of the Federal Aid Highway Act, as amended, and Section 5303 of Title 49 of the Federal Transit Act, as amended.
The most recent reauthorization of the federal surface transportation law is the Bipartisan Infrastructure Law (BIL).The BIL sets policies related to metropolitan transportation planning and requires that all MPOs carry out a continuing, comprehensive, and cooperative (3C) transportation planning process.
The Boston Region MPO, which is responsible for carrying out the 3C planning process in the Boston region, has established the following objectives for the process:
More information about the federal, state, and regional guidance governing the transportation planning process, and about the regulatory framework in which the MPO operates can be found in Appendix E.
The Boston Region MPO’s planning area extends across 97 cities and towns from Boston north to Ipswich, south to Marshfield, and west to Interstate 495.
Figure 1-1 shows the map of the Boston Region MPO’s member municipalities.
Figure 1-1
Municipalities in the Boston Region
The MPO’s board comprises 22 voting members. Several state agencies, regional organizations, and the City of Boston are permanent voting members, while 12 municipalities are elected as voting members for three-year terms. Eight municipal members represent each of the eight subregions of the Boston region, and there are four at-large municipal seats. The Federal Highway Administration (FHWA) and Federal Transit Administration (FTA) participate on the MPO board as advisory (nonvoting) members. More details about the MPO’s permanent members can be found in Appendix F.
Figure 1-2 shows MPO membership and the organization of the Central Transportation Planning Staff, which serves as staff to the MPO.
Figure 1-2
Boston Region MPO Organizational Chart
The following paragraph is the MPO’s vision statement, as adopted in Destination 2050, the MPO’s current Long-Range Transportation Plan (LRTP), which was adopted in July 2023:
Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
The Boston Region Metropolitan Planning Organization envisions an equitable, pollution-free, and modern regional transportation system that gets people to their destinations safely, easily, and reliably, and that supports an inclusive, resilient, healthy, and economically vibrant Boston Region.
When developing this vision statement, the MPO members took into consideration the significant public input received during the drafting of the Needs Assessment for Destination 2050. This statement also reflects the desire to emphasize the maintenance and RES of the transportation system while supporting the MPO’s six core goals: Transportation Equity; Safety; Mobility and Reliability; Access and Connectivity; Resiliency; and Clean Air and Healthy Communities.
More information on the MPO’s vision, goals, and objectives for the transportation system is available in Figure 1-3.
Figure 1-3
Vision, Goals, and Objectives
GOALS | OBJECTIVES |
EQUITY | blank |
Facilitate an inclusive and transparent transportation-planning process and make investments that eliminate transportation-related disparities borne by people in disadvantaged communities. | ā¢ Facilitate an inclusive and transparent engagement process with a focus on involving people in disadvantaged communities.* ā¢ Ensure that people have meaningful opportunities to share needs and priorities in a way that influences MPO decisions. ā¢ Eliminate harmful environmental, health, and safety effects of the transportation system on people in disadvantaged communities. ā¢ Invest in high-quality transportation options in disadvantaged communities to fully meet residents’ transportation needs. Ā Ā Ā Ā Ā * Disadvantaged communities are those in which a significant portion of the population identifies as an MPO TE populationāpeople who identify as minority, have limited English proficiency, are 75 years old or older or 17 years old or younger, or have a disabilityāor has low income. |
SAFETY | blank |
Achieve zero transportation-related fatalities and serious injuries and improve safety for all users of the transportation system. | ā¢ Eliminate fatalities, injuries, and safety incidents experienced by people who walk, bike, roll, use assistive mobility devices, travel by car, or take transit. ā¢ Prioritize investments that improve safety for the most vulnerable roadway users: people who walk, bike, roll, or use assistive mobility devices. ā¢ Prioritize investments that eliminate disparities in safety outcomes for people in disadvantaged communities. |
MOBILITY AND RELIABILITY | blank |
Support easy and reliable movement of people and freight. | ā¢ Enable people and goods to travel reliably on the region’s transit and roadway networks. ā¢ Prioritize investments that address disparities in transit reliability and frequency for people in disadvantaged communities. ā¢ Reduce delay on the region’s roadway network, emphasizing solutions that reduce single-occupancy-vehicle trips, such as travel demand management. ā¢ Prioritize investments that reduce delay on the region’s transit network. ā¢ Support reliable, safe travel by keeping roadways, bridges, transit assets, and other infrastructure in a state of good repair, and prioritize these investments in disadvantaged communities. ā¢ Modernize transit systems and roadway facilities, including by incorporating new technology that supports the MPO’s goals, such as electric-vehicle technologies. |
ACCESS AND CONNECTIVITY | blank |
Provide transportation options and improve access to key destinations to support economic vitality and high quality of life. | ā¢ Improve multimodal access to jobs, affordable housing, essential services, education, logistics sites, open space, and other key destinations. ā¢ Prioritizing transportation investments that support the region’s and the Commonwealth’s goals for housing production, land use, and economic growth. ā¢ Increase people’s access to transit, biking, walking, and other non-single-occupancy-vehicle transportation options to expand their travel choices and opportunities.Ā Ā ā¢ Prioritize investments that improve access to high quality, frequent transportation options that enable people in disadvantaged communities to easily get where they want to go. ā¢ Close gaps in walking, biking, and transit networks and support interorganizational coordination for seamless travel. ā¢ Remove barriers to make it easy for people of all abilities to use the transportation system, regardless of whether they walk, bike, roll, use assistive mobility devices, or take transit. |
RESILIENCY | blank |
Provide transportation that supports sustainable environments and enables people to respond and adapt to climate change and other changing conditions. | ā¢ Prioritize investments to make the region’s roadway and transit infrastructure more resilient and responsive to current and future climate hazards, particularly within areas vulnerable to increased heat and precipitation, extreme storms, winter weather, and sea level rise. ā¢ Prioritize resiliency investments in disadvantaged communities and in areas that bear disproportionate climate and environmental burdens. ā¢ Prioritize investments in transportation resiliency that improve emergency access and protect evacuation routes. ā¢ Prioritize investments that include nature-based strategies such as low-impact design, pavement reduction, and landscape buffers to reduce runoff and negative impacts to water resources, open space, and environmentally sensitive areas. |
CLEAN AIR AND HEALTHY COMMUNITIES | blank |
Provide transportation free of greenhouse gas emissions and air pollutants and that supports good health. | ā¢ Reduce transportation-related greenhouse gases, other air pollutants, and growth in vehicle-miles traveled by encouraging people and goods to move by non-single-occupancy-vehicle modes. ā¢ Support transit vehicle electrification and use of electric vehicles throughout the transportation system to reduce greenhouse gases and other air pollutants. ā¢ Prioritize investments that address air pollution and environmental burdens experienced by disadvantaged and vulnerable communities. ā¢ Support public health through investments in transit and active transportation options and by improving access to outdoor space and healthcare. |
As part of its 3C process, the Boston Region MPO produces the Transportation Improvement Program (TIP) and the Unified Planning Work Program (UPWP) annually, and the Long-Range Transportation Plan every four years. These documents, referred to as certification documents, are required for the federal government to certify the MPO’s planning process. This federal certification is a prerequisite for the MPO to receive federal transportation funds. An inclusive public engagement process accompanies the development of each certification document.
The LRTP guides decision-making on investments that will be made in the Boston region’s transportation system over the next two decades. It defines an overarching vision of the future of transportation in the region, establishes goals and objectives that will lead to achieving that vision, and allocates projected revenue to transportation projects and programs consistent with the established goals and objectives.
Ā
Destination 2050, the current LRTP, was endorsed by the MPO board in July 2023 and went into effect on October 1, 2023.
The TIP is a multimodal program of transportation improvements, consistent with the LRTP, that describes and prioritizes transportation projects that are expected to be implemented during a five-year period. The TIP contains a financial plan that shows the current or proposed revenue sources for each project.
The types of transportation projects funded include major highway reconstruction and maintenance, arterial and intersection improvements, public transit expansion and maintenance, bicycle paths and facilities, improvements for pedestrians, and first- and last-mile connections to transit or other key destinations.
An MPO-endorsed TIP is incorporated into the State Transportation Improvement Program (STIP) for submission to the FHWA, FTA, United States Environmental Protection Agency, and the Massachusetts Department of Environmental Protection for approval. Investments programmed in the TIP and STIP are also reflected in Massachusetts Department of Transportation’s (MassDOT) Capital Investment Plan, which shows capital expenditures in the state over a five-year period.
The UPWP contains information about transportation planning studies that will be conducted by MPO staff during the course of a federal fiscal year, which runs from October 1 through September 30. The UPWP describes all of the supportive planning activities undertaken by the MPO staff, including data resources management, preparation of the federally required certification documents, and ongoing regional transportation planning assistance.
The UPWP often offers a means to study transportation projects and alternatives before advancing to further design, construction, and possible future programming through the TIP. The studies and work products programmed for funding through the UPWP are integrally related to other planning initiatives conducted by the Boston Region MPO, MassDOT, the Massachusetts Bay Transportation Authority, the Massachusetts Port Authority, the Metropolitan Area Planning Council, and municipalities in the Boston region.
Figure 1-4 depicts the relationship between the three certification documents and the MPO’s performance-based planning and programming process, which is a means to monitor progress towards the MPO’s goals and to evaluate the MPO’s approach to achieving those goals.
Figure 1-4
Relationship between the LRTP, TIP, UPWP,
and Performance-Based Planning Process
Transportation improvements are part of the solution to many critical regional, state, national, and even global problems, such as traffic congestion, air pollution, fatalities and injuries on roadways, climate change, and environmental injustice. Therefore, one of the most important decisions a metropolitan planning organization (MPO) faces is deciding how to allocate limited funds for transportation projects and programs. Because there is insufficient funding available for all projects that would address these problems, an MPO’s investment choices must be guided by policies that help identify the most viable and effective solutions.
The Boston Region MPO is guided by the policies in its Long-Range Transportation Plan (LRTP) and the MPO develops a Transportation Improvement Program (TIP) to prioritize the expenditure of federal funds on transportation projects. The MPO staff manages the development of both plans.
During the annual development process for the TIP, the MPO staff supports the MPO board by evaluating project funding requests from municipalities and state transportation agencies. The staff proposes a range of alternative scenarios for the programming of new and ongoing projects based on anticipated yearly funding levels, and work with the board to create a draft TIP document. The staff facilitates a public engagement process that affords the public an opportunity to comment on proposed projects and review the draft TIP before the MPO board endorses the final document.
The first step in allocating federal transportation funds is the passage by the United States Congress of a multiyear act that establishes a maximum level of federal transportation funding per federal fiscal year (FFY). The establishment of this level of funding is referred to as an authorization. The most recent authorization act, the Bipartisan Infrastructure Law (BIL), was signed into law on November 15, 2021. The BIL governed the development of the FFYs 2025ā29 TIP by establishing new formula funding levels, reauthorizing existing discretionary grant programs and creating new ones, and setting policy priorities. (More information on the impacts of the BIL on the development of the FFYs 2025ā29 TIP is available throughout this report, with specific guidance on new BIL Planning Emphasis Areas available in Appendix E.)
After the authorization level has been established, the United States Department of Transportation annually allocates funding among the states according to various federal formulas. This allocation is referred to as an apportionment. The annual apportionment rarely represents the actual amount of federal funds that are ultimately committed to a state because of federally imposed limitations on spending in a given fiscal year, referred to as the obligation authority. In Massachusetts, TIPs are developed based on the estimated obligation authority.
The TIP Highway Program was developed with the assumption that funding for Massachusetts from the Federal-Aid Highway Program would range between $818 million and $882 million annually over the next five years. These figures do not include matching funds provided for projects by the state or local entities. Projects are typically funded with 80 percent federal dollars and 20 percent state dollars, depending on the funding program, while costs for project design are often borne by the proponent of the project. With the addition of matching funds, approximately $1.09 billion to $1.18 billion was available statewide for projects in FFYs 2025ā29.
The process of determining the MPO’s share of this federal funding for the Boston region followed several steps. First, the Massachusetts Department of Transportation (MassDOT) reserved funding for Grant Anticipation Notes (GANs) debt service payments for the Accelerated Bridge Program; these payments are expected to conclude in FFY 2026. Then, the remaining Federal-Aid Highway Program funds were budgeted to support state and regional (i.e., MPO) priorities. The funding for regional priorities is referred to as Regional Target funds. Ā
The Regional Targetsare discretionary funds for MPOs, suballocated by formula to each metropolitan planning region. The Boston Region MPO receives about 43 percent of the total funds available statewide for Regional Targets. MassDOT developed the target formula for determining this distribution of funds in consultation with the Massachusetts Association of Regional Planning Agencies (MARPA).
Each MPO in the state can decide how to prioritize its Regional Target funding. The Boston Region MPO does this by engaging its 97 cities and towns in an annual TIP development process. Given that the Regional Target funding originates from the Federal-Aid Highway Program, the Boston Region MPO board typically programs the majority of its target funding on roadway projects; however, the MPO board has flexed portions of its TIP Highway Program funding to the TIP’s Transit Program, most notably when the MPO board provided funding in support of the Green Line Extension transit expansion project.
In addition, this FFYs 2025ā29 TIP includes an annual allotment of funding to the MPO’s Transit Transformation Program. This commitment to flex Federal-Aid Highway funds to transit projects on a yearly basis is an affirmation of the regional goals to support multimodal transportation options in a meaningful way. More information on the MPO’s investment strategy is discussed later in this chapter.
During the next five years, the Boston Region MPO’s total Regional Target funding will be approximately $727.9 million, an average of $145.6 million per year. As with the overall increase in funding for the Highway Program from the BIL, the MPO’s Regional Target funds increased 4.4 percent per year in the FFYs 2025ā29 TIP relative to the levels planned for in the development of the FFYs 2024ā28 TIP. The continued absence of GANs funding in FFY 2029 drove this increase. Funding levels in FFYs 2025 through 2028 remain unchanged from the previous TIP.
The Federal-Aid Highway Program dollars discussed in this chapter are delivered through several Federal Highway Administration (FHWA) funding programs, each of which has unique requirements. Table 2-1 lists the programs in the BIL that fund projects in the FFYs 2025ā29 TIP.
Table 2-1
Federal Highway Administration Programs Applicable to the FFYs 2025ā29 Transportation Improvement Program
Bipartisan Infrastructure Law Program |
Eligible Uses |
Bridge Formula Program (BFP) |
Efforts to replace, rehabilitate, preserve, protect, and construct highway bridges |
Carbon Reduction Program (CARBON) |
Projects that reduce transportation emissions or develop carbon reduction strategies |
Congestion Mitigation and Air Quality Improvement (CMAQ) |
A wide range of projects to reduce congestion and improve air quality in nonattainment and maintenance areas for ozone, carbon monoxide, and particulate matter |
Highway Safety Improvement Program (HSIP) |
Implementation of infrastructure-related highway safety improvements |
Metropolitan Planning |
Facilities that contribute to an intermodal transportation system, including intercity bus, pedestrian, and bicycle facilities |
National Electric Vehicle Infrastructure (NEVI) Program |
Projects that support the strategic deployment of electric vehicle (EV) charging infrastructure and establish an interconnected EV network to facilitate data collection, access, and reliability |
National Highway Freight Program (NHFP) |
Projects that improve the efficient movement of freight on the National Highway Freight Network |
National Highway Performance Program (NHPP) |
Improvements to interstate routes, major urban and rural arterials, connectors to major intermodal facilities, and the national defense network; replacement or rehabilitation of any public bridge; and resurfacing, restoring, and rehabilitating routes on the Interstate Highway System |
Promoting Resilient Operations for Transformative, Efficient, and Cost-saving Transportation Program (PROTECT) |
Resiliency improvements, including improvements to community resilience and evacuation routes, and at risk coastal infrastructure. Highway, transit, and port projects are also eligible |
Surface Transportation Block Grant Program (STBGP) |
A broad range of surface transportation capital needs, including roads; transit, sea, and airport access; and vanpool, bicycle, and pedestrian facilities |
Transportation Alternatives Program (TAP) |
A set-aside from the STBGP that funds the construction of infrastructure-related projects (for example, sidewalk, crossing, and on-road bicycle facility improvements) |
Source: Federal Highway Administration.
Federal aid for public transit authorities is allocated by formula to urbanized areas (UZAs). MassDOT is the recipient of this federal aid in the Boston MA-NH-RI UZA. In UZAs with populations greater than 200,000, such as the Boston MA-NH-RI UZA, the distribution formula factors in passenger-miles traveled, population density, and other factors associated with each transit provider. The three regional transit authorities (RTAs) in the Boston Region MPO area are the Massachusetts Bay Transportation Authority (MBTA), MetroWest Regional Transit Authority (MWRTA), and Cape Ann Transportation Authority (CATA). The MBTA, with its extensive transit program and infrastructure, is the recipient of the preponderance of federal transit funds in the region.
The Federal Transit Administration (FTA) distributes funding to transit agencies through several different programs. As previously noted, the MPO also converts some of its FHWA funding to FTA to support transit investments. Table 2-2 shows FTA programs in the BIL that support transit investments in the FFYs 2025ā29 TIP.
Table 2-2
Federal Transit Administration Programs Applicable to the FFYs 2025ā29 Transportation Improvement Program
Bipartisan Infrastructure Law Program |
Eligible Uses |
Urbanized Area Formula Grants (Section 5307) |
Transit capital and operating assistance in urbanized areas |
Fixed Guideway/Bus (Section 5337) |
Replacement, rehabilitation, and other state-of-good-repair capital projects |
Bus and Bus Facilities (Section 5339) |
Capital projects to replace, rehabilitate, and purchase buses and related equipment, and to construct bus-related facilities |
Enhanced Mobility of Seniors and Individuals with Disabilities (Section 5310) |
Capital expenses that support transportation to meet the special needs of older adults and persons with disabilities |
Fixed-Guideway Capital Investment Grants (Section 5309) |
Grants for new and expanded rail, bus rapid transit, and ferry systems that reflect local priorities to improve transportation options in key corridors |
Source: Federal Transit Administration.
As mentioned previously, each MPO in the state can decide how to prioritize the Regional Target funding it receives through the processes established by FHWA and MassDOT. The Boston Region MPO’s LRTP defines the investment framework that informs the specific investment decisions made in the TIP by establishing
The MPO’s goals and objectives provide the foundation for the evaluation criteria that the MPO board uses when selecting transportation projects to be funded with Regional Target dollars. MPO staff compares candidate projects’ characteristics to these criteria to evaluate whether individual projects can help the MPO advance its various goals. The criteria used to select projects for this TIP are based on the MPO’s goals and objectives, adopted as part of Destination 2050, which is the LRTP the MPO endorsed in July 2023. Chapter 1 lists these goals and objectives.
In Destination 2050 and the prior LRTP, Destination 2040, the MPO strengthened the link between its spending and improvements to transportation performance by revising its investment programs to include a broader range of prospective projects. These investment programs focus on specific types of projects that the MPO expects will help achieve its goals and objectives for the transportation system. The MPO created these programs to give municipalities the confidence that if they design these types of projects, the MPO will be willing to fund them through the TIP:
The MPO has taken a clear stance that investing in transit is central to improving the region’s broader transportation system. The MPO established the Transit Modernization program in Destination 2040, which became the Transit Transformation program in Destination 2050. The Transit Transformation program represents a significant shift in the MPO’s investment strategy as funding will be allocated to transit projects on an annual basis. In prior years, the MPO only funded transit projects on a one-off basis when funding was requested for specific projects in the region. By creating the programming infrastructure to reallocate Regional Target highway funds to transit projects annually, the Boston Region MPO has established itself as a leader among MPOs nationally by crafting an investment strategy that is truly multimodal. Ā Ā Ā Ā Ā
The MPO funded multiple Transit Transformation projects in FFY 2025 and FFY 2026 to make use of funding surpluses. The MPO has also continued to reserve funding in the amount of $5 million in FFY 2026 and $6.5 million in each following fiscal year for future allocation. The MPO will continue to work with municipalities and transit providers in the region to identify transit needs and determine the most effective use of this funding; the FFYs 2025ā29 TIP invested in five projects from regional transit authorities, a first for the Transit Transformation program. In addition to two other MBTA projects in Central Square in Cambridge and Boston’s Roxbury neighborhood, a systemwide Pedal-and-Park modernization project spanning 13 MBTA stations in nine municipalities was funded by the MPO in FFY 2025.
As with the original Transit Modernization program, the MPO also will continue to work with municipalities to develop and fund transit improvements as part of larger projects through the Complete Streets investment program. In Destination 2040, the MPO added dedicated bus lanes and climate resiliency measures as eligible projects.
In this FFYs 2025ā29 TIP, the MPO funded 10 other Community Connections projects in addition to the 34 projects funded in the previous four TIP cycles. Funding for the Community Connections, Transit Transformation, and Bikeshare Support Programs continues to be reserved in FFYs 2026ā29 for allocation in future TIP cycles.
More information on the projects selected for funding in each of the MPO’s investment programs can be found in Chapter 3.
Since 2015, the MPO has chosen to prioritize lower-cost, smaller-scale projects in most investment areas, while limiting larger projects to the Major Infrastructure program. Early in the development of the FFYs 2022ā26 TIP, the MPO reassessed its definition of Major Infrastructure projects, adopting a new definition through sequential votes on August 20, 2020, and October 1, 2020. This revised definition persists in the FFYs 2025ā29 TIP. The MPO previously defined Major Infrastructure projects as those that cost more than $20 million or that add capacity to the transportation network. The MPO’s revised definition classifies Major Infrastructure projects as follows:
Under the MPO’s prior Major Infrastructure definition, the relatively low-cost threshold caused several large-scale Complete Streets projects to be classified as Major Infrastructure projects although they were local in nature. The changes outlined above are intended to focus the Major Infrastructure investment program on those projects that are of significant scale or that are truly important for the broader region. This allows the MPO to better compare projects when conducting project evaluations.
Because the MPO considers the five-year distribution of TIP funds across its investment programs relative to the goals set forth in the LRTP (as shown in Figure 2-1), properly categorizing projects is a critical component of the MPO’s decision-making process. Funding allocation goals are some of the LRTP-based guidelines the MPO employs to ensure limited Regional Target funding is programmed in ways that best achieve the MPO’s goals for transportation in the region. Ā Ā Ā Ā Ā
Figure 2-1
Destination 2050 Funding Goals by MPO Investment Program
Source: Boston Region MPO.
The MPO requires that project proponents submit 25 percent designs and obtain an updated cost estimate for their project prior to being programmed in the TIP. This standard was set by the MPO as part of a multi-pronged effort to reduce the prevalence of cost increases and delays for projects that have already been selected for funding in the TIP.
MassDOT and the MBTA each update their rolling five-year Capital Investment Plans (CIP) on an annual basis. MassDOT’s CIP identifies priority roadway, bridge, and statewide infrastructure projects for the five MassDOT divisions and includes funding for specific transit projects such as the South Coast Rail. The MBTA’s CIP outlines the agency’s five-year investment strategy for transit projects in its service area. Both CIP processes use a similar framework that prioritizes funding according to statewide strategic goals for the transportation system. Reliability is the top priority for MassDOT and the MBTA, followed by modernization and then expansion. Both agencies have created investment programs for their respective CIPs that relate to these strategic goals and allocate funding to these programs in ways that emphasize their priority. These goals and investment programs are as follows:
The MPO applies its investment framework when developing the TIP. The MPO board’s process for selecting projects to receive Regional Target funding relies on evaluation criteria to help identify and prioritize projects that advance the MPO’s goals. The criteria are based on the MPO’s goals and objectives outlined in the LRTP. All projects are required to show consistency with the LRTP and other statewide and regional plans. Other considerations include the readiness of a project for construction and municipal support for the project. Background information about the TIP project evaluation process is presented in Appendix A.
Following the adoption of Destination 2050 in July 2023, the MPO revised the TIP evaluation criteria to better align with the MPO’s updated goals, objectives, and investment programs, including a new resilience goal area. These new criteria were employed during the project selection process for the FFYs 2025ā29 TIP. The final criteria were informed by robust public engagement conducted during the development of Destination 2050, and developed through an update process that engaged MPO members, staff, and external stakeholders. The most significant update to the criteria for the FFYs 2025ā29 TIP was the development of new and broader resilience evaluation metrics to align with the resilience goal area in Destination 2050 and elevate resilience to equal consideration in project prioritization alongside other goal-focused TIP criteria. To develop these metrics, staff held a stakeholder workshop that engaged environmental advocates, community-based organizations, municipalities, and environmental agencies, and also distributed a survey and held one-on-one meetings with stakeholders. In addition, staff used data from this engagement to create a Climate Resilience Guidance for Planners StoryMap to highlight strategies and resources for municipalities to address resilience and meet new TIP criteria in project design. The outcomes of this process are discussed further in the Project Evaluation section on the following pages.
More information on these criteria is available in the Project Evaluation section of this chapter, as well as in Appendix A.
The TIP development process begins early in the federal fiscal year when cities and towns in the region designate staff as TIP contacts and begin developing a list of priority projects to be considered for federal funding. Each fall, the MPO staff asks these TIP contacts to identify their city or town’s priority projects and then MPO staff elicits input from interested parties and members of the general public.
These discussions on municipalities’ priority projects mark the start of a robust dialogue between MPO staff and project proponents that continues through the duration of the TIP cycle. In November of 2023, MPO staff held two virtual workshops for municipalities in the region to develop an understanding of the TIP process. MPO staff also held several one-on-one virtual office hours throughout the fall and winter for proponents to ask more detailed questions about advancing specific projects for funding.
Once project proponents have decided to pursue federal funding, they must begin the formal project initiation process. All new Bicycle Network and Pedestrian Connections, Complete Streets, Intersection Improvements, and Major Infrastructure projects must be initiated with the MassDOT Highway Division before they can be considered for programming in the TIP. These include projects seeking design funding as well as construction funds. MassDOT details this process on its project initiation webpage, mass.gov/info-details/massdot-highway-initiating-a-project. To be considered for programming, proponents of Community Connections, Bikeshare Support, and Transit Transformation projects must apply for funding directly to MPO staff, as these projects do not require initiation with MassDOT.
The MPO staff compiles project funding requests for projects into a Universe of Projects list, which consists of all identified projects being advanced for possible funding in a future TIP cycle. The Universe includes projects that are at advanced stages of project design, those that are undergoing preliminary engineering and design, and projects still in the conceptual planning stage. Those projects that are active municipal priorities and that are feasibly ready to be programmed in the current TIP cycle continue forward into the MPO’s project evaluation process if an application is received. Projects that are not ready for programming remain in the Universe for consideration in future TIP cycles. In developing the FFYs 2025ā29 TIP, MPO staff began incorporating Community Connections projects into the Universe. Ā Ā Ā Ā
The MPO staff uses its project evaluation criteria to logically and transparently evaluate and select projects for programming in the TIP that advance the MPO’s vision for transportation in the region. This process favors projects that support the following goals:
As noted previously, the MPO undertook a process of revising the TIP evaluation criteria prior to the launch of the FFYs 2025ā29 TIP to enhance the alignment between the TIP project selection process and the MPO’s updated goals, objectives, and investment programs outlined in Destination 2050. In terms of the overall structure of the criteria, this process resulted in the following outcomes:
In addition to these broader structural changes, several updates were made to individual criteria to better accomplish the MPO’s goals in the LRTP:Ā Ā Ā Ā Ā Ā Ā Ā Ā
Several other changes were made to the project evaluation criteria, which are detailed in Appendix A. The point distributions by MPO investment program and LRTP goal area are also available in Figure 2-4. Projects scored using both sets of criteria are programmed in each of these six investment programs in the FFYs 2025ā29 TIP, so both sets of criteria are referenced throughout this document.
Ā Ā Ā Ā
Prior to the FFYs 2025ā29 TIP cycle, the MPO also undertook a parallel process to update its evaluation criteria for the smaller-scale, first- and last-mile projects considered for funding through the Community Connections Program. These adjustments were based on the lessons learned from the past four years of administering the program. In these revisions, MPO staff created a more focused set of criteria that better aligned with the types of projects pursuing funding through this program.
Revisions to the Community Connections criteria addressed the discrepancies between projects that serve a limited set of locations, such as small-scale purchases of bicycle racks or transit signal priority installations versus projects that serve larger areas, such as on-demand microtransit. The original criteria favored projects that had broad service areas. The new criteria are specific to each project type: Bicycle Lanes, Bicycle Racks, Bikeshare (Expansion and Replacement), Microtransit Pilots, and Wayfinding Signage.2 These adjustments result in more balanced scores to better reflected the goals of the program.
More information on the scoring areas for these criteria is available in Figures 2-2 and 2-3, and all criteria are available in Appendix A. For this TIP, Community Connection projects were scored using both the old and new criteria for, so both sets of criteria are referenced throughout this document.
Figure 2-2
TIP Project Evaluation Criteria: Point Distributions by Community Connections Project Type
Source: Boston Region MPO.
Figure 2-3
TIP Project Evaluation Criteria: Point Distributions by Project Type
(All Investment Programs except Community Connections)
LRTP = Long-Range Transportation Plan.
Source: Boston Region MPO.
In order for the MPO staff to conduct a complete project evaluation, each project proponent must provide enough information so that staff can meaningfully apply the evaluation criteria. Bicycle Network and Pedestrian Connections, Complete Streets, Intersection Improvements, and Major Infrastructure projects must have submitted 25 percent design plans to MassDOT, or its plans must include the level of detail defined in a functional design report. (See MassDOT’s Project Development and Design Guide for information about the contents of a functional design report. This guide is available at mass.gov/lists/design-guides-and-manuals.)
Projects seeking design funding are required to provide a written scope or vision for development consistent with the information provided in a MassDOT Project Initiation Form. For Community Connections projects, proponents must submit a complete application to the MPO, including required supporting documentation such as budget sheets, letters of support from partner entities, and work estimates. Transit Transformation project applicants must submit an application with all relevant forms, budget sheets, and designs based on the scope of work proposed.
After MPO staff has completed an initial round of project scoring, draft scores are distributed to project proponents for their review. The MPO’s goal is to assess all projects fairly and accurately, making this review a critical component of the TIP process. Proponents are encouraged to submit feedback to MPO staff on their projects’ scores if they believe any criteria have been applied inaccurately. Proponents are also encouraged to submit additional supporting documentation on their projects if doing so would help clarify or correct any elements of the draft scoring. MPO staff takes all proponent feedback into consideration and makes any warranted adjustments to project scores before considering the evaluation process final and preparing the scores for presentation to the MPO.
For more details about the criteria used to score projects and project evaluation results for projects considered for programming in this TIP, see Appendix A.
On TIP Readiness Day, MPO staff meets with members of the MassDOT Highway Division and Office of Transportation Planning to review cost and schedule changes related to currently programmed projects, which are undergoing design review, permitting, and right-of-way acquisition. The MPO board then considers these updated project construction costs and changes to the expected dates for construction advertisement when making decisions about changes to TIP programming. These changes have an impact on the ability of the MPO to program its target funds for new projects in the five-year TIP.
Between the development of the FFYs 2021ā25 TIP and the FFYs 2022ā26 TIP, more than half of the projects programmed by the MPO experienced cost increases, many of which represented significant increases in percentage terms or in absolute cost. These changes placed severe limitations on the MPO’s ability to consider new projects for funding during the FFYs 2022ā26 TIP cycle. As a partner to MassDOT’s Highway Division and Office of Transportation Planning, the MPO recognizes its role in supporting the on-time and on-budget delivery of projects by proponents. For this reason, the MPO board created a committee in the wake of the FFYs 2022ā26 TIP cycle to further explore the causes of project cost increases and devise MPO policy changes to support more reliable project delivery by all parties.
The TIP Project Cost Ad Hoc Committee began its work in June 2021 and advanced a set of policy recommendations to the full MPO board in September 2021. These changes were formally adopted by the MPO on November 4, 2021, and went into effect for the development of the FFYs 2023ā27 TIP. In addition to the requirement that project proponents submit 25 percent design plans and obtain an updated cost estimate for their project prior to obtaining funding in the TIP, the committee’s work resulted in several other policy changes. Most notably, the MPO board adopted a policy that proponents of any projects that experienced a cost increase of 25 percent or greater (for projects less than $10 million in cost) or of greater than $2.5 million (for projects more than $10 million in cost) would be required to present to the MPO board on the reasons for these cost increases. The MPO would then compare this projectāat its new costāto other projects based on a cost-effectiveness evaluation before deciding whether or not to fund the project at its higher cost. These cost changes are most often revealed through conversations between MassDOT staff and MPO staff during TIP Readiness Day, making this policy especially relevant at this stage of TIP development.
More information on the work of the TIP Project Cost Ad Hoc Committee is available in Chapter 3.
Using the evaluation scores and information gathered about project readiness (when a project likely would be fully designed and ready for advertisement) and cost, staff prepares possible TIP project programming scenarios for the MPO’s consideration. When developing these scenarios, MPO staff also considers whether a project was programmed in the LRTP, LRTP-based guidelines for allocating funds to different programs or project types, the distribution of investments across the region, and availability of sufficient funding. The MPO staff gathers feedback from board members, project proponents, and the public to inform a final staff recommendation, which is then presented to the MPO for approval before it is included in the draft TIP for public review.
In the FFYs 2025ā29 TIP, the MPO selected and funded 23 new projects for implementation during this TIP cycle, including the following:
In addition to these projects, the MPO also selected 9 new projects to be funded for design work, with construction anticipated in future TIP development cycles.Ā These projects included the following:
In total, the MPO allocated more than $51 million in this TIP cycle to projects not previously funded in the Regional Target program. More information on the projects funded in the FFYs 2025ā29 TIP is available in Chapter 3.
As discussed above, the selection of transit, bridge, and statewide infrastructure projects for programming in the TIP draws primarily from the CIPs produced by MassDOT and the MBTA. These agencies evaluate projects for inclusion in CIP programs using criteria established by the independent Project Selection Advisory Council (PSAC). The following criteria are from the PSAC process guide project evaluation:
Projects that receive the highest priority are those that meet each agency’s goals for maintaining and improving the overall condition and reliability of the system; modernizing the system to make it safer and more accessible and to accommodate growth; and expanding and diversifying transportation options for communities. These project-prioritization processes may also reflect other planning initiatives, such as Focus40, the MBTA’s 25-year investment plan, or MassDOT’s modal plans. More information on regulatory and planning guidance governing TIP project prioritization is available in Appendix E.
Once project prioritization is complete, programming decisions are made based on these evaluations and information regarding project readiness, program sizing, and existing asset management plans.
As discussed previously, the transit element of the TIP also includes the Federal-Aid Programs of the other two RTAs in the region, CATA and MWRTA. Once selection processes are complete for all four agencies, these agencies submit their lists of bridge and roadway projects, bicycle and pedestrian improvements, statewide infrastructure items, and transit capital projects to the MPO for review.
The MPO board considers the project evaluation results and staff recommendation when prioritizing projects for Regional Target funding. The board also considers public comments, the regional importance of projects, and other factors. In addition to prioritizing the Regional Target funding, the MPO board reviews MassDOT’s proposed statewide highway programming and the proposed capital programs for the MBTA, CATA, and MWRTA before voting to release a draft TIP for public review.
The MPO board votes to release the draft document for public review and invites members of the public, municipal and elected officials, and other stakeholders in the Boston region to review the proposed TIP. The MPO staff hosts outreach events during the public review period to elicit comments on the draft document. (See Appendix C for a full list of public comments submitted on the draft TIP.)
After the public review period ends, the MPO staff and board review all public comments, and the board may change the programming or the document as appropriate before endorsing the TIP. MassDOT staff incorporates the MPO-endorsed TIP into the State Transportation Improvement Program (STIP) and submits it to the FHWA and FTA for approval. The FHWA, FTA, and US Environmental Protection Agency review the STIP and certify it by September 30, the end of the federal fiscal year.
The TIP is a dynamic program that may be amended and adjusted throughout the year. Administrative modifications and amendments are often introduced because of changes in project status (advertisement readiness), project cost, project design scope, or available revenue. An amendment is a revision that requires public review and a demonstration of fiscal constraint.
Consistent with federal guidelines, the Boston Region MPO must release an amendment if there is (1) a change in project cost of $500,000 or more for projects valued at $5 million or less, or (2) a change of 10 percent or more of the project cost for projects valued greater than $5 million. TIP amendments are also released if there is a proposal to add or remove a project from the TIP or if the programming year of a project is changed. Cost changes that are less than the above threshold amounts may be considered in the form of administrative modifications or adjustments, which must still undergo MPO board action for approval. Administrative modifications or adjustments are also undertaken in the event that a project’s funding source changes. Although a public review period is not required for administrative modifications or adjustments, one may be offered at the MPO board’s discretion.
Regardless of the nature of an amendment, all proposed TIP amendments are presented in a public setting at an MPO meeting, and details are posted on the MPO’s website, bostonmpo.org. Public notices are distributed through the MPO’s email contact list, which members of the public may join by signing up on the MPO’s website. Municipal staff who are TIP contacts at the affected municipalities and the public are notified of pending amendments at the start of an amendment’s public review period.
A history of TIP Amendments can be found at https://www.ctps.org/tip.
Notices of draft TIP amendments include a summary of the amendment’s contents, dates of the public review period, contact information for submitting a comment to the MPO, and the date, time, and location that the MPO will vote on that amendment. Municipal representatives and members of the public are invited to submit written or oral testimony at the MPO meetings at which amendments are discussed or voted upon.
The MPO typically holds a 21-day public review period before taking final action on an amendment. In extraordinary circumstances, the MPO may vote to shorten the public review period to a minimum of 15 days. These circumstances are detailed in the MPO’s Public Engagement Plan.
The MPO’s website is the best place to find current information about the TIP. All changes to the draft TIP and changes to the endorsed TIP, such as amendments and modifications that have been approved by the MPO, are available on the TIP webpage, bostonmpo.org/tip.
Comments or questions about the draft TIP materials may be submitted directly to the MPO staff via the website, email, or US mail, or voiced at MPO meetings and other public MPO events.
1 More information on the Multi-Family Zoning Requirement for MBTA Communities (Section 3A of MGL c. 40A) can be found at https://www.mass.gov/info-details/multi-family-zoning-requirement-for-mbta-communities.
2 Transit signal priority and bus lane projects were incorporated under the Transit Transformation scoring criteria. They were previously under the Community Connections criteria.
The Transportation Improvement Program (TIP) tables included in this chapter present a listing of all the projects and programs funded with federal highway and transit aid in the Boston region during federal fiscal years (FFYs) 2025ā29. These funding tables are also included as part of the State Transportation Improvement Program (STIP).
Table 3-1 presents a summary of the Boston Region Metropolitan Planning Organization’s (MPO) share of Regional Target funds from the Federal-Aid Highway Program. The allocation of these funds is constrained by projections of available federal aid. As shown in Table 3-1, the MPO has programmed much of the available discretionary funds within the limits of projected funding for highway funding programs. As such, the FFYs 2025ā29 TIP Regional Target Program complies with financial constraint requirements.
Table 3-1
Boston Region MPO Regional Target Program
Funding Summary
|
FFY 2025 |
FFY 2026 |
FFY 2027 |
FFY 2028 |
FFY 2029 |
Total |
Regional Target Obligation Authority |
$128,427,689 |
$125,285,687 |
$155,132,142 |
$158,052,175 |
$161,030,608 |
$727,928,301 |
Regional Target Funds Programmed |
$126,277,235 |
$124,569,057 |
$154,195,127 |
$157,830,836 |
$160,243,467 |
$723,115,723 |
Regional Target Funds Unprogrammed |
$2,150,454 |
$716,630 |
$937,015 |
$221,339 |
$787,141 |
$4,812,578 |
Source: Boston Region MPO.
As discussed in Chapter 2, the signing of the Bipartisan Infrastructure Law (BIL), on November 15, 2021, increased the amount of Regional Target funding available to the Boston Region MPO in the previous FFYs 2024ā28 TIP cycle by approximately nine percent from the funding levels in the FFYs 2023ā27 TIP. This funding level was sustained in the development of this FFYs 2025ā29 TIP. The projects selected by the MPO for funding for the first time in the FFYs 2025ā29 TIP are listed in Table 3-2.
During the development of the FFYs 2025ā29 TIP, the MPO had significant amounts of funding available to program in FFYs 2025, 2026, and 2029.Ā However, there were significant shortfalls of funding in 2027 and 2028 as a result of delayed programming of 14 projects.
Projects already programmed in the TIP to receive Regional Target funds could not be accelerated, so the MPO worked with the Massachusetts Department of Transportation (MassDOT), the Massachusetts Bay Transportation Authority (MBTA), MetroWest Regional Transit Authority (MWRTA), and Cape Ann Transportation Authority (CATA) to identify other projects that could be funded in FFYs 2025 and 2026. Jointly, these agencies presented more than 13 projects to the MPO for consideration, from which the MPO selected 11 projects for funding in the Transit Transformation program in FFYs 2025 and 2026:
The MPO also voted to fund two projects in FFY 2025 that were previously incorporated into MassDOT’s Statewide Highway Program:
Because many of these projects were identified later in the project evaluation life cycleāthat is, months after the regular cycle of project submissionsāscoring information is included in the TIP with some delay compared to other project line items. While these projects were identified too late in the TIP cycle to be quantitatively evaluated using the MPO’s scoring criteria, these projects align well qualitatively with many of the MPO’s goals, including enhancing bicycle and pedestrian safety and access, and expanding the accessibility of and maintaining a state of good repair for the region’s transit system. These projects may be scored using the MPO’s scoring criteria in a later TIP cycle.
Table 3-2
New Regional Target Projects Funded in the FFYs 2025ā29 TIP
Project Name |
Proponent |
MPO Investment Program |
FFYs of Funding |
Regional Target Dollars Programmed in FFYs 2025ā29Ā |
|||
---|---|---|---|---|---|---|---|
Arlington- Broadway Complete Streets Design |
Arlington |
Complete Streets |
2025 |
$1,395,000 |
|||
Arlington- Installation of 123 Bicycle Racks and Related Materials |
Arlington |
Community Connections |
2025 |
$90,878 |
|||
Arlington- Stratton School Improvements (Safe Routes to Schools) |
MassDOT |
Bicycle and Pedestrian |
2025 |
$1,625,250 |
|||
Boston- Bluebikes Station Replacement and Electrification, 12 Stations |
Boston |
Community Connections |
2025 |
$590,348 |
|||
Boston- Repurposing Single Space Parking Meter Poles for 1,600 Bicycle Racks |
Boston |
Community Connections |
2025 |
$379,470 |
|||
Brookline- Bluebikes State of Good Repair, 3 Stations and 62 Pedal Bikes |
Brookline |
Community Connections |
2025 |
$200,000 |
|||
Cambridge- Bluebikes State of Good Repair, 8 Stations and 65 Pedal Bikes |
Cambridge |
Community Connections |
2025 |
$385,456 |
|||
CATA- CATA Gloucester Facility Modernization |
CATA |
Transit Transformation |
2025 |
$1,293,000 |
|||
CATA- Fare Upgrades for ADA and Dial-A-Ride Customers |
CATA |
Transit Transformation |
2025 |
$65,000 |
|||
CATA- Vehicle Replacement (4 Vehicles) |
CATA |
Transit Transformation |
2025-26 |
$2,460,000 |
|||
Chelsea-Revere- Regional On-Demand Microtransit Pilot Project |
Chelsea |
Community Connections |
2025-28 |
$1,413,735 |
|||
Framingham- Chris Walsh Trail, Phase 2 [Design Only] |
Framingham |
Bicycle and Pedestrian |
2025 |
$850,000 |
|||
Holliston- Intersection Improvements at Route 16 and Whitney Street [Design Only] |
Holliston |
Intersection Improvements |
2025 |
$250,000 |
|||
Malden- Canal Street Bicycle Lanes |
Malden |
Community Connections |
2025 |
$81,250 |
|||
Marlborough- Reconstruction of Granger Boulevard [Design Only] |
Marlborough |
Complete Streets |
2025 |
$1,215,000 |
|||
MBTA- Central Square Station Accessibility Improvements (Cambridge) |
MBTA |
Transit Transformation |
2025 |
$5,000,000 |
|||
MBTA- Nubian Square Accessibility and Operational Improvements (Boston) |
MBTA |
Transit Transformation |
2025 |
$5,000,000 |
|||
MBTA- Systemwide Pedal and Park Modernization (Alewife, Ashmont, Braintree, Davis Square, Forest Hills, Malden Center, Nubian, Oak Grove, Route 128, Salem, South Station, Wollaston, and Wonderland) |
MBTA |
Transit Transformation |
2025 |
$2,500,000 |
|||
Medfordā Shared-Use Path Connection at the Route 28/Wellington Underpass |
MassDOT |
Bicycle and Pedestrian |
2025 |
$5,509,294 |
|||
MWRTA- Blandin Hub Equitable Redesign Initiative |
MWRTA |
Transit Transformation |
2025-26 |
$2,500,000 |
|||
MWRTA- Procurement of Three 29-foot Buses |
MWRTA |
Transit Transformation |
2025 |
$1,980,000 |
|||
Norfolk-Wrentham-Walpole- Shared-Use Path Installation (Metacomet Greenway) [Design Only] |
Norfolk |
Bicycle and Pedestrian |
2025 |
$1,550,000 |
|||
Revere- Bluebikes Expansion to Northern Strand (Salem Street at North Marshall Street) and Griswold Park |
Revere |
Community Connections |
2025 |
$169,000 |
|||
Scituate- Installation of 25 Bicycle Racks |
Scituate |
Community Connections |
2025 |
$22,800 |
|||
Sherborn- Reconstruction of Route 27 and Route 16 [Design Only] |
Sherborn |
Intersection Improvements |
2025 |
$900,000 |
|||
Somerville- Bluebikes State of Good Repair, 13 Stations |
Somerville |
Community Connections |
2025 |
$278,127 |
|||
Framingham- Design of Intersection Improvements at Route 126/135/MBTA and CSX Railroad |
Framingham |
Major Infrastructure |
2026 |
$1,400,000 |
|||
Lexington- Design of Safety Improvements at the Interstate 95 and Route 4/225 Interchange |
Lexington |
Major Infrastructure |
2026 |
$1,650,000 |
|||
Quincy- Intersection Improvements at Willard Street and Ricciuti Drive |
Quincy |
Intersection Improvements |
2026 |
$1,885,352 |
|||
Bellingham- Roadway Rehabilitation of Route 126 (Hartford Road), from 800 feet north of the I-495 NB off-ramp to Medway town line, including B-06-017. |
Bellingham |
Complete Streets |
2029-30 |
*$8,340,000 |
|||
Ipswich- Argilla Road Roadway Reconstruction |
Ipswich |
Complete Streets |
2029-30 |
*$3,000,000 |
|||
Sudbury-Framingham- Bike Path Construction of Bruce Freeman Rail Trail, from the Sudbury Diamond Railroad Crossing to Eaton Road West |
Sudbury |
Bicycle and Pedestrian |
2029-30 |
*$4,263,000 |
|||
Total |
N/A |
N/A |
N/A |
$51,107,417 |
|
Note: Funding amounts in this table include both federal and non-federal funds, including matching funds.
* These projects are funded starting in FFY 2029 of the TIP, with further funding expected to be programmed in FFY 2030 of the FFYs 2026ā30 TIP.
ADA = Americans with Disabilities Act. CATA = Cape Ann Transportation Authority. FFY = federal fiscal year. MassDOT = Massachusetts Department of Transportation. MBTA = Massachusetts Bay Transportation Authority. MWRTA = MetroWest Regional Transit Authority. N/A = not applicable. NB = northbound. TIP = Transportation Improvement Program.
Source: Boston Region MPO.
In addition to the project selection, several other key decisions were made by the MPO in the drafting of the FFYs 2025ā29 Regional Target Program:
In order to address funding constraints in FFY 2027, the MPO voted to delay Project 610662, WoburnāRoadway and Intersection Improvements at Woburn Common, Route 38 (Main Street), Winn Street, Pleasant Street and Montvale Avenue, to FFY 2029 given a lack of significant design progress on the project since the FFYs 2021ā25 TIP cycle.
Additional details of the specific projects programmed with Regional Target funding are shown in Section 1A of each annual element of the TIP tables (Table 3-7). The other sections in Table 3-7 (Sections 1B, 2A, 2B, 2C, and 3B) list the following:
Tables 3-8, 3-9, 3-10, and 3-11 list the federally funded transit projects and programs in the Boston region that the MBTA, MWRTA, and CATA plan to undertake.
Detailed descriptions of projects funded through both the Regional Target and statewide portions of the Highway Program follow the tables. The descriptions note the evaluation scores (for MPO-funded projects), project proponents, and funding details. The pages are organized alphabetically by the municipality in which each project is located.
This section summarizes the investments made by the Boston Region MPO, MassDOT, MBTA, CATA, and MWRTA that are documented in the FFYs 2025ā29 TIP. Table 3-3 shows the Boston Region MPO’s investments of Regional Target fundingāincluding both the number of projects and the dollar amountāby investment program. These investments are aimed at making progress towards the MPO’s goals for the region, including enhancing safety for all users, preserving and modernizing the transportation system, promoting mobility and reducing congestion, supporting clean air and sustainability, ensuring all have equitable access to the transportation system, and fostering economic vitality in the region through investments in transportation.
The MPO’s Regional Target Program increased in size by approximately $30.4Ā Ā Ā Ā million between the FFYs 2024ā28 TIP and the FFYs 2025ā29 TIP to a total program size of more than $727.9 million.
Ā Ā Ā Ā Table 3-3
FFYs 2025ā29 Boston Region MPO Regional Target Investment Summary
.
MPO Investment Program |
Number of Projects |
Regional Target Dollars Programmed |
Bicycle Network and Pedestrian Connections |
10 |
$69,238,369 |
Community Connections (allocated to projects) |
16 |
$5,154,222 |
Community Connections (not yet allocated to projects)* |
N/A |
$15,423,415 |
Complete Streets |
21 |
$334,236,398 |
Intersection Improvements |
8 |
$47,155,319 |
Major InfrastructureāRoadway |
4 |
$171,860,000 |
Transit Transformation (allocated to projects) |
11 |
$55,548,000 |
Transit Transformation (not yet allocated to projects) |
N/A |
$24,500,000 |
Unprogrammed |
N/A |
$4,812,578 |
Total |
70 |
$727,928,301 |
Note: Funding amounts in this table include both federal and non-federal funds, including matching funds.
* This figure includes $7 million in BikeShare Support funding starting in FFY 2026.
FFY = federal fiscal year. MPO = metropolitan planning organization. N/A = not applicable.
Source: Boston Region MPO.
Table 3-4 shows MassDOT’s FFYs 2025ā29 TIP investmentsāincluding both the number of projects or programs and the dollar amountāorganized by MassDOT program. MassDOT’s investments are distributed across a variety of programs and will support bridge and pavement improvements, roadway improvements and reconstruction, new bicycle and pedestrian infrastructure, and safety improvements. More details on these investments are available on the project description pages in the second section of this chapter.
As detailed above for the MPO’s Regional Target Program, the BIL significantly increased the funding available to MassDOT for programming projects in the statewide Highway Program. Most notably, the BIL’s Bridge Formula Program allowed MassDOT to increase the funding allocated to federal-aid bridge projects. Furthermore, FFY 2026 represents the conclusion of Grant Anticipation Notes (GANS) payments for MassDOT’s Accelerated Bridge Program (ABP). As this program winds down, the passage of the 2021 Massachusetts Transportation Bond Bill and the new federal funding available through the BIL has allowed for the creation of MassDOT’s Next Generation Bridge Program (NGBP).
Like the ABP, the NGBP leverages state bonding capacity to accelerate the rehabilitation and replacement of critical or structurally deficient bridges in Massachusetts. In the FFYs 2025ā29 TIP, 13 bridge projects are funded by MassDOT through the NGBP using state bond bill funds. These projects are shown in the TIP as debt payments on these bonds, which will use future federal formula funding.
Continued funding from the BIL supports increased investment across MassDOT’s other programs represented in the FFYs 2025ā29 TIP, including the Bicycle and Pedestrian Program, the Intersection Improvements Program, the Interstate and Non-Interstate Pavement Programs, the Roadway Reconstruction Program, and the Safety Improvements Program. MassDOT’s Highway Program is substantively similar in total programming between the FFYs 2024ā28 TIP and FFYs 2025ā29 TIP. The FFYs 2025ā29 TIP introduces a new Highway Resiliency Improvement Program.
Table 3-4
FFYs 2025ā29 MassDOT Highway Program Investment Summary
MassDOT Program |
Number of Projects |
MassDOT Dollars Programmed |
Bicycle and Pedestrian |
11 |
$59,536,059 |
Federal-Aid Bridge Program |
38 |
$859,070,202 |
Next Generation Bridge Program |
13 |
$261,283,061 |
Earmarks or Discretionary Grants* |
3 |
$14,690,359 |
Highway Resiliency Improvement Program |
4 |
$23,084,295 |
Intersection Improvements |
7 |
$43,504,651 |
Interstate Pavement |
6 |
$101,152,160 |
Non-Interstate Pavement |
7 |
$46,821,976 |
Roadway Reconstruction |
5 |
$127,321,017 |
Safety Improvements |
5 |
$29,062,449 |
Safe Routes to School |
13 |
$20,712,494 |
Non-Federal Aid (NFA) |
1 |
$53,360,000 |
Total |
113 |
$1,639,598,723 |
Note: Funding amounts in this table include both federal and non-federal funds, including matching funds.
* Three projects receiving earmark funding are also receiving funding through other sources: Project 607977āInterstates 90/495 Interchange Reconstructionāis funded through MassDOT’s Roadway Reconstruction and NFA Programs; Project 605313āNatick Bridge Replacement over Route 9 and Interchange Improvementsāis funded through MassDOT’s Bridge On-System NHS NB Program; and Project 608436āAshland Rehabilitation and Rail Crossing Improvements on Cherry Streetāis funded through MassDOT’s Railroad Crossings Program. Each project is counted in the tally for each funding category but is only counted once in the total number of projects funded.
Table 3-5 shows the MBTA’s programs and associated FFYs 2025ā29 TIP funding amounts. Additional details on the MBTA’s programs and projects are in Tables 3-8 and 3-9. The MBTA’s capital program is substantively similar between FFYs 2024ā28 TIP and the FFYs 2025ā29 TIP, decreasing from a total program size of $3.99 billion to $3.85 billion. Investments made through these programs allow the MBTA to continue to maintain and modernize its infrastructure in support of the agency’s role as the largest transit provider in the Commonwealth of Massachusetts.
The MBTA caters to a wide range of needs, serving the Boston region with commuter rail, light rail, subway, fixed-route bus, and paratransit services. The MBTA prioritizes projects that keep the existing transit system in a state of good repair, including the purchase of new rolling stock, accessibility and resiliency improvements to stations, the rehabilitation of bridges and tunnels, and the replacement of tracks and signals to support system-wide reliability. Limited system expansion projects are also undertaken through the MBTA’s federal capital program. Further information on how the MBTA’s investments support system safety and condition is available in Chapter 4.
Table 3-5
Ā FFYs 2025ā29 MBTA Transit Program Investment Summary
Federal Transit Administration Program |
MBTA Program |
Ā MBTA Dollars Programmed |
Section 5307: Urbanized Area Formula Grants |
Bridge and Tunnel Program |
$95,000,000 |
Section 5307: Urbanized Area Formula Grants |
Revenue Vehicle Program |
$672,627,205 |
Section 5307: Urbanized Area Formula Grants |
Signals/Systems Upgrade Program |
$216,549,653 |
Section 5307: Urbanized Area Formula Grants |
Stations and Facilities Program |
229,376,680 |
Section 5337: Fixed Guideway/Bus Funds |
Bridge and Tunnel Program |
$612,484,215 |
Section 5337: Fixed Guideway/Bus Funds |
Revenue Vehicle Program |
$207,097,948 |
Section 5337: Fixed Guideway/Bus Funds |
Signals/Systems Upgrade Program |
$179,111,523 |
Section 5337: Fixed Guideway/Bus Funds |
Stations and Facilities Program |
$373,116,657 |
Section 5337: Fixed Guideway/Bus Funds |
Preventive Maintenance |
$132,328,125 |
Section 5339: Bus and Bus Facilities Funds |
Bus Program |
$39,911,811 |
Other Federal Funds |
Positive Train Control* |
$100,085,333 |
Other Federal Funds |
RRIF/TIFIA Financing Programā |
$797,500,000 |
Other Federal Funds |
FFY 2025 Flex from Boston Region MPO Regional Prioritization |
$47,250,000 |
Total |
N/A |
$3,749,314,149 |
Note: Federal Transit Administration formula funds (Sections 5307, 5337 and 5339) are based on estimated apportionments for FFYs 2025ā29. These apportionments include additional funding to be made available through the Bipartisan Infrastructure Law, based on current estimates. TIP programs and projects are based on a preliminary draft Capital Investment Plan (CIP) as of April 2022. Adjustments will be made to federal projects and budgets as the CIP process is finalized. Funding amounts in this table include both federal and non-federal funds, including matching funds.
* Positive Train Control investments are funded with RRIF funds.
ā RRIF/TIFIA financing program funding is an initial estimate and will be refined as projects are identified and loans are finalized with the Build America Bureau.
FFY = federal fiscal year. N/A = not applicable. RRIF = Railroad Rehabilitation and Improvement Financing. TIFIA = Transportation Infrastructure Finance and Innovation Act. TIP = Transportation Improvement Program.
Sources: MBTA and the Boston Region MPO.
Table 3-6 summarizes CATA and MWRTA investments included in the FFYs 2025ā29 TIP, and more information is available on each agency’s investments in Tables 3-10 and 3-11. Though the MBTA provides commuter rail service to the Cape Ann communities of Rockport and Gloucester, CATA provides additional paratransit and fixed-route bus services to these communities and to Danvers, Peabody, Ipswich, Essex, and Beverly. CATA’s federal capital program supports its role in providing critical transportation alternatives to residents and visitors of the area, including through the replacement of buses, the modernization of facilities, and the maintenance of assets.
MWRTA similarly complements MBTA commuter rail service, operating fixed-route bus, on-demand microtransit, and commuter shuttle services to a number of communities in the MetroWest subregion. MWRTA’s federal capital program supports this mission by funding vehicle replacements, station and facility maintenance and improvements, and operating assistance for paratransit services, among other efforts. Other MWRTA projects funded in the MWRTA’s capital program include the electrification of the agency’s paratransit fleet and investments in technology to support travel training and customer service efforts.
The program sizes for CATA and MWRTA increased greatly between the FFYs 2024ā28 TIP and FFYs 2025ā29. This was driven by a 91 percent increase in the state budget for regional transit authorities in state fiscal year 2024. These agencies collectively received an approximate $41.52 million increase in funding levels in this TIP, increasing from $65.36 million to a total program size of $106.88 million. This funding level also includes approximately $8.3 million in flexed funding from the Boston Region MPO’s Regional Target Program between FFYs 2025 and 2026.
Table 3-6
FFYs 2025ā29 CATA and MWRTA Transit Program Investment Summary
Regional Transit Authority |
Federal Transit Administration Program |
Ā RTA Dollars Programmed |
CATA |
Section 5307: Urbanized Area Formula Funding |
$5,374,400 |
CATA |
State Transportation Bond Capital Assistance |
$7,158,750 |
CATA |
Municipal and Local Assessments |
$500,000 |
MWRTA |
Section 5307: Urbanized Area Formula Funding |
$25,847,172 |
MWRTA |
Section 5339: Bus and Bus Facilities |
$11,474,981 |
MWRTA |
State Transportation Bond Capital Assistance |
$12,884,064 |
MWRTA |
Other Federal |
$43,637,496 |
Total |
N/A |
$106,876,863 |
Note: Funding amounts in this table include both federal and non-federal funds, including matching funds.
CATA = Cape Ann Transportation Authority. FFY = federal fiscal year. MWRTA = Metro West Regional Transit Authority. N/A = not applicable. RTA = regional transit authority.
Sources: CATA, MWRTA, and the Boston Region MPO.
Tables 3-7 through 3-11 build on the summary tables listed above by detailing investments made through both the Highway and Transit Programs by project, program, and funding year.
Table 3-7
FFYs 2025ā29 TIP Highway Table
Year | MassDOT Project ID | MPO | Municipality | MassDOT Project Description | District | Funding Source | Adjusted TFPC | Total Programmed Funds | Federal Funds | Non-Federal Funds | ||
Federal Fiscal Year 2025 | $384,358,434 | $251,898,203 | $132,460,231 | |||||||||
Section 1A / Regionally Prioritized Projects | $126,277,235 | $101,321,788 | $24,955,447 | |||||||||
Roadway Reconstruction | $37,452,645 | $30,262,116 | $7,190,529 | |||||||||
2025 | 608051 | Boston Region | Wilmington | WILMINGTON- RECONSTRUCTION ON ROUTE 38 (MAIN STREET), FROM ROUTE 62 TO THE WOBURN C.L. | 4 | CMAQ | $37,452,645 | $3,200,000 | $2,560,000 | $640,000 | ||
2025 | 608051 | Boston Region | Wilmington | WILMINGTON- RECONSTRUCTION ON ROUTE 38 (MAIN STREET), FROM ROUTE 62 TO THE WOBURN C.L. | 4 | HSIP | $37,452,645 | $3,000,000 | $2,700,000 | $300,000 | ||
2025 | 608051 | Boston Region | Wilmington | WILMINGTON- RECONSTRUCTION ON ROUTE 38 (MAIN STREET), FROM ROUTE 62 TO THE WOBURN C.L. | 4 | STBG | $37,452,645 | $31,252,645 | $25,002,116 | $6,250,529 | ||
Intersection Improvements | $3,688,311 | $2,950,649 | $737,662 | |||||||||
2025 | 608067 | Boston Region | Multiple | WOBURN- BURLINGTON- INTERSECTION RECONSTRUCTION AT ROUTE 3 (CAMBRIDGE ROAD) & BEDFORD ROAD AND SOUTH BEDFORD STREET | 4 | CMAQ | $3,438,311 | $1,978,080 | $1,582,464 | $395,616 | ||
2025 | 608067 | Boston Region | Multiple | WOBURN- BURLINGTON- INTERSECTION RECONSTRUCTION AT ROUTE 3 (CAMBRIDGE ROAD) & BEDFORD ROAD AND SOUTH BEDFORD STREET | 4 | STBG | $3,438,311 | $1,460,231 | $1,168,185 | $292,046 | ||
2025 | S12984 | Boston Region | Holliston | HOLLISTONā INTERSECTION IMPROVEMENTS AT ROUTE 16 AND WHITNEY STREET [DESIGN ONLY] | 3 | STBG | $250,000 | $250,000 | $200,000 | $50,000 | ||
Safe Routes to School | $1,625,250 | $1,300,200 | $325,050 | |||||||||
2025 | 609531 | Boston Region | Arlington | ARLINGTON- STRATTON SCHOOL IMPROVEMENTS (SRTS) | 4 | TAP | $1,625,250 | $1,625,250 | $1,300,200 | $325,050 | ||
Bicycle and Pedestrian | $24,072,722 | $19,258,178 | $4,814,544 | |||||||||
2025 | 610544 | Boston Region | Peabody | PEABODY- MULTI-USE PATH CONSTRUCTION OF INDEPENDENCE GREENWAY AT I-95 AND ROUTE 1 | 4 | CMAQ | $13,966,099 | $5,500,000 | $4,400,000 | $1,100,000 | ||
2025 | 610544 | Boston Region | Peabody | PEABODY- MULTI-USE PATH CONSTRUCTION OF INDEPENDENCE GREENWAY AT I-95 AND ROUTE 1 | 4 | STBG | $13,966,099 | $5,466,099 | $4,372,879 | $1,093,220 | ||
2025 | 610544 | Boston Region | Peabody | PEABODY- MULTI-USE PATH CONSTRUCTION OF INDEPENDENCE GREENWAY AT I-95 AND ROUTE 1 | 4 | TAP | $13,966,099 | $3,000,000 | $2,400,000 | $600,000 | ||
2025 | 611982 | Boston Region | Medford | MEDFORD- SHARED USE PATH CONNECTION AT THE ROUTE 28/WELLINGTON UNDERPASS | 4 | CMAQ | $5,509,294 | $5,509,294 | $4,407,435 | $1,101,859 | ||
2025 | S12958 | Boston Region | Boston | BOSTON- BLUEBIKES STATION REPLACEMENT AND ELECTRIFICATION, 12 STATIONS | STBG | $590,348 | $590,348 | $472,278 | $118,070 | |||
2025 | S12959 | Boston Region | Boston | BOSTON- REPURPOSING SINGLE SPACE PARKING METER POLES FOR 1600 BICYCLE RACKS | CMAQ | $379,470 | $379,470 | $303,576 | $75,894 | |||
2025 | S12960 | Boston Region | Cambridge | CAMBRIDGE- BLUEBIKES STATE OF GOOD REPAIR, 8 STATIONS AND 65 PEDAL BIKES | STBG | $385,456 | $385,456 | $308,365 | $77,091 | |||
2025 | S12961 | Boston Region | Brookline | BROOKLINE- BLUEBIKES STATE OF GOOD REPAIR, 3 STATIONS AND 62 PEDAL BIKES | STBG | $200,000 | $200,000 | $160,000 | $40,000 | |||
2025 | S12962 | Boston Region | Somerville | SOMERVILLE- BLUEBIKES STATE OF GOOD REPAIR, 3 STATIONS AND 62 PEDAL BIKES | STBG | $278,127 | $278,127 | $222,502 | $55,625 | |||
2025 | S12964 | Boston Region | Revere | REVERE- BLUEBIKES EXPANSION TO NORTHERN STRAND (SALEM STREET AT NORTH MARSHALL STREET) AND GRISWOLD PARK | CMAQ | $169,000 | $169,000 | $135,200 | $33,800 | |||
2025 | S12965 | Boston Region | Arlington | ARLINGTON- INSTALLATION OF 123 BICYCLE RACKS AND RELATED MATERIALS | CMAQ | $90,878 | $90,878 | $72,702 | $18,176 | |||
2025 | S12966 | Boston Region | Malden | MALDEN- CANAL STREET BICYCLE LANES | CMAQ | $81,250 | $81,250 | $65,000 | $16,250 | |||
2025 | S12967 | Boston Region | Scituate | SCITUATE- INSTALLATION OF 25 BICYCLE RACKS | CMAQ | $22,800 | $22,800 | $18,240 | $4,560 | |||
2025 | S12981 | Boston Region | Multiple | NORFOLK-WRENTHAM-WALPOLE- SHARED-USE PATH INSTALLATION (METACOMET GREENWAY) [DESIGN ONLY] | 5 | TAP | $1,550,000 | $1,550,000 | $1,240,000 | $310,000 | ||
2025 | S12982 | Boston Region | Framingham | FRAMINGHAMā CHRIS WALSH TRAIL PHASE 2 [DESIGN ONLY] | 3 | TAP | $850,000 | $850,000 | $680,000 | $170,000 | ||
Transit Grant Program | $7,731,777 | $6,185,422 | $1,546,355 | |||||||||
2025 | S12697 | Boston Region | Watertown | PLEASANT STREET SHUTTLE SERVICE EXPANSION | 6 | CMAQ | $1,002,198 | $228,939 | $183,151 | $45,788 | ||
2025 | S12699 | Boston Region | Stoneham | STONEHAM SHUTTLE SERVICE | 4 | CMAQ | $796,817 | $205,189 | $164,151 | $41,038 | ||
2025 | S12963 | Boston Region | Multiple | CHELSEA-REVERE- REGIONAL ON-DEMAND MICROTRANSIT PILOT PROJECT | CMAQ | $1,413,375 | $499,649 | $399,719 | $99,930 | |||
2025 | S12968 | Boston Region | CATAā FARE UPGRADES FOR ADA AND DIAL-A-RIDE CUSTOMERS | 4 | CMAQ | $65,000 | $65,000 | $52,000 | $13,000 | |||
2025 | S12969 | Boston Region | Gloucester | CATAā GLOUCESTER FACILITY MODERNIZATION | 4 | CMAQ | $1,293,000 | $1,293,000 | $1,034,400 | $258,600 | ||
2025 | S12970 | Boston Region | CATAā VEHICLE REPLACEMENT (4 VEHICLES) | 4 | CMAQ | $2,460,000 | $1,710,000 | $1,368,000 | $342,000 | |||
2025 | S12971 | Boston Region | Framingham | MWRTAā BLANDIN HUB EQUITABLE REDESIGN INITIATIVE | 3 | CMAQ | $2,500,000 | $1,750,000 | $1,400,000 | $350,000 | ||
2025 | S12972 | Boston Region | MWRTAā PROCUREMENT OF THREE 29 FOOT BUSES (CNG) | CMAQ | $1,980,000 | $1,980,000 | $1,584,000 | $396,000 | ||||
Flex to FTA | $48,196,530 | $38,557,224 | $9,639,306 | |||||||||
2025 | S12700 | Boston Region | Multiple | CATA ON DEMAND MICROTRANSIT SERVICE EXPANSION ā ROCKPORT AND LANESVILLE | 4 | CMAQ | $813,291 | $214,776 | $171,821 | $42,955 | ||
2025 | S12701 | Boston Region | Multiple | MWRTA CATCHCONNECT MICROTRANSIT SERVICE EXPANSION - HUDSON AND MARLBOROUGH | 3 | CMAQ | $450,163 | $159,488 | $127,590 | $31,898 | ||
2025 | S12703 | Boston Region | Multiple | MONTACHUSETT RTA MICROTRANSIT SERVICE ā ON-DEMAND SERVICE FOR BOLTON, BOXBOROUGH, LITTLETON, STOW | 3 | CMAQ | $1,316,061 | $406,641 | $325,313 | $81,328 | ||
2025 | S12807 | Boston Region | Multiple | MWRTA CATCHCONNECT MICROTRANSIT EXPANSION PHASE 2 | 3 | CMAQ | $380,477 | $165,625 | $132,500 | $33,125 | ||
2025 | S12819 | Boston Region | Boston | JACKSON SQUARE STATION ACCESSIBILITY IMPROVEMENTS | 6 | CMAQ | $33,500,000 | $21,250,000 | $17,000,000 | $4,250,000 | ||
2025 | S12974 | Boston Region | Cambridge | MBTAā CENTRAL SQUARE STATION ACCESSIBILITY IMPROVEMENTS (CAMBRIDGE) | CMAQ | $5,000,000 | $5,000,000 | $4,000,000 | $1,000,000 | |||
2025 | S12975 | Boston Region | Multiple | MBTAā SYSTEMWIDE PEDAL AND PARK MODERNIZATION (ALEWIFE, ASHMONT, BRAINTREE, DAVIS SQUARE, FOREST HILLS, MALDEN CENTER, NUBIAN, OAK GROVE, ROUTE 128, SALEM, SOUTH STATION, WOLLASTON, WONDERLAND) | CMAQ | $2,500,000 | $2,500,000 | $2,000,000 | $500,000 | |||
2025 | S12976 | Boston Region | Boston | MBTAā NUBIAN SQUARE ACCESSIBILITY AND OPERATIONAL IMPROVEMENTS (BOSTON) | CMAQ | $5,000,000 | $5,000,000 | $4,000,000 | $1,000,000 | |||
2025 | S12985 | Boston Region | Boston | MBTAā COLUMBUS AVENUE BUS LANES PHASE II (BOSTON) | 6 | CMAQ | $7,500,000 | $7,500,000 | $6,000,000 | $1,500,000 | ||
2025 | S12986 | Boston Region | Multiple | MBTAā RAIL TRANSFORMATION EARLY ACTION ITEMS - READING STATION AND WILBUR INTERLOCKING | 4 | CMAQ | $6,000,000 | $6,000,000 | $4,800,000 | $1,200,000 | ||
Non-Interstate Pavement | $3,510,000 | $2,808,000 | $702,000 | |||||||||
2025 | S12979 | Boston Region | Arlington | ARLINGTONā BROADWAY COMPLETE STREETS DESIGN | 4 | STBG | $1,395,000 | $1,395,000 | $1,116,000 | $279,000 | ||
2025 | S12980 | Boston Region | Marlborough | MARLBOROUGHā RECONSTRUCTION OF GRANGER BOULEVARD [DESIGN ONLY] | 3 | STBG | $1,215,000 | $1,215,000 | $972,000 | $243,000 | ||
2025 | S12983 | Boston Region | Sherborn | SHERBORNā RECONSTRUCTION OF ROUTE 27 AND ROUTE 16 [DESIGN ONLY] | 3 | STBG | $900,000 | $900,000 | $720,000 | $180,000 | ||
Section 1B / Earmark or Discretionary Grant Funded Projects | $75,137,846 | $60,110,277 | $15,027,569 | |||||||||
Earmark Discretionary | $14,210,359 | $11,368,287 | $2,842,072 | |||||||||
2025 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | HIP-BR | $300,942,837 | $13,935,359 | $11,148,287 | $2,787,072 | ||
2025 | S12907 | Boston Region | Framingham | Framingham - Chris Walsh Aqueduct Trail Connectivity Project (Design Earmark MA275) | 3 | HPP | $275,000 | $275,000 | $220,000 | $55,000 | ||
Bridge On-system Non-NHS NB | $7,209,518 | $5,767,614 | $1,441,904 | |||||||||
2025 | 608522 | Boston Region | Middleton | MIDDLETON- BRIDGE REPLACEMENT, M-20-003, ROUTE 62 (MAPLE STREET) OVER IPSWICH RIVER | 4 | HIP-BR | $3,635,960 | $3,635,960 | $2,908,768 | $727,192 | ||
2025 | 608865 | Boston Region | Multiple | STONEHAM- WINCHESTER- DECK REPLACEMENT, S-27-008=W-40-030 (2M5), MARBLE STREET OVER I-93 | 4 | HIP-BR | $3,573,558 | $3,573,558 | $2,858,846 | $714,712 | ||
Bridge Systematic Maintenance NB | $52,520,197 | $42,016,158 | $10,504,039 | |||||||||
2025 | 612073 | Boston Region | Sharon | SHARON- BRIDGE PRESERVATION OF S-09-015 AND S-09-016 ALONG THE I-95 CORRIDOR | 5 | HIP-BR | $1,329,697 | $1,329,697 | $1,063,758 | $265,939 | ||
2025 | 613178 | Boston Region | Lexington | LEXINGTON- DECK REPLACEMENT, L-10-019 (2DW, 2DX), STATE ROUTE 2/CONCORD TURNPIKE OVER PLEASANT STREET | 4 | HIP-BR | $13,006,500 | $13,006,500 | $10,405,200 | $2,601,300 | ||
2025 | 613181 | Boston Region | Multiple | BOSTON- NEWTON- BRIDGE PRESERVATION OF 3 BRIDGES ALONG STATE ROUTE 9/BOYLSTON STREET | 6 | HIP-BR | $9,499,000 | $9,499,000 | $7,599,200 | $1,899,800 | ||
2025 | 613209 | Boston Region | Boston | BOSTON- BRIDGE PRESERVATION, B-16-236 (39M, 39P, 39U, 39W, 39Y), 5 BRIDGES CARRYING STATE ROUTE 1A (EAST BOSTON EXPRESSWAY NB/SB) AND RAMPS | 6 | HIP-BR | $6,525,000 | $6,525,000 | $5,220,000 | $1,305,000 | ||
2025 | 613216 | Boston Region | Marlborough | MARLBOROUGH- BRIDGE PRESERVATION, M-06-010, ELM STREET OVER I-495 | 3 | HIP-BR | $2,160,000 | $2,160,000 | $1,728,000 | $432,000 | ||
2025 | 613638 | Boston Region | Boston | BOSTON- CLEANING & PAINTING, B-16-259, I-93 OVER MBTA/COLUMBIA ROAD/RED LINE/RELIEF | 6 | HIP-BR | $20,000,000 | $20,000,000 | $16,000,000 | $4,000,000 | ||
Bicycle and Pedestrian | $1,197,772 | $958,218 | $239,554 | |||||||||
2025 | 613357 | Boston Region | Cambridge | CAMBRIDGE- SEPARATED BICYCLE LANEĀ ON STEEL PLACE (MA272) | 6 | HPP | $1,197,772 | $1,197,772 | $958,218 | $239,554 | ||
Section 2A / Federal Aid Funded State Prioritized Reliability Projects | $61,631,063 | $52,294,850 | $9,336,213 | |||||||||
Bridge On-system NHS | $23,387,813 | $18,710,250 | $4,677,563 | |||||||||
2025 | 608703 | Boston Region | Wilmington | WILMINGTON- BRIDGE REPLACEMENT, W-38-029 (2KV), ST 129 LOWELL STREET OVER I 93 | 4 | NHPP-PEN | $15,954,700 | $15,954,700 | $12,763,760 | $3,190,940 | ||
2025 | 610776 | Boston Region | Cambridge | CAMBRIDGE- SUPERSTRUCTURE REPLACEMENT, C-01-031, US ROUTE 3/ROUTE 16/ROUTE 2 OVER MBTA REDLINE | 6 | NHPP-PEN | $7,433,113 | $7,433,113 | $5,946,490 | $1,486,623 | ||
Non-Interstate Pavement | $8,343,250 | $6,674,600 | $1,668,650 | |||||||||
2025 | 612044 | Boston Region | Multiple | BROOKLINE- NEWTON- RESURFACING AND RELATED WORK ON ROUTE 9 | 6 | NHPP | $8,343,250 | $8,343,250 | $6,674,600 | $1,668,650 | ||
Interstate Pavement | $29,900,000 | $26,910,000 | $2,990,000 | |||||||||
2025 | 612094 | Boston Region | Multiple | CANTON- DEDHAM- WESTWOOD- INTERSTATE MAINTENANCE AND RELATED WORK ON I-95 AND I-93 | 6 | NHPP-I | $29,899,107 | $29,900,000 | $26,910,000 | $2,990,000 | ||
Section 2B / Federal Aid Funded State Prioritized Modernization Projects | $43,188,978 | $38,171,288 | $5,017,690 | |||||||||
Intersection Improvements | $9,080,341 | $8,172,307 | $908,034 | |||||||||
2025 | 607342 | Boston Region | Milton | MILTON- INTERSECTION IMPROVEMENTS AT ROUTE 28 (RANDOLPH AVENUE) & CHICKATAWBUT ROAD | 6 | HSIP | $9,080,341 | $9,080,341 | $8,172,307 | $908,034 | ||
Roadway Reconstruction | $34,108,637 | $29,998,981 | $4,109,656 | |||||||||
2025 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | NHPP-I | $300,942,837 | $9,000,000 | $8,100,000 | $900,000 | ||
2025 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | NFP-I | $300,942,837 | $18,120,711 | $16,308,640 | $1,812,071 | ||
2025 | 609516 | Boston Region | Burlington | BURLINGTON- IMPROVEMENTS AT I-95 (ROUTE 128)/ROUTE 3 INTERCHANGE | 4 | NHPP | $6,987,927 | $6,987,926 | $5,590,341 | $1,397,585 | ||
Section 3B / Non-Federal Aid Funded | $78,123,312 | $0 | $78,123,312 | |||||||||
Bridge On-system Non-NHS | $39,218,766 | $0 | $39,218,766 | |||||||||
2025 | 606901 | Boston Region | Boston | BOSTON- BRIDGE REPLACEMENT, B-16-109, RIVER STREET BRIDGE OVER MBTA/AMTRAK | 6 | NGBP | $12,538,835 | $12,538,835 | $0 | $12,538,835 | ||
2025 | 612173 | Boston Region | Bellingham | BELLINGHAM- BRIDGE REPLACEMENT, B-06-022, MAPLE STREET OVER I-495 | 3 | NGBP | $13,721,814 | $13,721,814 | $0 | $13,721,814 | ||
2025 | S12908 | Boston Region | Somerville | P# 611940: SOMERVILLE- BRIDGE REPLACEMENT, S-17-016 (3GF), WEBSTER AVENUE OVER MBTA & BMRR | 4 | NGBP | $12,958,117 | $12,958,117 | $0 | $12,958,117 | ||
NFA | $26,680,000 | $0 | $26,680,000 | |||||||||
2025 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | NFA | $300,942,837 | $26,680,000 | $0 | $26,680,000 | ||
Bridge On-system NHS | $12,224,546 | $0 | $12,224,546 | |||||||||
2025 | 86461 | Boston Region | Lincoln | LINCOLN- BRIDGE REPLACEMENT, L-12-002, CONCORD ROAD (ROUTE 126) OVER MBTA | 4 | NGBP | $12,224,546 | $12,224,546 | $0 | $12,224,546 | ||
Federal Fiscal Year 2026 | $588,278,222 | $379,531,999 | $208,746,223 | |||||||||
Section 1A / Regionally Prioritized Projects | $124,569,057 | $101,561,946 | $23,007,111 | |||||||||
Roadway Reconstruction | $61,952,049 | $49,711,639 | $12,240,410 | |||||||||
2026 | 605168 | Boston Region | Hingham | HINGHAM- IMPROVEMENTS ON ROUTE 3A, FROM OTIS STREET/COLE ROADĀ INCLUDING SUMMER STREET AND ROTARY, ROCKLAND STREET TO GEORGE WASHINGTON BOULEVARDĀ | 5 | NHPP | $28,738,432 | $11,738,432 | $9,390,746 | $2,347,686 | ||
2026 | 605168 | Boston Region | Hingham | HINGHAM- IMPROVEMENTS ON ROUTE 3A, FROM OTIS STREET/COLE ROADĀ INCLUDING SUMMER STREET AND ROTARY, ROCKLAND STREET TO GEORGE WASHINGTON BOULEVARDĀ | 5 | STBG | $28,738,432 | $15,000,000 | $12,000,000 | $3,000,000 | ||
2026 | 605168 | Boston Region | Hingham | HINGHAM- IMPROVEMENTS ON ROUTE 3A, FROM OTIS STREET/COLE ROADĀ INCLUDING SUMMER STREET AND ROTARY, ROCKLAND STREET TO GEORGE WASHINGTON BOULEVARDĀ | 5 | TAP | $28,738,432 | $2,000,000 | $1,600,000 | $400,000 | ||
2026 | 606453 | Boston Region | Boston | BOSTON- IMPROVEMENTS ON BOYLSTON STREET, FROM INTERSECTION OF BROOKLINE AVENUE & PARK DRIVE TO IPSWICH STREET | 6 | CMAQ | $8,665,052 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2026 | 606453 | Boston Region | Boston | BOSTON- IMPROVEMENTS ON BOYLSTON STREET, FROM INTERSECTION OF BROOKLINE AVENUE & PARK DRIVE TO IPSWICH STREET | 6 | STBG | $8,665,052 | $2,851,808 | $2,281,446 | $570,362 | ||
2026 | 606453 | Boston Region | Boston | BOSTON- IMPROVEMENTS ON BOYLSTON STREET, FROM INTERSECTION OF BROOKLINE AVENUE & PARK DRIVE TO IPSWICH STREET | 6 | TAP | $8,665,052 | $813,244 | $650,595 | $162,649 | ||
2026 | 608045 | Boston Region | Milford | MILFORD- REHABILITATION ON ROUTE 16, FROM ROUTE 109 TO BEAVER STREET | 3 | HSIP | $13,548,565 | $1,500,000 | $1,350,000 | $150,000 | ||
2026 | 608045 | Boston Region | Milford | MILFORD- REHABILITATION ON ROUTE 16, FROM ROUTE 109 TO BEAVER STREET | 3 | STBG | $13,548,565 | $12,048,565 | $9,638,852 | $2,409,713 | ||
2026 | 609252 | Boston Region | Lynn | LYNN- REHABILITATION OF ESSEX STREET | 4 | CMAQ | $19,698,640 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2026 | 609252 | Boston Region | Lynn | LYNN- REHABILITATION OF ESSEX STREET | 4 | STBG | $19,698,640 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2026 | S12820 | Boston Region | BOSTON REGION - BIKESHARE SUPPORT SET ASIDE | STBG | $6,000,000 | $1,000,000 | $800,000 | $200,000 | ||||
Intersection Improvements | $30,874,140 | $25,286,726 | $5,587,414 | |||||||||
2026 | 605857 | Boston Region | Norwood | NORWOOD- INTERSECTION IMPROVEMENTS @ ROUTE 1 & UNIVERSITY AVENUE/EVERETT STREETĀ | 5 | CMAQ | $27,636,336 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2026 | 605857 | Boston Region | Norwood | NORWOOD- INTERSECTION IMPROVEMENTS @ ROUTE 1 & UNIVERSITY AVENUE/EVERETT STREETĀ | 5 | HSIP | $27,636,336 | $2,636,336 | $2,372,702 | $263,634 | ||
2026 | 605857 | Boston Region | Norwood | NORWOOD- INTERSECTION IMPROVEMENTS @ ROUTE 1 & UNIVERSITY AVENUE/EVERETT STREETĀ | 5 | NHPP | $27,636,336 | $10,000,000 | $8,000,000 | $2,000,000 | ||
2026 | 605857 | Boston Region | Norwood | NORWOOD- INTERSECTION IMPROVEMENTS @ ROUTE 1 & UNIVERSITY AVENUE/EVERETT STREETĀ | 5 | STBG | $27,636,336 | $10,000,000 | $8,000,000 | $2,000,000 | ||
2026 | 608940 | Boston Region | Weston | WESTON- INTERSECTION IMPROVEMENTS BOSTON POST ROAD (ROUTE 20) AT WELLESLEY STREETĀ | 6 | HSIP | $3,237,804 | $3,237,804 | $2,914,024 | $323,780 | ||
Bicycle and Pedestrian | $8,000,000 | $6,400,000 | $1,600,000 | |||||||||
2026 | 609204 | Boston Region | Belmont | BELMONT- COMMUNITY PATH, BELMONT COMPONENT OF THE MCRT (PHASE I) | 4 | CMAQ | $20,499,750 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2026 | 609204 | Boston Region | Belmont | BELMONT- COMMUNITY PATH, BELMONT COMPONENT OF THE MCRT (PHASE I) | 4 | TAP | $20,499,750 | $3,000,000 | $2,400,000 | $600,000 | ||
Safety Improvements | $11,692,868 | $10,523,581 | $1,169,287 | |||||||||
2026 | 609532 | Boston Region | Chelsea | CHELSEA- TARGETED SAFETY IMPROVEMENTS AND RELATED WORK ON BROADWAY, FROM WILLIAMS STREET TO CITY HALL AVENUE | 6 | HSIP | $9,807,515 | $9,807,515 | $8,826,764 | $980,752 | ||
2026 | 610823 | Boston Region | Quincy | QUINCY- INTERSECTION IMPROVEMENTS AT WILLARD STREET AND RICCIUTI DRIVE | 6 | HSIP | $1,885,353 | $1,885,353 | $1,696,818 | $188,535 | ||
Flex to FTA | $5,162,500 | $4,130,000 | $1,032,500 | |||||||||
2026 | S12113 | Boston Region | BOSTON REGION - TRANSIT TRANSFORMATION PROGRAM | CMAQ | $21,500,000 | $5,000,000 | $4,000,000 | $1,000,000 | ||||
2026 | S12807 | Boston Region | Multiple | MWRTA CATCHCONNECT MICROTRANSIT EXPANSION PHASE 2 | 3 | CMAQ | $380,477 | $162,500 | $130,000 | $32,500 | ||
Transit Grant Program | $3,837,500 | $3,070,000 | $767,500 | |||||||||
2026 | S12124 | Boston Region | Multiple | BOSTON REGION - COMMUNITY CONNECTIONS PROGRAM | CMAQ | $8,423,415 | $1,887,222 | $1,509,778 | $377,444 | |||
2026 | S12963 | Boston Region | Multiple | CHELSEA-REVERE- REGIONAL ON-DEMAND MICROTRANSIT PILOT PROJECT | CMAQ | $1,413,375 | $450,278 | $360,222 | $90,056 | |||
2026 | S12970 | Boston Region | CATAā VEHICLE REPLACEMENT (4 VEHICLES) | 4 | CMAQ | $2,460,000 | $750,000 | $600,000 | $150,000 | |||
2026 | S12971 | Boston Region | Framingham | MWRTAā BLANDIN HUB EQUITABLE REDESIGN INITIATIVE | 3 | CMAQ | $2,500,000 | $750,000 | $600,000 | $150,000 | ||
Railroad Grade Crossings | $1,400,000 | $1,120,000 | $280,000 | |||||||||
2026 | S12977 | Boston Region | Framingham | FRAMINGHAM- PRELIMINARY DESIGN OF INTERSECTION IMPROVEMENTS AT ROUTE 126/135/MBTA & CSX RAILROADĀ | 3 | STBG | $1,400,000 | $1,400,000 | $1,120,000 | $280,000 | ||
Bridge On-system NHS | $1,650,000 | $1,320,000 | $330,000 | |||||||||
2026 | S12978 | Boston Region | Lexington | LEXINGTON- DESIGN OF SAFETY IMPROVEMENTS AT THE INTERSTATE 95 AND ROUTE 4/225 INTERCHANGE | NHPP | $1,650,000 | $1,650,000 | $1,320,000 | $330,000 | |||
Section 1B / Earmark or Discretionary Grant Funded Projects | $235,884,640 | $189,385,029 | $46,499,611 | |||||||||
Bridge On-system Non-NHS NB | $9,699,477 | $7,759,582 | $1,939,895 | |||||||||
2026 | 608197 | Boston Region | Boston | BOSTON- BRIDGE REHABILITATION, B-16-107, CANTERBURY STREET OVER AMTRAK RAILROAD | 6 | HIP-BR | $5,919,826 | $5,919,826 | $4,735,861 | $1,183,965 | ||
2026 | 612075 | Boston Region | Salem | SALEM- BRIDGE REPLACEMENT, S-01-024, JEFFERSON AVENUE OVER PARALLEL STREET | 4 | HIP-BR | $3,779,651 | $3,779,651 | $3,023,721 | $755,930 | ||
Bridge Off-system Local NB | $3,386,585 | $3,386,585 | $0 | |||||||||
2026 | 609467 | Boston Region | Multiple | HAMILTON- IPSWICH- BRIDGE REPLACEMENT, H-03-002=I-01-006, WINTHROP STREET OVER IPSWICH RIVER | 4 | BROFF | $3,386,585 | $3,386,585 | $3,386,585 | $0 | ||
Bridge On-System NHS NB | $188,740,741 | $150,992,593 | $37,748,148 | |||||||||
2026 | 612496 | Boston Region | Somerville | SOMERVILLE- BRIDGE PRESERVATION, S-17-031, I-93 (NB & SB) FROM ROUTE 28 TO TEMPLE STREET (PHASE 2) | 4 | HIP-BR | $188,740,741 | $105,261,935 | $84,209,548 | $21,052,387 | ||
2026 | 612496 | Boston Region | Somerville | SOMERVILLE- BRIDGE PRESERVATION, S-17-031, I-93 (NB & SB) FROM ROUTE 28 TO TEMPLE STREET (PHASE 2) | 4 | HIP-BRRR | $188,740,741 | $83,478,806 | $66,783,045 | $16,695,761 | ||
Bridge Systematic Maintenance NB | $34,057,837 | $27,246,270 | $6,811,567 | |||||||||
2026 | 613182 | Boston Region | Milford | MILFORD- BRIDGE PRESERVATION, M-21-022 (1UD, 1UE), I-495 OVER STATE ROUTE 109/MEDWAY ROAD | 3 | HIP-BR | $3,744,000 | $3,744,000 | $2,995,200 | $748,800 | ||
2026 | 613184 | Boston Region | Gloucester | GLOUCESTER- BRIDGE PRESERVATION, G-05-017 (2U8), STATE ROUTE 128/YANKEE DIVISION HIGHWAY OVER ANNISQUAM RIVER | 4 | HIP-BR | $15,081,560 | $15,081,560 | $12,065,248 | $3,016,312 | ||
2026 | 613274 | Boston Region | Foxborough | FOXBORO- BRIDGE PRESERVATION AT 6 BRIDGES ALONG THE I-95 CORRIDOR | 5 | HIP-BR | $5,278,000 | $5,278,000 | $4,222,400 | $1,055,600 | ||
2026 | 613649 | Boston Region | Braintree | BRAINTREE- QUINCY- RANDOLPH- BRIDGE PRESERVATION, B-21-029, Q-01-046, AND R-01-009, BRIDGES OVER I-93 & STATE ROUTE 28 | 6 | HIP-BR | $7,800,000 | $7,799,993 | $6,239,994 | $1,559,999 | ||
2026 | 613650 | Boston Region | Dedham | DEDHAM- BRIDGE PRESERVATION, D-05-002, GREENDALE AVENUE OVER CHARLES RIVER | 6 | HIP-BR | $2,154,286 | $2,154,284 | $1,723,427 | $430,857 | ||
Section 2A / Federal Aid Funded State Prioritized Reliability Projects | $48,189,356 | $39,586,202 | $8,603,154 | |||||||||
Bridge On-system NHS | $19,535,371 | $15,628,297 | $3,907,074 | |||||||||
2026 | 606449 | Boston Region | Cambridge | CAMBRIDGE- BRIDGE REPLACEMENT, C-01-008, FIRST STREET BRIDGE & C-01-040, LAND BOULEVARD/BROAD CANAL BRIDGE | 6 | NHPP-PEN | $13,832,000 | $13,832,000 | $11,065,600 | $2,766,400 | ||
2026 | 610782 | Boston Region | Multiple | DANVERS- MIDDLETON- BRIDGE REPLACEMENT, D-03-009=M-20-005, ANDOVER STREET (SR 114) OVER IPSWICH RIVER | 4 | NHPP-PEN | $5,703,371 | $5,703,371 | $4,562,697 | $1,140,674 | ||
Non-Interstate Pavement | $15,165,717 | $12,132,574 | $3,033,143 | |||||||||
2026 | 609399 | Boston Region | Randolph | RANDOLPH- RESURFACING AND RELATED WORK ON ROUTE 28 | 6 | NHPP | $7,194,377 | $7,194,377 | $5,755,502 | $1,438,875 | ||
2026 | 612050 | Boston Region | Multiple | BRAINTREE- WEYMOUTH- RESURFACING AND RELATED WORK ON ROUTE 3 | 6 | NHPP | $7,971,340 | $7,971,340 | $6,377,072 | $1,594,268 | ||
Safety Improvements | $10,347,168 | $9,312,451 | $1,034,717 | |||||||||
2026 | 611954 | Boston Region | Boston | BOSTON- GUIDE AND TRAFFIC SIGN REPLACEMENT ON I-90/I-93 WITHIN CENTRAL ARTERY/TUNNEL SYSTEM | 6 | HSIP | $2,333,968 | $2,333,968 | $2,100,571 | $233,397 | ||
2026 | 612599 | Boston Region | Lynn | LYNN- TARGETED SAFETY AND MULTIMODAL IMPROVEMENTS (PLAYBOOK PRIORITY CORRIDORS) | 4 | HSIP | $8,013,200 | $8,013,200 | $7,211,880 | $801,320 | ||
Highway Resiliency Improvement Program | $3,141,100 | $2,512,880 | $628,220 | |||||||||
2026 | 613099 | Boston Region | Boston | BOSTON- SLOPE STABILIZATION AND RELATED WORK ON I-93 | 6 | PRCT | $3,141,100 | $3,141,100 | $2,512,880 | $628,220 | ||
Section 2B / Federal Aid Funded State Prioritized Modernization Projects | $52,252,446 | $46,256,138 | $5,996,308 | |||||||||
Roadway Reconstruction | $35,703,894 | $32,133,505 | $3,570,389 | |||||||||
2026 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | NHPP-I | $300,942,837 | $29,229,180 | $26,306,262 | $2,922,918 | ||
2026 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | NFP-I | $300,942,837 | $6,474,714 | $5,827,243 | $647,471 | ||
Safe Routes to School | $7,710,632 | $6,168,506 | $1,542,126 | |||||||||
2026 | 610537 | Boston Region | Boston | BOSTON- ELLIS ELEMENTARY TRAFFIC CALMING (SRTS) | 6 | TAP | $2,705,058 | $2,705,058 | $2,164,046 | $541,012 | ||
2026 | 611997 | Boston Region | Newton | NEWTON- HORACE MANN ELEMENTARY SCHOOL IMPROVEMENTS (SRTS) | 6 | TAP | $861,238 | $861,237 | $688,990 | $172,247 | ||
2026 | 612001 | Boston Region | Medford | MEDFORD- MILTON FULLER ROBERTS ELEMENTARY SCHOOL (SRTS) | 4 | TAP | $1,020,484 | $1,020,484 | $816,387 | $204,097 | ||
2026 | 612804 | Boston Region | Dedham | DEDHAM- IMPROVEMENTS AT AVERY ELEMENTARY (SRTS) | 6 | TAP | $1,566,100 | $1,566,099 | $1,252,879 | $313,220 | ||
2026 | 612884 | Boston Region | Chelsea | CHELSEA- IMPROVEMENTS AT MARY C. BURKE ELEMENTARY (SRTS) | 6 | TAP | $1,557,754 | $1,557,754 | $1,246,203 | $311,551 | ||
Intersection Improvements | $8,837,920 | $7,954,128 | $883,792 | |||||||||
2026 | 611974 | Boston Region | Medford | MEDFORD- INTERSECTION IMPROVEMENTS AT MAIN STREET/SOUTH STREET, MAIN STREET/MYSTIC VALLEY PARKWAY RAMPS, AND MAIN STREET/MYSTIC AVENUE | 4 | VUS | $8,837,920 | $2,583,870 | $2,325,483 | $258,387 | ||
2026 | 611974 | Boston Region | Medford | MEDFORD- INTERSECTION IMPROVEMENTS AT MAIN STREET/SOUTH STREET, MAIN STREET/MYSTIC VALLEY PARKWAY RAMPS, AND MAIN STREET/MYSTIC AVENUE | 4 | HSIP | $8,837,920 | $6,254,050 | $5,628,645 | $625,405 | ||
Section 2C / Federal Aid Funded State Prioritized Expansion Projects | $3,428,355 | $2,742,684 | $685,671 | |||||||||
Bicycle and Pedestrian | $3,428,355 | $2,742,684 | $685,671 | |||||||||
2026 | 610680 | Boston Region | Natick | NATICK- LAKE COCHITUATE PATH | 3 | CMAQ | $3,428,355 | $3,428,355 | $2,742,684 | $685,671 | ||
Section 3B / Non-Federal Aid Funded | $123,954,368 | $0 | $123,954,368 | |||||||||
Bridge On-system NHS | $68,334,621 | $0 | $68,334,621 | |||||||||
2026 | 604564 | Boston Region | Maynard | MAYNARD- BRIDGE REPLACEMENT, M-10-004, ROUTE 62 (MAIN STREET) OVER THE ASSABET RIVER | 3 | NGBP | $6,036,680 | $6,036,680 | $0 | $6,036,680 | ||
2026 | 607684 | Boston Region | Braintree | BRAINTREE- BRIDGE REPLACEMENT, B-21-017, WASHINGTON STREET (ST 37) OVER MBTA/CSX RAILROAD | 6 | NGBP | $26,818,168 | $26,818,168 | $0 | $26,818,168 | ||
2026 | 612182 | Boston Region | Newton | NEWTON- BRIDGE REPLACEMENT, N-12-040, BOYLSTON STREET OVER GREEN LINE D | 6 | NGBP | $15,206,778 | $15,206,778 | $0 | $15,206,778 | ||
2026 | 612184 | Boston Region | Revere | REVERE- BRIDGE REPLACEMENT, R-05-015, REVERE BEACH PARKWAY OVER BROADWAY | 4 | NGBP | $20,272,995 | $20,272,995 | $0 | $20,272,995 | ||
NFA | $26,680,000 | $0 | $26,680,000 | |||||||||
2026 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | NFA | $300,942,837 | $26,680,000 | $0 | $26,680,000 | ||
Bridge On-system Non-NHS | $28,939,747 | $0 | $28,939,747 | |||||||||
2026 | 608952 | Boston Region | Chelsea | CHELSEA- BRIDGE SUPERSTRUCTURE REPLACEMENT C-09-013, WASHINGTON AVENUE, CARTER STREET & COUNTY ROAD/ROUTE 1 | 6 | NGBP | $22,217,165 | $22,217,165 | $0 | $22,217,165 | ||
2026 | 612178 | Boston Region | Natick | NATICK- BRIDGE REPLACEMENT, N-03-010, SPEEN STREET OVER RR MBTA/CSX | 3 | NGBP | $6,722,582 | $6,722,582 | $0 | $6,722,582 | ||
Federal Fiscal Year 2027 | $520,203,742 | $333,687,222 | $186,516,520 | |||||||||
Section 1A / Regionally Prioritized Projects | $154,195,126 | $123,956,101 | $30,239,025 | |||||||||
Roadway Reconstruction | $116,063,376 | $93,450,701 | $22,612,675 | |||||||||
2027 | 605743 | Boston Region | Ipswich | IPSWICH- RESURFACING & RELATED WORK ON CENTRAL & SOUTH MAIN STREETS | 4 | STBG | $11,728,698 | $6,000,000 | $4,800,000 | $1,200,000 | ||
2027 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | NHPP | $95,310,000 | $13,000,000 | $10,400,000 | $2,600,000 | ||
2027 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | STBG | $95,310,000 | $15,000,000 | $12,000,000 | $3,000,000 | ||
2027 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | TAP | $95,310,000 | $2,000,000 | $1,600,000 | $400,000 | ||
2027 | 608954 | Boston Region | Weston | WESTON- RECONSTRUCTION ON ROUTE 30 | 6 | STBG | $19,999,712 | $14,999,712 | $11,999,770 | $2,999,942 | ||
2027 | 608954 | Boston Region | Weston | WESTON- RECONSTRUCTION ON ROUTE 30 | 6 | TAP | $19,999,712 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2027 | 609252 | Boston Region | Lynn | LYNN- REHABILITATION OF ESSEX STREET | 4 | CMAQ | $19,698,640 | $5,500,000 | $4,400,000 | $1,100,000 | ||
2027 | 609252 | Boston Region | Lynn | LYNN- REHABILITATION OF ESSEX STREET | 4 | HSIP | $19,698,640 | $4,000,000 | $3,600,000 | $400,000 | ||
2027 | 609252 | Boston Region | Lynn | LYNN- REHABILITATION OF ESSEX STREET | 4 | STBG | $19,698,640 | $198,640 | $158,912 | $39,728 | ||
2027 | 609257 | Boston Region | Everett | EVERETT- RECONSTRUCTION OF BEACHAM STREET | 4 | HSIP | $10,954,656 | $1,000,000 | $900,000 | $100,000 | ||
2027 | 609257 | Boston Region | Everett | EVERETT- RECONSTRUCTION OF BEACHAM STREET | 4 | STBG | $10,954,656 | $8,054,656 | $6,443,725 | $1,610,931 | ||
2027 | 609257 | Boston Region | Everett | EVERETT- RECONSTRUCTION OF BEACHAM STREET | 4 | TAP | $10,954,656 | $1,900,000 | $1,520,000 | $380,000 | ||
2027 | 609437 | Boston Region | Multiple | SALEM- PEABODY- BOSTON STREET IMPROVEMENTS | 4 | STBG | $26,122,721 | $20,187,705 | $16,150,164 | $4,037,541 | ||
2027 | 609437 | Boston Region | Multiple | SALEM- PEABODY- BOSTON STREET IMPROVEMENTS | 4 | TAP | $26,122,721 | $5,935,016 | $4,748,013 | $1,187,003 | ||
2027 | 611983 | Boston Region | Chelsea | CHELSEA- PARK STREET & PEARL STREET RECONSTRUCTION | 6 | HSIP | $11,287,647 | $1,000,000 | $900,000 | $100,000 | ||
2027 | 611983 | Boston Region | Chelsea | CHELSEA- PARK STREET & PEARL STREET RECONSTRUCTION | 6 | STBG | $11,287,647 | $10,287,647 | $8,230,118 | $2,057,529 | ||
2027 | S12820 | Boston Region | BOSTON REGION - BIKESHARE SUPPORT SET ASIDE | STBG | $6,000,000 | $2,000,000 | $1,600,000 | $400,000 | ||||
Bicycle and Pedestrian | $12,499,750 | $9,999,800 | $2,499,950 | |||||||||
2027 | 609204 | Boston Region | Belmont | BELMONT- COMMUNITY PATH, BELMONT COMPONENT OF THE MCRT (PHASE I) | 4 | CMAQ | $20,499,750 | $1,499,750 | $1,199,800 | $299,950 | ||
2027 | 609204 | Boston Region | Belmont | BELMONT- COMMUNITY PATH, BELMONT COMPONENT OF THE MCRT (PHASE I) | 4 | STBG | $20,499,750 | $9,000,000 | $7,200,000 | $1,800,000 | ||
2027 | 609204 | Boston Region | Belmont | BELMONT- COMMUNITY PATH, BELMONT COMPONENT OF THE MCRT (PHASE I) | 4 | TAP | $20,499,750 | $2,000,000 | $1,600,000 | $400,000 | ||
Bridge On-system NHS | $16,632,000 | $13,305,600 | $3,326,400 | |||||||||
2027 | 612989 | Boston Region | Boston | BOSTON- BRIDGE PRESERVATION, B-16-066 (38D), CAMBRIDGE STREET OVER MBTA | 6 | NHPP | $16,632,000 | $16,632,000 | $13,305,600 | $3,326,400 | ||
Flex to FTA | $6,500,000 | $5,200,000 | $1,300,000 | |||||||||
2027 | S12113 | Boston Region | BOSTON REGION - TRANSIT TRANSFORMATION PROGRAM | CMAQ | $21,500,000 | $6,500,000 | $5,200,000 | $1,300,000 | ||||
Transit Grant Program | $2,500,000 | $2,000,000 | $500,000 | |||||||||
2027 | S12124 | Boston Region | Multiple | BOSTON REGION - COMMUNITY CONNECTIONS PROGRAM | CMAQ | $8,423,415 | $2,036,193 | $1,628,954 | $407,239 | |||
2027 | S12963 | Boston Region | Multiple | CHELSEA-REVERE- REGIONAL ON-DEMAND MICROTRANSIT PILOT PROJECT | CMAQ | $1,413,375 | $463,807 | $371,046 | $92,761 | |||
Section 1B / Earmark or Discretionary Grant Funded Projects | $7,762,241 | $6,838,144 | $924,097 | |||||||||
Bridge Off-system Local NB | $3,141,758 | $3,141,758 | $0 | |||||||||
2027 | 612076 | Boston Region | Topsfield | TOPSFIELD- BRIDGE REPLACEMENT, T-06-013, PERKINS ROW OVER MILE BROOK | 4 | BROFF | $3,141,758 | $3,141,758 | $3,141,758 | $0 | ||
Bridge On-system Non-NHS NB | $4,620,483 | $3,696,386 | $924,097 | |||||||||
2027 | 612099 | Boston Region | Ashland | ASHLAND- BRIDGE REPLACEMENT, A-14-006, CORDAVILLE ROAD OVER SUDBURY RIVER | 3 | HIP-BR | $4,620,483 | $4,620,483 | $3,696,386 | $924,097 | ||
Section 2A / Federal Aid Funded State Prioritized Reliability Projects | $179,097,542 | $147,713,675 | $31,383,867 | |||||||||
Bridge On-system NHS | $111,768,155 | $89,414,524 | $22,353,631 | |||||||||
2027 | 606728 | Boston Region | Boston | BOSTON- BRIDGE REPLACEMENT B-16-365, STORROW DRIVE OVER BOWKER RAMPS | 6 | NHPP | $108,054,000 | $10,000,000 | $8,000,000 | $2,000,000 | ||
2027 | 606728 | Boston Region | Boston | BOSTON- BRIDGE REPLACEMENT B-16-365, STORROW DRIVE OVER BOWKER RAMPS | 6 | NHPP-PEN | $108,054,000 | $54,236,956 | $43,389,565 | $10,847,391 | ||
2027 | 611987 | Boston Region | Cambridge | CAMBRIDGE- BRIDGE REPLACEMENT, C-01-026, MEMORIAL DRIVE OVER BROOKLINE STREET | 6 | NHPP | $49,283,338 | $25,022,802 | $20,018,242 | $5,004,560 | ||
2027 | 612519 | Boston Region | Boston | BOSTON- BRIDGE REPLACEMENT, B-16-165, BLUE HILL AVENUE OVER RAILROAD | 6 | NHPP | $33,524,397 | $22,508,397 | $18,006,718 | $4,501,679 | ||
Safety Improvements | $5,059,530 | $4,553,577 | $505,953 | |||||||||
2027 | 613121 | Boston Region | Everett | EVERETT- TARGETED MULTI-MODAL AND SAFETY IMPROVEMENTS ON ROUTE 16 (DESIGN ONLY) | 4 | HSIP | $5,059,530 | $5,059,530 | $4,553,577 | $505,953 | ||
Highway Resiliency Improvement Program | $4,332,177 | $3,465,742 | $866,435 | |||||||||
2027 | 613154 | Boston Region | Wellesley | WELLESLEY- DRAINAGE IMPROVEMENTS ALONG ROUTE 9 AND CULVERT REPLACEMENTS OVER BOULDER BROOK FOR FLOOD MITIGATION | 6 | PRCT | $4,332,177 | $4,332,177 | $3,465,742 | $866,435 | ||
Bridge Systematic Maintenance | $18,640,800 | $14,912,640 | $3,728,160 | |||||||||
2027 | 613275 | Boston Region | Multiple | BEVERLY- DANVERS- GLOUCESTER- BRIDGE PRESERVATION AT 5 BRIDGES CARRYING STATE ROUTE 128 | 4 | NHPP | $16,480,800 | $16,480,800 | $13,184,640 | $3,296,160 | ||
2027 | 613646 | Boston Region | Watertown | WATERTOWN- BRIDGE PRESERVATION, W-10-003, STATE ROUTE 16/GALEN STREET OVER CHARLES RIVER | 6 | NHPP | $2,160,000 | $2,160,000 | $1,728,000 | $432,000 | ||
Interstate Pavement | $39,296,880 | $35,367,192 | $3,929,688 | |||||||||
2027 | 613318 | Boston Region | Multiple | BURLINGTON- WOBURN- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95 | 4 | NHPP-I | $9,128,700 | $9,128,700 | $8,215,830 | $912,870 | ||
2027 | 613343 | Boston Region | Foxborough | FOXBOROUGH - INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95 | 5 | NHPP-I | $14,953,680 | $14,953,680 | $13,458,312 | $1,495,368 | ||
2027 | 613382 | Boston Region | Multiple | DEDHAM- NEEDHAM- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95 | 6 | NHPP-I | $15,214,500 | $15,214,500 | $13,693,050 | $1,521,450 | ||
Section 2B / Federal Aid Funded State Prioritized Modernization Projects | $45,089,554 | $37,984,184 | $7,105,370 | |||||||||
Roadway Reconstruction | $29,014,942 | $24,654,695 | $4,360,248 | |||||||||
2027 | 607977 | Boston Region | Multiple | HOPKINTON- WESTBOROUGH- RECONSTRUCTION OF I-90/I-495 INTERCHANGE | 3 | NFP-I | $300,942,837 | $14,427,409 | $12,984,668 | $1,442,741 | ||
2027 | 609527 | Boston Region | Reading | READING- IMPROVEMENTS ON I-95 | 4 | NHPP | $14,587,533 | $14,587,533 | $11,670,026 | $2,917,507 | ||
Safe Routes to School | $11,376,612 | $9,101,290 | $2,275,322 | |||||||||
2027 | 612100 | Boston Region | Revere | REVERE- IMPROVEMENTS AT BEACHMONT VETERANS ELEMENTARY (SRTS) | 4 | TAP | $351,341 | $351,341 | $281,073 | $70,268 | ||
2027 | 612816 | Boston Region | Brookline | BROOKLINE- IMPROVEMENTS AT WILLIAM H. LINCOLN SCHOOL (SRTS) | 6 | TAP | $955,020 | $955,021 | $764,017 | $191,004 | ||
2027 | 612889 | Boston Region | Sharon | SHARON- COTTAGE STREET SCHOOL IMPROVEMENTS (SRTS) | 5 | TAP | $3,709,491 | $3,709,491 | $2,967,593 | $741,898 | ||
2027 | 612894 | Boston Region | Framingham | FRAMINGHAM- IMPROVEMENTS AT HARMONY GROVE ELEMENTARY SCHOOL (SRTS) | 3 | TAP | $1,370,066 | $1,370,066 | $1,096,053 | $274,013 | ||
2027 | 613468 | Boston Region | Newton | NEWTON- IMPROVEMENTS AT PARKER STREET FOR THE OAK HILL MIDDLE SCHOOL (SRTS) | 6 | TAP | $1,492,169 | $1,492,169 | $1,193,735 | $298,434 | ||
2027 | 613477 | Boston Region | Holliston | HOLLISTON- LINDEN STREET IMPROVEMENTS AT ROBERT ADAMS MIDDLE SCHOOL (SRTS) | 3 | TAP | $1,012,500 | $1,012,500 | $810,000 | $202,500 | ||
2027 | 613564 | Boston Region | Reading | READING- OAKLAND ROAD AT READING MEMORIAL HIGH SCHOOL AND COOLIDGE MIDDLE SCHOOL (SRTS) | 4 | TAP | $2,486,024 | $2,486,024 | $1,988,819 | $497,205 | ||
Intersection Improvements | $4,698,000 | $4,228,200 | $469,800 | |||||||||
2027 | 612613 | Boston Region | Newton | NEWTON- INTERSECTION IMPROVEMENTS AT ROUTE 16 AND QUINOBEQUIN ROAD | 6 | HSIP | $4,698,000 | $4,698,000 | $4,228,200 | $469,800 | ||
Section 2C / Federal Aid Funded State Prioritized Expansion Projects | $21,493,898 | $17,195,118 | $4,298,780 | |||||||||
Bicycle and Pedestrian | $21,493,898 | $17,195,118 | $4,298,780 | |||||||||
2027 | 610660 | Boston Region | Multiple | SUDBURY- WAYLAND- MASS CENTRAL RAIL TRAIL (MCRT) | 3 | CMAQ | $3,916,363 | $3,916,363 | $3,133,090 | $783,273 | ||
2027 | 612499 | Boston Region | Medford | MEDFORD- SOUTH MEDFORD CONNECTOR BIKE PATH | 4 | CMAQ | $7,621,466 | $7,621,466 | $6,097,173 | $1,524,293 | ||
2027 | 612523 | Boston Region | Revere | REVERE- STATE ROAD BEACHMONT CONNECTOR | 4 | CMAQ | $8,263,382 | $8,263,382 | $6,610,706 | $1,652,676 | ||
2027 | 613082 | Boston Region | Medford | MEDFORD- WELLINGTON GREENWAY CONSTRUCTION (PHASE IV) | 4 | CMAQ | $1,692,687 | $1,692,687 | $1,354,150 | $338,537 | ||
Section 3B / Non-Federal Aid Funded | $112,565,381 | $0 | $112,565,381 | |||||||||
Bridge On-system Non-NHS | $112,565,381 | $0 | $112,565,381 | |||||||||
2027 | 605276 | Boston Region | Multiple | BEVERLY- SALEM- BRIDGE REPLACEMENT, B-11-005=S-01-013, KERNWOOD AVENUE OVER DANVERS RIVER AND B-11-001, BRIDGE STREET OVER BASS RIVER (HALL-WHITAKER DRAWBRIDGE) | 4 | NGBP | $88,805,268 | $88,805,268 | $0 | $88,805,268 | ||
2027 | 607420 | Boston Region | Natick | NATICK- SUPERSTRUCTURE REPLACEMENT, N-03-012, BODEN LANE OVER CSX/MBTA | 3 | NGBP | $11,407,315 | $11,407,315 | $0 | $11,407,315 | ||
2027 | 612196 | Boston Region | Braintree | BRAINTREE- BRIDGE REPLACEMENT, B-21-067, JW MAHER HIGHWAY OVER MONATIQUOT RIVER | 6 | NGBP | $12,352,798 | $12,352,798 | $0 | $12,352,798 | ||
Federal Fiscal Year 2028 | $455,148,861 | $368,407,280 | $86,741,581 | |||||||||
Section 1A / Regionally Prioritized Projects | $157,830,836 | $127,431,937 | $30,398,899 | |||||||||
Roadway Reconstruction | $124,935,651 | $100,690,134 | $24,245,517 | |||||||||
2028 | 605743 | Boston Region | Ipswich | IPSWICH- RESURFACING & RELATED WORK ON CENTRAL & SOUTH MAIN STREETS | 4 | STBG | $11,728,698 | $4,530,852 | $3,624,682 | $906,170 | ||
2028 | 605743 | Boston Region | Ipswich | IPSWICH- RESURFACING & RELATED WORK ON CENTRAL & SOUTH MAIN STREETS | 4 | TAP | $11,728,698 | $1,197,846 | $958,277 | $239,569 | ||
2028 | 606226 | Boston Region | Boston | BOSTON- RECONSTRUCTION OF RUTHERFORD AVENUE, FROM CITY SQUARE TO SULLIVAN SQUARE | 6 | NHPP | $197,759,449 | $12,000,000 | $9,600,000 | $2,400,000 | ||
2028 | 606226 | Boston Region | Boston | BOSTON- RECONSTRUCTION OF RUTHERFORD AVENUE, FROM CITY SQUARE TO SULLIVAN SQUARE | 6 | STBG | $197,759,449 | $19,500,000 | $15,600,000 | $3,900,000 | ||
2028 | 606226 | Boston Region | Boston | BOSTON- RECONSTRUCTION OF RUTHERFORD AVENUE, FROM CITY SQUARE TO SULLIVAN SQUARE | 6 | TAP | $197,759,449 | $2,000,000 | $1,600,000 | $400,000 | ||
2028 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | NHPP | $95,310,000 | $25,000,000 | $20,000,000 | $5,000,000 | ||
2028 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | STBG | $95,310,000 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2028 | 608158 | Boston Region | Multiple | WESTWOOD- NORWOOD- RECONSTRUCTION OF CANTON STREET TO UNIVERSITY DRIVE, INCLUDING REHAB OF N-25-032=W-31-018 | 6 | CMAQ | $22,854,847 | $4,000,000 | $3,200,000 | $800,000 | ||
2028 | 608158 | Boston Region | Multiple | WESTWOOD- NORWOOD- RECONSTRUCTION OF CANTON STREET TO UNIVERSITY DRIVE, INCLUDING REHAB OF N-25-032=W-31-018 | 6 | STBG | $22,854,847 | $8,854,847 | $7,083,878 | $1,770,969 | ||
2028 | 609246 | Boston Region | Lynn | LYNN- REHABILITATION OF WESTERN AVENUE (ROUTE 107) | 4 | HSIP | $45,897,600 | $5,000,000 | $4,500,000 | $500,000 | ||
2028 | 609246 | Boston Region | Lynn | LYNN- REHABILITATION OF WESTERN AVENUE (ROUTE 107) | 4 | STBG | $45,897,600 | $10,000,000 | $8,000,000 | $2,000,000 | ||
2028 | 610932 | Boston Region | Brookline | BROOKLINE- REHABILITATION OF WASHINGTON STREET | 6 | HSIP | $28,995,267 | $2,416,130 | $2,174,517 | $241,613 | ||
2028 | 610932 | Boston Region | Brookline | BROOKLINE- REHABILITATION OF WASHINGTON STREET | 6 | STBG | $28,995,267 | $5,000,000 | $4,000,000 | $1,000,000 | ||
2028 | 613145 | Boston Region | Wakefield | WAKEFIELD- COMPRHENSIVE DOWNTOWN TRANSPORTATION IMPROVEMENT PROJECT | 4 | CMAQ | $18,435,976 | $8,000,000 | $6,400,000 | $1,600,000 | ||
2028 | 613145 | Boston Region | Wakefield | WAKEFIELD- COMPRHENSIVE DOWNTOWN TRANSPORTATION IMPROVEMENT PROJECT | 4 | STBG | $18,435,976 | $8,435,976 | $6,748,781 | $1,687,195 | ||
2028 | 613145 | Boston Region | Wakefield | WAKEFIELD- COMPRHENSIVE DOWNTOWN TRANSPORTATION IMPROVEMENT PROJECT | 4 | TAP | $18,435,976 | $2,000,000 | $1,600,000 | $400,000 | ||
2028 | S12820 | Boston Region | BOSTON REGION - BIKESHARE SUPPORT SET ASIDE | STBG | $6,000,000 | $2,000,000 | $1,600,000 | $400,000 | ||||
Railroad Crossings | $836,339 | $836,339 | $0 | |||||||||
2028 | 608436 | Boston Region | Ashland | ASHLAND- REHABILITATION AND RAIL CROSSING IMPROVEMENTS ON CHERRY STREET | 3 | RRHE | $1,316,339 | $836,339 | $836,339 | $0 | ||
Bicycle and Pedestrian | $20,974,976 | $16,779,981 | $4,194,995 | |||||||||
2028 | 610666 | Boston Region | Swampscott | SWAMPSCOTT- RAIL TRAIL CONSTRUCTION | 4 | CMAQ | $8,624,000 | $6,992,000 | $5,593,600 | $1,398,400 | ||
2028 | 610666 | Boston Region | Swampscott | SWAMPSCOTT- RAIL TRAIL CONSTRUCTION | 4 | TAP | $8,624,000 | $1,632,000 | $1,305,600 | $326,400 | ||
2028 | 610691 | Boston Region | Natick | NATICK- COCHITUATE RAIL TRAIL EXTENSION, FROM MBTA STATION TO MECHANIC STREET | 3 | STBG | $7,492,849 | $7,492,849 | $5,994,279 | $1,498,570 | ||
2028 | 613088 | Boston Region | Malden | MALDEN- SPOT POND BROOK GREENWAY | 4 | CMAQ | $4,858,127 | $3,000,000 | $2,400,000 | $600,000 | ||
2028 | 613088 | Boston Region | Malden | MALDEN- SPOT POND BROOK GREENWAY | 4 | TAP | $4,858,127 | $1,858,127 | $1,486,502 | $371,625 | ||
Safety Improvements | $2,583,870 | $2,325,483 | $258,387 | |||||||||
2028 | 610932 | Boston Region | Brookline | BROOKLINE- REHABILITATION OF WASHINGTON STREET | 6 | VUS | $28,995,267 | $2,583,870 | $2,325,483 | $258,387 | ||
Flex to FTA | $6,500,000 | $5,200,000 | $1,300,000 | |||||||||
2028 | S12113 | Boston Region | BOSTON REGION - TRANSIT TRANSFORMATION PROGRAM | CMAQ | $21,500,000 | $6,500,000 | $5,200,000 | $1,300,000 | ||||
Transit Grant Program | $2,000,000 | $1,600,000 | $400,000 | |||||||||
2028 | S12124 | Boston Region | Multiple | BOSTON REGION - COMMUNITY CONNECTIONS PROGRAM | CMAQ | $8,423,415 | $2,000,000 | $1,600,000 | $400,000 | |||
Section 1B / Earmark or Discretionary Grant Funded Projects | $63,200,000 | $50,560,000 | $12,640,000 | |||||||||
Bridge On-system Non-NHS NB | $62,720,000 | $50,176,000 | $12,544,000 | |||||||||
2028 | 608397 | Boston Region | Gloucester | GLOUCESTER- BRIDGE RECONSTRUCTION, G-05-002, WESTERN AVENUE OVER BLYNMAN CANAL | 4 | HIP-BRRR | $62,720,000 | $62,720,000 | $50,176,000 | $12,544,000 | ||
Earmark Discretionary | $480,000 | $384,000 | $96,000 | |||||||||
2028 | 608436 | Boston Region | Ashland | ASHLAND- REHABILITATION AND RAIL CROSSING IMPROVEMENTS ON CHERRY STREET | 3 | HPP | $1,316,339 | $480,000 | $384,000 | $96,000 | ||
Section 2A / Federal Aid Funded State Prioritized Reliability Projects | $215,497,703 | $174,556,850 | $40,940,853 | |||||||||
Bridge Systematic Maintenance | $37,077,600 | $29,662,080 | $7,415,520 | |||||||||
2028 | 605091 | Boston Region | Natick | NATICK- BRIDGE PRESERVATION, N-03-032, N-03-033, N-03-034, N-03-035, RAMP A & B OVER ROUTE 9 & SPEEN STREET OVER RAMPS G & D | 3 | NHPP | $11,205,600 | $11,205,600 | $8,964,480 | $2,241,120 | ||
2028 | 613276 | Boston Region | Multiple | READING- WILMINGTON- BRIDGE PRESERVATION, W-38-028 (2HR, 2HT) AND R-03-011 (2HK), I-93 (NB/SB) OVER MBTA/B&M RAILROAD AND I-95/STATE ROUTE 128 | 4 | NHPP | $18,032,000 | $18,032,000 | $14,425,600 | $3,606,400 | ||
2028 | 613656 | Boston Region | Cambridge | CAMBRIDGE- BRIDGE PRESERVATION, C-01-038, MEMORIAL DRIVE (EB) OVER CHARLES RIVER | 6 | NHPP | $7,840,000 | $7,840,000 | $6,272,000 | $1,568,000 | ||
Bridge On-system NHS | $147,307,623 | $117,846,098 | $29,461,525 | |||||||||
2028 | 606728 | Boston Region | Boston | BOSTON- BRIDGE REPLACEMENT B-16-365, STORROW DRIVE OVER BOWKER RAMPS | 6 | NHPP-PEN | $108,054,000 | $43,817,044 | $35,053,635 | $8,763,409 | ||
2028 | 608396 | Boston Region | Multiple | LYNN- REVERE- BRIDGE RECONSTRUCTION, L-18-015=R-05-008, ROUTE 1A OVER SAUGUS RIVER | 4 | NHPP | $101,920,000 | $43,551,647 | $34,841,318 | $8,710,329 | ||
2028 | 611987 | Boston Region | Cambridge | CAMBRIDGE- BRIDGE REPLACEMENT, C-01-026, MEMORIAL DRIVE OVER BROOKLINE STREET | 6 | NHPP | $49,283,338 | $24,260,536 | $19,408,429 | $4,852,107 | ||
2028 | 612519 | Boston Region | Boston | BOSTON- BRIDGE REPLACEMENT, B-16-165, BLUE HILL AVENUE OVER RAILROAD | 6 | NHPP | $33,524,397 | $11,016,000 | $8,812,800 | $2,203,200 | ||
2028 | 613124 | Boston Region | Boston | BOSTON- DECK/SUPERSTRUCTURE REPLACEMENT, B-16-054 (4T2), BEACON STREET OVER I-90 (STRUCTURE 50, MILE 132.2) | 6 | NHPP-PEN | $40,837,135 | $9,486,278 | $7,589,022 | $1,897,256 | ||
2028 | 613125 | Boston Region | Boston | BOSTON- DECK/SUPERSTRUCTURE REPLACEMENT OF BRIDGE B-16-051 (4T5), MASS AVENUE OVER I-90 & MBTA (STRUCTURE 54, MILE 132.84)Ā | 6 | NHPP-PEN | $15,176,118 | $15,176,118 | $12,140,894 | $3,035,224 | ||
Safety Improvements | $6,440,000 | $5,796,000 | $644,000 | |||||||||
2028 | 610650 | Boston Region | Boston | BOSTON- SAFETY IMPROVEMENTS ON GALLIVAN BOULEVARD (ROUTE 203), FROM WASHINGTON STREET TO GRANITE AVENUE | 6 | HSIP | $6,440,000 | $6,440,000 | $5,796,000 | $644,000 | ||
Interstate Pavement | $15,146,880 | $13,632,192 | $1,514,688 | |||||||||
2028 | 613383 | Boston Region | Multiple | LYNNFIELD- WAKEFIELD- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95 | 4 | NHPP-I | $15,146,880 | $15,146,880 | $13,632,192 | $1,514,688 | ||
Non-Interstate Pavement | $9,525,600 | $7,620,480 | $1,905,120 | |||||||||
2028 | 613639 | Boston Region | Framingham | FRAMINGHAM- RESURFACING AND RELATED WORK ON ROUTE 9 | 3 | NHPP | $9,525,600 | $9,525,600 | $7,620,480 | $1,905,120 | ||
Section 2B / Federal Aid Funded State Prioritized Modernization Projects | $9,622,354 | $8,660,119 | $962,235 | |||||||||
Intersection Improvements | $9,622,354 | $8,660,119 | $962,235 | |||||||||
2028 | 608052 | Boston Region | Norwood | NORWOOD- INTERSECTION & SIGNAL IMPROVEMENTS AT US 1 (PROVIDENCE HIGHWAY) & MORSE STREET | 5 | HSIP | $1,668,001 | $1,668,001 | $1,501,201 | $166,800 | ||
2028 | 610665 | Boston Region | Stoneham | STONEHAM- INTERSECTION IMPROVEMENTS AT ROUTE 28 (MAIN STREET), NORTH BORDER ROAD AND SOUTH STREET | 4 | HSIP | $4,872,001 | $4,872,001 | $4,384,801 | $487,200 | ||
2028 | 612616 | Boston Region | Milton | MILTON- INTERSECTION IMPROVEMENTS AT ROUTE 138 AND BRADLEE ROAD | 6 | HSIP | $3,082,352 | $3,082,352 | $2,774,117 | $308,235 | ||
Section 2C / Federal Aid Funded State Prioritized Expansion Projects | $8,997,968 | $7,198,374 | $1,799,594 | |||||||||
Bicycle and Pedestrian | $8,997,968 | $7,198,374 | $1,799,594 | |||||||||
2028 | 612607 | Boston Region | Danvers | DANVERS- RAIL TRAIL WEST EXTENSION (PHASE 3) | 4 | CMAQ | $3,848,600 | $3,848,600 | $3,078,880 | $769,720 | ||
2028 | 613164 | Boston Region | Multiple | BOSTON- MILTON- NEW BRIDGE AND SHARED-USE PATH CONSTRUCTION OVER NEPONSET RIVER AT OSCEOLA STREET | 6 | CMAQ | $5,149,368 | $5,149,368 | $4,119,494 | $1,029,874 | ||
Federal Fiscal Year 2029 | $406,837,926 | $330,078,553 | $76,759,373 | |||||||||
Section 1A / Regionally Prioritized Projects | $160,243,467 | $129,273,967 | $30,969,500 | |||||||||
Roadway Reconstruction | $143,396,597 | $115,438,084 | $27,958,513 | |||||||||
2029 | 606226 | Boston Region | Boston | BOSTON- RECONSTRUCTION OF RUTHERFORD AVENUE, FROM CITY SQUARE TO SULLIVAN SQUARE | 6 | NHPP | $197,759,449 | $24,000,000 | $19,200,000 | $4,800,000 | ||
2029 | 606226 | Boston Region | Boston | BOSTON- RECONSTRUCTION OF RUTHERFORD AVENUE, FROM CITY SQUARE TO SULLIVAN SQUARE | 6 | STBG | $197,759,449 | $18,000,000 | $14,400,000 | $3,600,000 | ||
2029 | 606226 | Boston Region | Boston | BOSTON- RECONSTRUCTION OF RUTHERFORD AVENUE, FROM CITY SQUARE TO SULLIVAN SQUARE | 6 | TAP | $197,759,449 | $3,000,000 | $2,400,000 | $600,000 | ||
2029 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | NHPP | $95,310,000 | $20,000,000 | $16,000,000 | $4,000,000 | ||
2029 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | STBG | $95,310,000 | $8,518,065 | $6,814,452 | $1,703,613 | ||
2029 | 608158 | Boston Region | Multiple | WESTWOOD- NORWOOD- RECONSTRUCTION OF CANTON STREET TO UNIVERSITY DRIVE, INCLUDING REHAB OF N-25-032=W-31-018 | 6 | STBG | $22,854,847 | $10,000,000 | $8,000,000 | $2,000,000 | ||
2029 | 609246 | Boston Region | Lynn | LYNN- REHABILITATION OF WESTERN AVENUE (ROUTE 107) | 4 | HSIP | $45,897,600 | $3,208,065 | $2,887,259 | $320,807 | ||
2029 | 609246 | Boston Region | Lynn | LYNN- REHABILITATION OF WESTERN AVENUE (ROUTE 107) | 4 | STBG | $45,897,600 | $15,000,000 | $12,000,000 | $3,000,000 | ||
2029 | 610662 | Boston Region | Woburn | WOBURN- ROADWAY AND INTERSECTION IMPROVEMENTS AT WOBURN COMMON, ROUTE 38 (MAIN STREET), WINN STREET, PLEASANT STREET AND MONTVALE AVENUE | 4 | HSIP | $18,670,200 | $4,000,000 | $3,600,000 | $400,000 | ||
2029 | 610662 | Boston Region | Woburn | WOBURN- ROADWAY AND INTERSECTION IMPROVEMENTS AT WOBURN COMMON, ROUTE 38 (MAIN STREET), WINN STREET, PLEASANT STREET AND MONTVALE AVENUE | 4 | STBG | $18,670,200 | $5,335,200 | $4,268,160 | $1,067,040 | ||
2029 | 610932 | Boston Region | Brookline | BROOKLINE- REHABILITATION OF WASHINGTON STREET | 6 | STBG | $28,995,267 | $18,995,267 | $15,196,214 | $3,799,053 | ||
2029 | 612738 | Boston Region | Ipswich | IPSWICH- ARGILLA ROAD ROADWAY RECONSTRUCTION | 4 | STBG | $5,368,966 | $3,000,000 | $2,400,000 | $600,000 | ||
2029 | 612963 | Boston Region | Bellingham | BELLINGHAM- ROADWAY REHABILITATION OF ROUTE 126 (HARTFORD ROAD), FROM 800 NORTH OF THE I-495 NB OFF RAMP TO MEDWAY TL, INCLUDING B-06-017 | 3 | NHPP | $12,702,000 | $8,340,000 | $6,672,000 | $1,668,000 | ||
2029 | S12820 | Boston Region | BOSTON REGION - BIKESHARE SUPPORT SET ASIDE | STBG | $6,000,000 | $2,000,000 | $1,600,000 | $400,000 | ||||
Safety Improvements | $3,583,870 | $3,225,483 | $358,387 | |||||||||
2029 | 607981 | Boston Region | Somerville | SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION | 4 | VUS | $95,310,000 | $1,791,935 | $1,612,742 | $179,194 | ||
2029 | 609246 | Boston Region | Lynn | LYNN- REHABILITATION OF WESTERN AVENUE (ROUTE 107) | 4 | VUS | $45,897,600 | $1,791,935 | $1,612,742 | $179,194 | ||
Bicycle and Pedestrian | $4,263,000 | $3,410,400 | $852,600 | |||||||||
2029 | 613319 | Boston Region | Multiple | SUDBURY- FRAMINGHAM- BIKE PATH CONSTRUCTION OF BRUCE FREEMAN RAIL TRAIL, FROM THE SUDBURY DIAMOND RAILROAD CROSSING TO EATON ROAD WEST | 3 | CMAQ | $8,526,000 | $4,263,000 | $3,410,400 | $852,600 | ||
Flex to FTA | $6,500,000 | $5,200,000 | $1,300,000 | |||||||||
2029 | S12113 | Boston Region | BOSTON REGION - TRANSIT TRANSFORMATION PROGRAM | CMAQ | $21,500,000 | $6,500,000 | $5,200,000 | $1,300,000 | ||||
Transit Grant Program | $2,500,000 | $2,000,000 | $500,000 | |||||||||
2029 | S12124 | Boston Region | Multiple | BOSTON REGION - COMMUNITY CONNECTIONS PROGRAM | CMAQ | $8,423,415 | $2,500,000 | $2,000,000 | $500,000 | |||
Section 2A / Federal Aid Funded State Prioritized Reliability Projects | $188,146,479 | $152,919,598 | $35,226,881 | |||||||||
Bridge On-system NHS | $132,366,857 | $105,893,486 | $26,473,371 | |||||||||
2029 | 608396 | Boston Region | Multiple | LYNN- REVERE- BRIDGE RECONSTRUCTION, L-18-015=R-05-008, ROUTE 1A OVER SAUGUS RIVER | 4 | NHPP | $101,920,000 | $41,016,000 | $32,812,800 | $8,203,200 | ||
2029 | 612634 | Boston Region | Somerville | SOMERVILLE- BRIDGE REPLACEMENT, S-17-024, ROUTE 28/MCGRATH HWY OVER SOMERVILLE AVE EXT & MBTA | 4 | NHPP-PEN | $97,206,144 | $30,000,000 | $24,000,000 | $6,000,000 | ||
2029 | 613124 | Boston Region | Boston | BOSTON- DECK/SUPERSTRUCTURE REPLACEMENT, B-16-054 (4T2), BEACON STREET OVER I-90 (STRUCTURE 50, MILE 132.2) | 6 | NHPP-PEN | $40,837,135 | $31,350,857 | $25,080,686 | $6,270,171 | ||
2029 | 613130 | Boston Region | Boston | BOSTON- BRIDGE REPLACEMENT, B-16-033, MORRISSEY BOULEVARD OVER DORCHESTER BAY | 6 | NHPP-PEN | $180,854,486 | $30,000,000 | $24,000,000 | $6,000,000 | ||
Non-Interstate Pavement | $13,787,409 | $11,029,927 | $2,757,482 | |||||||||
2029 | 608495 | Boston Region | Multiple | CONCORD- LEXINGTON- LINCOLN- RESURFACING AND RELATED WORK ON ROUTE 2A | 4 | NHPP | $5,067,399 | $5,067,399 | $4,053,919 | $1,013,480 | ||
2029 | 612046 | Boston Region | Gloucester | GLOUCESTER- RESURFACING ON ROUTE 128 | 4 | NHPP | $4,557,060 | $4,557,060 | $3,645,648 | $911,412 | ||
2029 | 613640 | Boston Region | Natick | NATICK- RESURFACING AND RELATED WORK ON ROUTE 9 | 3 | NHPP | $4,162,950 | $4,162,950 | $3,330,360 | $832,590 | ||
Safety Improvements | $7,215,751 | $6,494,176 | $721,575 | |||||||||
2029 | 610675 | Boston Region | Chelsea | CHELSEA- RECONSTRUCTION OF SPRUCE STREET, FROM EVERETT AVENUE TO WILLIAMS STREET | 6 | HSIP | $7,215,751 | $7,215,751 | $6,494,176 | $721,575 | ||
Bridge Off-system | $2,889,387 | $2,311,510 | $577,877 | |||||||||
2029 | 613108 | Boston Region | Quincy | QUINCY- SUPERSTRUCTURE REPLACEMENT, Q-01-038 (3FG), STEDMAN STREET OVER I-93/US-1/STATE ROUTE 3 | 6 | STBG-BR-Off | $2,889,387 | $2,889,387 | $2,311,510 | $577,877 | ||
Highway Resiliency Improvement Program | $15,078,675 | $12,062,940 | $3,015,735 | |||||||||
2029 | 613162 | Boston Region | Littleton | LITTLETON- BRIDGE REPLACEMENT, L-13-008, ROUTE 119 OVER BEAVER BROOK AND CAUSEWAY IMPROVEMENT FOR WILDLIFE | 3 | PRCT | $15,078,675 | $15,078,675 | $12,062,940 | $3,015,735 | ||
Interstate Pavement | $16,808,400 | $15,127,560 | $1,680,840 | |||||||||
2029 | 613356 | Boston Region | Sharon | SHARON- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95 | 5 | NHPP-I | $16,808,400 | $16,808,400 | $15,127,560 | $1,680,840 | ||
Section 2B / Federal Aid Funded State Prioritized Modernization Projects | $39,759,580 | $32,934,268 | $6,825,312 | |||||||||
Intersection Improvements | $11,266,036 | $10,139,432 | $1,126,604 | |||||||||
2029 | 607748 | Boston Region | Acton | ACTON- INTERSECTION & SIGNAL IMPROVEMENTS ON SR 2 & SR 111 (MASSACHUSETTS AVENUE) AT PIPER ROAD & TAYLOR ROAD | 3 | HSIP | $11,266,036 | $11,266,036 | $10,139,432 | $1,126,604 | ||
Roadway Reconstruction | $28,493,544 | $22,794,835 | $5,698,709 | |||||||||
2029 | 610543 | Boston Region | Multiple | REVERE- MALDEN- IMPROVEMENTS AT ROUTE 1 (NB) (PHASE 1) | 4 | NHPP | $8,363,600 | $8,363,600 | $6,690,880 | $1,672,720 | ||
2029 | 612615 | Boston Region | Multiple | CANTON- MILTON- ROADWAY RECONSTRUCTION ON ROUTE 138, FROM ROYALL STREET TO DOLLAR LANE | 6 | NHPP | $20,129,944 | $20,129,944 | $16,103,955 | $4,025,989 | ||
Section 2C / Federal Aid Funded State Prioritized Expansion Projects | $18,688,400 | $14,950,720 | $3,737,680 | |||||||||
Bicycle and Pedestrian | $18,688,400 | $14,950,720 | $3,737,680 | |||||||||
2029 | 613163 | Boston Region | Lynnfield | LYNNFIELD- WAKEFIELD- RAIL TRAIL CONSTRUCTION | 4 | CMAQ | $38,491,410 | $10,000,000 | $8,000,000 | $2,000,000 | ||
2029 | 613654 | Boston Region | Framingham | FRAMINGHAM- BIKE PATH CONSTRUCTION OF BRUCE FREEMAN RAIL TRAIL, FROM EATON ROAD WEST TO FROST STREET | 3 | CMAQ | $8,688,400 | $8,688,400 | $6,950,720 | $1,737,680 |
Table 3-8
FFYs 2025ā29 TIP Transit Table (MBTA Federal Capital Program)
Federal Funding Program | ALI | 2025 | 2026 | 2027 | 2028 | 2029 | FFY25-29 Total (Federal) | FFY25-29 Total (Incl. Match) |
5307 | $197,611,190 | $202,682,910 | $202,682,910 | $202,682,910 | $202,682,910 | $1,008,342,830 | $1,260,428,538 | |
Bridge & Tunnel ProgramĀ Ā | 12.24.05 | $11,200,000 | $16,200,000 | $16,200,000 | $16,200,000 | $16,200,000 | $76,000,000 | $95,000,000 |
Revenue Vehicle ProgramĀ | 12.12.00 | $111,912,814 | $106,547,237 | $106,547,237 | $106,547,237 | $106,547,237 | $538,101,764 | $672,627,205 |
Signals/Systems Upgrade ProgramĀ | 12.63.01 | $16,780,660 | $39,114,766 | $39,114,766 | $39,114,766 | $39,114,766 | $173,239,722 | $216,549,653 |
Stations and Facilities ProgramĀ | 12.34.00 | $20,217,716 | $40,820,907 | $40,820,907 | $40,820,907 | $40,820,907 | $183,501,344 | $229,376,680 |
Preventive Maintenance | 12.7A.00 | $37,500,000 | $0 | $0 | $0 | $0 | $37,500,000 | $46,875,000 |
5337 | $236,571,519 | $241,684,814 | $241,684,814 | $241,684,814 | $241,684,814 | $1,203,310,775 | $1,504,138,468 | |
Bridge & Tunnel ProgramĀ Ā | 12.24.05 | $24,143,068 | $116,461,076 | $116,461,076 | $116,461,076 | $116,461,076 | $489,987,372 | $612,484,215 |
Revenue Vehicle ProgramĀ | 12.12.00 | $0 | $41,419,590 | $41,419,590 | $41,419,590 | $41,419,590 | $165,678,358 | $207,097,948 |
Signals/Systems Upgrade ProgramĀ | 12.63.01 | $62,621,955 | $20,166,816 | $20,166,816 | $20,166,816 | $20,166,816 | $143,289,218 | $179,111,523 |
Stations and Facilities ProgramĀ | 12.34.00 | $43,943,996 | $63,637,332 | $63,637,332 | $63,637,332 | $63,637,332 | $298,493,326 | $373,116,657 |
Preventive Maintenance | 12.7A.00 | $105,862,500 | $0 | $0 | $0 | $0 | $105,862,500 | $132,328,125 |
5339 | $6,261,816 | $6,416,908 | $6,416,908 | $6,416,908 | $6,416,908 | $31,929,448 | $39,911,811 | |
Bus ProgramĀ | 11.14.00 | $6,261,816 | $6,416,908 | $6,416,908 | $6,416,908 | $6,416,908 | $31,929,448 | $39,911,811 |
FFY25-29 FTA Formula Funding | $440,444,525 | $450,784,632 | $450,784,632 | $450,784,632 | $450,784,632 | $2,243,583,053 | $2,804,478,816 | |
Other Federal | $285,385,333 | $162,500,000 | $162,500,000 | $162,500,000 | $162,500,000 | $935,385,333 | $944,835,333 | |
RRIF Financing - PTC/ATC/Fiber | 12.63.01 | $100,085,333 | $0 | $0 | $0 | $0 | $100,085,333 | $100,085,333 |
RRIF/TIFIA Financing Program (Potential) | 12.24.05 | $147,500,000 | $162,500,000 | $162,500,000 | $162,500,000 | $162,500,000 | $797,500,000 | $797,500,000 |
Columbus Ave. Bus Lane Ph. II (CMAQ) | 11.23.01 | $6,000,000 | $0 | $0 | $0 | $0 | $6,000,000 | $7,500,000 |
Jackson Sq. Station Access Impr. (CMAQ) | 12.34.02 | $17,000,000 | $0 | $0 | $0 | $0 | $17,000,000 | $21,250,000 |
Rail Transformation - Early Action CMAQ) | 12.24.03 | $4,800,000 | $0 | $0 | $0 | $0 | $4,800,000 | $6,000,000 |
Central Station Accessibility Project | 12.33.02 | $4,000,000 | $0 | $0 | $0 | $0 | $4,000,000 | $5,000,000 |
Nubian Square Bus Circulation Improv. | 12.33.01 | $4,000,000 | $0 | $0 | $0 | $0 | $4,000,000 | $5,000,000 |
Pedal & Park System Modernization | 12.43.42 | $2,000,000 | $0 | $0 | $0 | $0 | $2,000,000 | $2,500,000 |
FFY25-29 Total Federal Funding | $725,829,858 | $613,284,632 | $613,284,632 | $613,284,632 | $613,284,632 | $3,178,968,386 | $3,749,314,149 | |
Note: | ||||||||
FTA formula funds (5307, 5337 and 5339) are based on estimated apportionments for FFY25-29.Ā Ā | ||||||||
TIP programs and projects are based on the draft FY 2025-29 CIP and planned federal obligations as of April 2024.Ā Adjustments may be made to federal projects and budgets as the FY 2025-29 CIP is finalized.Ā | ||||||||
The Activity Line Item (ALI) codes are preliminary only and generally reflect the bulk of the TIP program. Within a program there may be several different ALI codes used.Ā | ||||||||
RRIF loan funding for the PTC/ATC/Fiber Resiliency project is based on the currently planned drawdown schedule and is subject to change. | ||||||||
RRIF/TIFIA financing program funding is an initial estimate and will be refined as projects are identified and loans are finalized with the Build America Bureau. |
Table 3-9
FFYs 2025ā29 TIP Transit Table (MBTA Federal Capital Program ā Project List and Descriptions [80% Federal Share])
Funds | TIP Program | CIP ID# | Project Name | FFY 2024 | FFY 2025-2029 | Total (Federal) | Project Description |
FTA Formula Funds (5307, 5337, 5339) | |||||||
5307 - Bridge and Tunnel | |||||||
5307 | Bridge and Tunnel | P0014 | Merrimack River Bridge | $0 | $800,000 | $800,000 | Rehabilitation, strengthening, and painting of the superstructure of the Merrimack River and Washington Street Bridges. Includes repairs to stone piers, substructure, scour countermeasures, and replacement of bearings. |
5307 | Bridge and Tunnel | P1107 | Bridge Program Pipeline - Rehabilitation, Repair and Replacement | $0 | $75,200,000 | $75,200,000 | This program uses information provided through the bridge inspection and load rating program to design and construct prioritized bridge rehabilitation, repair, or replacement projects.Ā |
$0 | $76,000,000 | $76,000,000 | |||||
5307 - Revenue Vehicles | |||||||
5307 | Revenue Vehicles | P0369 | Green Line Type 10 Vehicle Replacement Program | $20,117,766 | $327,554,314 | $347,672,080 | Procurement of 102 new fully-accessible light rail vehicles and related infrastructure improvements to replace the existing Type 7 and Type 8 fleets, with additional optional cars available in the contract to support increased system capacity. |
5307 | Revenue Vehicles | P0618 | Procurement of 40ft Enhanced Electric Hybrid Buses | $0 | $109,093,636 | $109,093,636 | Procurement of 460 40ft Enhanced Electric Hybrid (EEH) buses to replace 310 40ft diesel buses purchased in 2006-2008 and support more reliable, efficient, and sustainable operations. Includes vehicle testing, warranty, and inspection. |
5307 | Revenue Vehicles | P0649 | Option Order Procurement of New Flyer Hybrid 40ft Buses | $239,140 | $0 | $239,140 | Procurement of 194 40ft buses with hybrid propulsion to replace an aging fleet and improve fuel economy. |
5307 | Revenue Vehicles | P0652 | Procurement of 100 Bi-Level Commuter Rail Coaches | $0 | $35,076,265 | $35,076,265 | Procurement of 100 Bi-Level Commuter Rail coaches to replace aging single-level coaches, expand capacity from 120 to 180 passengers per coach, reduce number of coaches required, and mitigate operational bottlenecks. |
5307 | Revenue Vehicles | P0860 | Hybrid Bus Overhaul (New Flyer XDE40 - SR 1881) | $0 | $1,440,000 | $1,440,000 | Midlife overhaul of major systems and components (e.g., engine, battery upgrade, drive unit, cooling systems, axles, brakes) of 60 40ft BAE hybrid buses to ensure reliable and safe operations and to meet FTA service life requirements. |
5307 | Revenue Vehicles | P0911 | Hybrid Bus Overhaul (New Flyer XDE40 - SR1983) | $16,598,573 | $36,617,549 | $53,216,122 | Midlife overhaul of major systems and components of 156 40ft hybrid buses to ensure reliable and safe operations that meet FTA requirements. Also includes condition assessment activities for 175 40ft CNG buses, and 45 60ft hybrid buses.Ā |
5307 | Revenue Vehicles | P1154 | CNG Bus Overhaul (New Flyer XN40 - SR 1982) | $28,000,000 | $0 | $28,000,000 | Planning for the midlife overhaul of 175 40-foot New Flyer CNG buses delivered 2016 to 2017. These buses require overhaul of major systems and components to ensure continued reliable and safe operations and to meet FTA service life requirements. |
5307 | Revenue Vehicles | P1162 | Reliability Centered Maintenance - Blue, Orange and Red Line | $0 | $28,320,000 | $28,320,000 | Improvements to trucks, brakes, motors, current collectors, propulsion, and auxiliary fuses on the Blue Line and improvements to propulsion, brakes, HVAC, and doors on the Red and Orange Lines. |
$64,955,479 | $538,101,764 | $603,057,243 | |||||
5307 - Signals and Systems | |||||||
5307 | Signals and Systems | P0285 | Signal Program - Red/Orange Line | $0 | $71,578,427 | $71,578,427 | Replacement and upgrade of signal equipment on the Red and Orange Lines. Includes renewal of track circuit modules using latest digital audio frequency technology and replacement of wayside equipment. |
5307 | Signals and Systems | P0857 | Mattapan HSL Transformation | $0 | $69,861,295 | $69,861,295 | State of good repair and accessibility improvements, power upgrades, and other infrastructure investments on the Mattapan Line.Ā |
5307 | Signals and Systems | P0912 | Systemwide Tunnel Flood Mitigation Program | $0 | $5,600,000 | $5,600,000 | Planning, training, and infrastructure improvements to make the tunnel network more resilient to flooding exposures due to storm surge, precipitation, and sea level rise. |
5307 | Signals and Systems | P1210 | PILC-EPR Medium Voltage Cable Replacement Program | $0 | $11,800,000 | $11,800,000 | Replacement of medium voltage AC cables that are beyond their useful life between traction power substations to maintain a state of good repair and reduce lead exposure risk to employees. |
5307 | Signals and Systems | P1212 | Systemwide 15kV Feeder and Duct Bank Replacement | $0 | $7,200,000 | $7,200,000 | Design and systemwide replacement of cables with Paper Insulated Lead Covered (PILC) feeders with new cables containing Ethylene Propylene Rubber (EPR) feeders to increase employee safety and power system resiliency.Ā |
5307 | Signals and Systems | P1213 | Systemwide SCADA Equipment Upgrade | $0 | $7,200,000 | $7,200,000 | Equipment and fiber optic network upgrades to the Supervisory Control and Data Acquisition (SCADA) system that controls critical power infrastructure. Upgrades incl. a new master terminal, programmable logic controllers, and remote terminal units.Ā Ā |
5307 | Signals and Systems | P1255 | Track Improvement Plan - Green and Blue LinesĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā | $20,775,823 | $0 | $20,775,823 | Implementation of the MBTA Track Improvement Plan to remove speed restrictions on the Green and Blue Lines. |
5307 | Signals and Systems | P1263 | Track Improvement Program - Red Line | $147,976,778 | $0 | $147,976,778 | Implementation of the MBTA Track Improvement Plan to remove speed restrictions on the Red Line. |
$168,752,601 | $173,239,722 | $341,992,323 | |||||
5307 - Stations and Facilities | |||||||
5307 | Stations and Facilities | P0066a | Quincy Adams Accessibility Improvements | $126,633 | $0 | $126,633 | Replacement of three existing elevators and addition of new elevator at Quincy Adams, according to ADA/BCIL requirements. Also includes upgrades to mechanical, communication, and safety systems, as well as wayfinding signage. |
5307 | Stations and Facilities | P0066e | Harvard/Central Elevator | $400,000 | $0 | $400,000 | Replacement of existing station elevator No. 821 at Harvard Square and No. 861 at Central Square on the Red Line, per ADA/BCIL requirements. Also includes replacement of central escalator No. 360. |
5307 | Stations and Facilities | P0066g | Downtown Crossing Elevator Phase 1 | $72,000 | $0 | $72,000 | Installation of two new elevators at Downtown Crossing to meet ADA and BCIL requirements. Includes exit gate improvements, creation of ‘points of safety’ with fire/smoke rated wall and door assemblies, and a new fire alarm system. |
5307 | Stations and Facilities | P0075 | Elevator Program Multiple Location Design | $6,632,106 | $20,636,654 | $27,268,761 | Design and some construction work for the replacement of elevators and/or addition of new, redundant elevators and related wayfinding amenities at transit stations. |
5307 | Stations and Facilities | P0104 | Charlestown Bus - Seawall Rehabilitation | $2,000,000 | $0 | $2,000,000 | Stabilization of the Mystic River shoreline and replacement of existing seawall to protect Charlestown Bus Facility from flooding. Includes a collaboration with Massachusetts DCR to build a multi-use public path along the seawall. |
5307 | Stations and Facilities | P0165 | Harvard Square Busway Repairs | $993,026 | $0 | $993,026 | Rehabilitation of roadway, lighting, signage, drainage, and catenary systems in the Harvard busway and accessibility upgrades to ensure near level boarding for the 71 and 73 buses.Ā |
5307 | Stations and Facilities | P0671a | Quincy Bus Facility Modernization | $52,521,372 | $42,528,597 | $95,049,968 | Relocation and replacement of the Quincy Bus Maintenance Facility. The new, modernized facility will expand capacity and includes the infrastructure necessary to support the MBTA's first battery-electric bus (BEB) fleet. |
5307 | Stations and Facilities | P0671b | Arborway Bus Facility - Design Funding | $0 | $22,320,000 | $22,320,000 | Design funding to support the construction of a new Arborway bus facility to accommodate battery electric bus (BEB) infrastructure and bus electrification. |
5307 | Stations and Facilities | P0671c | North Cambridge Bus Facility Retrofit | $30,928,812 | $0 | $30,928,812 | Renovation of North Cambridge facility to support conversion to battery electric bus (BEB) fleets and bus electrification. |
5307 | Stations and Facilities | P0912a | Airport Tunnel Portal Flood Protection | $0 | $16,398,322 | $16,398,322 | Addition of floodgates and large steel doors to the entrance of the Blue Line tunnel at the tunnel's Airport Portal to prevent flooding. Includes updates to pump rooms and traction power systems.Ā |
5307 | Stations and Facilities | P0912b | Systemwide Pump Room Upgrades | $0 | $1,920,000 | $1,920,000 | Design phase funding for state of good repair improvements to rapid transit and Silver Line tunnel pump rooms, including state of good repair and SCADA upgrades. |
5307 | Stations and Facilities | P1011 | Green Line Extension Vehicle Maintenance Facility Modifications & Upgrades | $0 | $9,943,729 | $9,943,729 | Design and installation of a new hoist at the Green Line Extension (GLX) Vehicle Maintenance Facility to accommodate the future Type 10 fleet. |
5307 | Stations and Facilities | P1103 | Reservoir Yard and Non-Revenue Track Optimization and Reconfiguration | $0 | $24,424,868 | $24,424,868 | Reconfiguration of various track elements at Reservoir, including the lower west yard, East/West Wye, Chestnut Hill Avenue connection, B-branch connection, and non-revenue track around Cleveland Circle. |
5307 | Stations and Facilities | P1216 | Everett Building 2 Floor Repairs | $0 | $15,031,457 | $15,031,457 | Repairs to the heavily deteriorated structure on the first floor of Everett's Building 2 facility that supports heavy rail service. |
5307 | Stations and Facilities | P1225 | Systemwide Escalator and Elevator Replacement Program | $0 | $12,000,000 | $12,000,000 | Replacement of escalators and elevators systemwide that are in poor condition, have limited parts available, and require replacement as identified in the MBTA's 20-Year Vertical Transportation Capital Plan. |
5307 | Stations and Facilities | P1232 | Green Line D Branch Enhanced Accessibility Improvements | $0 | $18,297,716 | $18,297,716 | Accessibility improvements on the Green Line D Branch to improve existing station entrances and increase accessibility. |
$93,673,949 | $183,501,344 | $277,175,293 | |||||
5307 - Preventive Maintenance | |||||||
5307 | Preventive Maintenance | N/A | Preventive Maintenance | $12,500,000 | $37,500,000 | $50,000,000 | Preventive maintenance activities eligible for FTA reimbursement. |
$12,500,000 | $37,500,000 | $50,000,000 | |||||
5337 - Bridge and Tunnel | |||||||
5337 | Bridge and Tunnel | P0006 | Gloucester Drawbridge Replacement | $2,028,934 | $0 | $2,028,934 | Replacement of Gloucester Drawbridge on the Rockport Line. The new bridge will consist of a moveable bascule span with two independent barrels, two spans of precast concrete box beams, a new steel superstructure, and a new micro-pile abutment. |
5337 | Bridge and Tunnel | P0008 | Emergency Bridge Design / Inspection & Rating | $1,796,261 | $0 | $1,796,261 | Funding to support as-needed emergency design, inspection, and rating of bridges. |
5337 | Bridge and Tunnel | P0009 | Bridges - Design | $4,479,231 | $4,333,605 | $8,812,836 | Design funding to support the repair, rehabilitation, and replacement of bridges across the system.Ā |
5337 | Bridge and Tunnel | P0018 | North Station Draw 1 Bridge Replacement | $40,247,016 | $409,290,315 | $449,537,332 | Replacement of North Station Draw 1 bridge structures and control tower. Includes construction of three new vertical lift bridges, and extension of existing station platform to accommodate track 11 and 12. |
5337 | Bridge and Tunnel | P0495 | Bridge Bundling Contract | $20,800,000 | $0 | $20,800,000 | Replacement of six Commuter Rail bridges at Intervale Rd. in Weston; Bacon St. in Wellesley; High Line Bridge in Somerville; Lynn Fells Parkway in Melrose; Parker St. in Lawrence; and Commercial St. in Lynn. |
5337 | Bridge and Tunnel | P0551 | Longfellow Approach | $0 | $41,902,447 | $41,902,447 | Rehabilitation of Longfellow Approach viaduct, Span 1 of the Longfellow Bridge, and station platforms at Charles/MGH Station. Includes new track, power, communication and signal systems, and additional emergency egress and redundant elevators. |
5337 | Bridge and Tunnel | P0552 | Dorchester Avenue Bridge | $8,000,000 | $0 | $8,000,000 | Replacement of Dorchester Avenue Bridge and installation of a new tunnel roof beneath the bridge. |
5337 | Bridge and Tunnel | P0627 | Systemwide Bridge Inspection and Rating | $17,285,716 | $18,461,005 | $35,746,721 | Program to support in-depth inspection and load rating of MBTA-owned bridges at regular intervals. Load ratings are used to establish a systemwide priority list of bridge repairs, rehabilitation, and replacement. |
5337 | Bridge and Tunnel | P0892 | Saugus Drawbridge Replacement | $8,000,000 | $0 | $8,000,000 | Design of Saugus Drawbridge replacement on the Newburyport/Rockport Line. The new bridge would include a widened approach embankment, a new control house, signal upgrades, and relocation of submerged utilities. |
5337 | Bridge and Tunnel | P0907 | East Street Bridge Replacement (Dedham) | $16,000,000 | $0 | $16,000,000 | Replacement of East Street bridge carrying the Franklin Line in Dedham. The new bridge will feature improved vertical and horizontal clearance, improved roadway features, and improved pedestrian and vehicle access to East Street. |
5337 | Bridge and Tunnel | P1107 | Bridge Program Pipeline - Rehabilitation, Repair and Replacement | $16,000,000 | $0 | $16,000,000 | This program uses information provided through the bridge inspection and load rating program to design and construct prioritized bridge rehabilitation, repair, or replacement projects.Ā |
5337 | Bridge and Tunnel | P1115 | South Elm Street Bridge Replacement | $4,095,886 | $0 | $4,095,886 | Replacement of South Elm Street bridge on the Haverhill Line serving Commuter Rail, Downeaster, and Pan Am freight trains. |
5337 | Bridge and Tunnel | P1116 | Systemwide Culvert Inspection and Load Rating | $0 | $10,000,000 | $10,000,000 | Inventory, inspection, and load rating of the MBTA's approx. 1,300 culverts supporting in-service structures systemwide. The scope of work includes an initial inspection to establish baseline condition, followed by inspection every five years.Ā Ā Ā |
5337 | Bridge and Tunnel | R0074 | Tunnel Inspection Systemwide | $5,243,025 | $6,000,000 | $11,243,025 | Ongoing inspection and rating of Red Line, Orange Line, Green Line, and Blue Line tunnels.Ā |
$143,976,069 | $489,987,372 | $633,963,441 | |||||
5337 - Revenue Vehicles | |||||||
5337 | Revenue Vehicles | P0239 | F40 Commuter Rail Locomotive Overhaul | $35,391,580 | $0 | $35,391,580 | Overhaul of 37 F40 Commuter Rail locomotives to improve reliability and reduce risk of unplanned maintenance. |
5337 | Revenue Vehicles | P0370 | Green Line Train Protection | $0 | $25,221,545 | $25,221,545 | Procurement and installation of on-board and wayside equipment for a train protection and information system on the Green Line to mitigate red signal violations, train-to-train collisions, derailments, and intrusions into work zones. |
5337 | Revenue Vehicles | P0918 | Rail Transformation - Future Rolling Stock | $0 | $40,000,000 | $40,000,000 | Planning funds to support future procurement of 25 electrified or decarbonized Commuter Rail rolling stock to replace the oldest vehicles in the fleet and support rail electrification. |
5337 | Revenue Vehicles | P0927 | Rolling Stock - Locomotive and Coach State of Good Repair and Resiliency | $6,000,000 | $0 | $6,000,000 | Program to upgrade system reliability, correct deficiencies, standardize procedures, and increase equipment availability for Commuter Rail rolling stock through vehicle procurement, testing, service life enhancement, and overhauls. |
5337 | Revenue Vehicles | P1173 | HSP46 Locomotive Overhaul | $0 | $100,456,813 | $100,456,813 | Midlife overhaul of 40 HSP46 Locomotives to improve reliability and reduce risk of unplanned maintenance. |
$41,391,580 | $165,678,358 | $207,069,938 | |||||
5337 - Signals and Systems | |||||||
5337 | Signals and Systems | P1315 | Fairmount Line Infrastructure for Decarbonized Service | $0 | $47,948,800 | $47,948,800 | Delivery of infrastructure necessary to operate decarbonized service every 20 minutes on the Fairmount line. |
5337 | Signals and Systems | P0146 | SCADA Upgrades | $1,600,000 | $0 | $1,600,000 | Upgrades to the Power Supervisory Control and Data Acquisition (SCADA) communication network from leased lines to the Security Wide Area Network (SWAN) to provide high-speed ethernet connection atĀ 24 traction power substations and unit substations. |
5337 | Signals and Systems | P0261 | Worcester Line Track and Station Accessibility Improvements | $0 | $25,885,742 | $25,885,742 | New third track and realignment of existing tracks on the Framingham and Worcester Commuter Rail lines between Weston and Framingham. Includes upgrades to Wellesley Farms, Wellesley Hills, Wellesley Square, and West Natick Stations. |
5337 | Signals and Systems | P0283 | Green Line Central Tunnel Signal - 25 Cycle | $3,840,000 | $0 | $3,840,000 | Replacement of 25Hz track circuits with 100Hz track circuits in the Green Line central tunnel. Includes replacement of track circuit cable, trough, messenger, cases, relays, rectifiers, and signal power equipment. |
5337 | Signals and Systems | P0301 | Systemwide Radio | $73,952,935 | $39,033,557 | $112,986,492 | Upgrade of the MBTA’s existing two-way radio system used by MBTA Transit Police and operations personnel. This project includes mobile radios for heavy rail, light rail, and bus vehicles. |
5337 | Signals and Systems | P0591 | Green Line Central Tunnel Track and Signal Replacement | $0 | $4,317,546 | $4,317,546 | Rehabilitation and upgrades to signal and track infrastructure within the Green Line Central Tunnel. Includes central instrumentation houses and signal, track, and power systems at Copley, Park Street, and Government Center. |
5337 | Signals and Systems | P0904 | Systemwide Asset Management Program Phase 3 | $7,600,000 | $0 | $7,600,000 | Continuation of implementing the Asset Management Program in accordance with FTA requirements. Includes professional services, audit, inventory, condition assessments, updates to the National Transit Database, and Transit Asset Management Plan. |
5337 | Signals and Systems | P1104 | Traction Power Substation Replacement | $5,760,000 | $4,000,000 | $9,760,000 | Complete replacement of electrical systems and strucural, mechanical, and plumbing improvements at aging traction power substations (TPSS). This scope also includes a TPSS Design Guide to standardize future improvements. |
5337 | Signals and Systems | P1132 | Ashmont Branch Track Replacement | $4,000,000 | $0 | $4,000,000 | Design and construction for partial reconstruction of track and track support systems on the Ashmont Branch of the Red Line. |
5337 | Signals and Systems | P1139 | Asset Management Program | $23,013,222 | $22,103,573 | $45,116,794 | Implementation of the MBTA Asset Management Program in accordance with FTA requirements, includeing asset inventory and condition assessments, updates to the National Transit Database and the Transit Asset Management Plan, and EAMS implementation. |
5337 | Signals and Systems | P1260 | Track Improvement Program ā Orange LineĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā | $71,975,633 | $0 | $71,975,633 | Implementation of the MBTA Track Improvement Plan to remove speed restrictions on the Orange Line. |
$191,741,790 | $143,289,218 | $335,031,008 | |||||
5337 - Stations and Facilities | |||||||
5337 | Stations and Facilities | P0003 | Green Line B Branch Consolidation | $295,716 | $0 | $295,716 | Consolidation of four Green Line B-Branch stops into two new, fully accessible stations: Babcock Street and Amory Street. Features include accessible boarding and exits, security and lighting upgrades, and longer platforms to accommodate Type 10s. |
5337 | Stations and Facilities | P0066 | Elevator Program | $1,485,474 | $0 | $1,485,474 | Design and construction funding for elevator improvements on the rapid transit system. Individual elevator projects are separated into unique projects once construction stage is reached. |
5337 | Stations and Facilities | P0074 | Downtown Crossing Vertical Transportation Improvements Phase 2 | $62,208,880 | $0 | $62,208,880 | Design and construction of 3 new elevators to provide vertical transfers from the Red Line northbound to the Orange Line southbound platform, and from the Orange Line northbound to the Red Line southbound platform at Downtown Crossing. |
5337 | Stations and Facilities | P0076 | Oak Grove Station Vertical Transportation Improvements | $800,000 | $0 | $800,000 | Accessibility upgrades at Oak Grove station, including three elevators, replacement of one existing elevator, sidewalk repairs, and wayfinding and station-brightening improvements. |
5337 | Stations and Facilities | P0087 | Braintree and Quincy Adams Garage Rehabilitation | $11,576,003 | $0 | $11,576,003 | Full rehabilitation of the Red Line’s Braintree Station and Quincy Adams Station parking garages to extend the operable service life of each facility by forty years. |
5337 | Stations and Facilities | P0129 | Newton Highlands Green Line Station Accessibility Project | $0 | $53,746,443 | $53,746,443 | Accessibility improvements at Newton Highlands Station on the Green Line D Branch, including three ramps covered with canopies, raised platforms, one at-grade pedestrian crossing, site lighting, new platform shelters, and covered bike racks.Ā Ā |
5337 | Stations and Facilities | P0163 | Forest Hills Improvement Project | $26,089,764 | $0 | $26,089,764 | Accessibility and state of good repair improvements at Forest Hills Station. Includes elevator replacement, new elevator/stair tower to connect upper and lower busway, accessibility upgrades, station brightening, wayfinding, and platform repairs.Ā |
5337 | Stations and Facilities | P0168 | Symphony Station Improvements | $0 | $0 | $0 | Upgrade Symphony Station to a modern and fully accessible passenger facility. Includes construction of four new elevators, raised platforms, accessible restrooms, installation of egress stairs, and upgraded fire alarm systems. |
5337 | Stations and Facilities | P0169 | Wollaston Station / Quincy Center Garage Demolition | $2,535,477 | $0 | $2,535,477 | Complete modernization of Wollaston Station, demolition of the top 3 levels of the Quincy Center parking garage, replacement of one elevator at Quincy Center, and construction of an accessible walkway from Burgin Parkway to Quincy Center Station. |
5337 | Stations and Facilities | P0174 | Natick Center Station Accessibility Project | $6,047,999 | $0 | $6,047,999 | Reconstruction and modernization of Natick Center Station, including new fully accessible high-level side platforms,elevators, ramps, stairs, lighting, wayfinding, streetscape, upgraded tracks, and connection to the Cochituate Rail Trail. |
5337 | Stations and Facilities | P0179 | Winchester Center Station | $10,264,133 | $0 | $10,264,133 | Reconstruction and modernization of Winchester Center Station including new fully accessible high-level side platforms,Ā elevators, ramps, stairs, lighting, signage and wayfinding, streetscape improvements, and upgraded track infrastructure. |
5337 | Stations and Facilities | P0395 | Worcester Union Station Accessibility and Infrastructure Improvements | $2,841,410 | $0 | $2,841,410 | Includes high-level center platform with elevators, ramps, and stairs; replacement and realignment of station tracks; and construction of a new rail crossover to improve accessibility, operations, and service capacity at Worcester Union Station. |
5337 | Stations and Facilities | P0631b | Blue Line Communications Rooms Improvements | $0 | $16,374,165 | $16,374,165 | Rehabilitation of communications rooms along the Blue Line to bring them into a state of good repair and support the implementation of Fare Transformation. |
5337 | Stations and Facilities | P0679 | Codman Yard Expansion and Improvements | $0 | $39,009,110 | $39,009,110 | Improvements to Codman Yard, including in-kind replacement of existing infrastructure and the expansion of storage capacity to support the new Red Line trains. |
5337 | Stations and Facilities | P0856 | Ruggles Station Improvements Phase 2 | $99,625,355 | $0 | $99,625,355 | Continuation of Ruggles Station Improvements to address accessibility, code-compliance, and state-of-good repair issues. Includes repair, reconstruction, and improvements to platforms, entrances, stairs, elevators, ramps, restrooms, and wayfinding. |
5337 | Stations and Facilities | P0923 | E Branch Accessibility & Capacity Improvements | $0 | $68,752,659 | $68,752,659 | Improvements to surface track and stations on the E branch of the Green Line, extending from the Northeastern Station portal to Heath Street Station. |
5337 | Stations and Facilities | P0924 | B Branch Accessibility & Capacity Improvements | $0 | $56,550,959 | $56,550,959 | Track realignments, accessibility improvements, potential consolidation, and station and traction power upgrades along the Green Line B branch between Blandford St. and Warren St. Stations. |
5337 | Stations and Facilities | P1010 | Riverside Vehicle Maintenance Facility Modifications & Upgrades | $0 | $38,592,184 | $38,592,184 | Upgrades to existing hoists, pits, and mezzanines at the Riverside Vehicle Maintenance Facility to accommodate the future Type 10 fleet.Ā |
5337 | Stations and Facilities | P1025 | Lynn Station Parking Garage DeconstructionĀ | $13,470,767 | $4,879,470 | $18,350,236 | Decommissioning of the closed Lynn Station parking garage.Ā |
5337 | Stations and Facilities | P1101 | Lake Street Complex Demolition and Reconfiguration | $0 | $4,989,028 | $4,989,028 | Demolition of the Lake Street facility and reconfiguration into an expanded yard. The site will be designed to maximize train storage, streamline yard operations, and eliminate a sharp curve in anticipation of the larger Type 10 light rail fleet. |
5337 | Stations and Facilities | P1171 | Billerica MOW Repair and Storage Facility | $0 | $7,948,908 | $7,948,908 | Funds to design and construct a new, fully accessible Commuter Rail maintenance facility, storage yards, and tracks in Billerica, with eight service bays, wash bay, overhead bridge crane, office space, and employee amenities. |
5337 | Stations and Facilities | P1222 | Codman Yard Storage and Office Facility | $0 | $7,650,400 | $7,650,400 | Establishment of a dedicated storage and office facility at the Codman Yard to house staff and to store, repair, and maintain critical equipment.Ā |
5337 | Stations and Facilities | R0069 | Park Street Station Wayfinding Improvements | $1,610,880 | $0 | $1,610,880 | Various improvements to lighting, CCTV placement, wayfinding and illuminated exit signage, Braille signage, floor finishes, benches, and 24 staircases at Park Street. Includes artwork restoration and reopening of Tremont Street's Temple Place stairs. |
5337 | Stations and Facilities | R0071 | Lynn Station and Parking Garage Improvements Phase II | $2,581,808 | $0 | $2,581,808 | Design funding for new elevators, stairs, platform, canopy, and architectural improvements to the station and the intent to acquire and demolish structures under station's viaduct. Existing parking garage will also be replaced by surface parking. |
$241,433,664 | $298,493,326 | $539,926,990 | |||||
5337 - Preventive Maintenance | |||||||
5337 | Preventive Maintenance | N/A | Preventive Maintenance | $35,287,500 | $105,862,500 | $141,150,000 | Preventive maintenance activities eligible for FTA reimbursement. |
$35,287,500 | $105,862,500 | $141,150,000 | |||||
5339 - Bus Program | |||||||
5339 | Bus Program | P0911 | Hybrid Bus Overhaul (New Flyer XDE40 - SR1983) | $0 | $28,667,507 | $28,667,507 | Midlife overhaul of major systems and components of 156 40ft hybrid buses to ensure reliable and safe operations that meet FTA requirements. Also includes condition assessment activities for 175 40ft CNG buses, and 45 60ft hybrid buses.Ā |
5339 | Bus Program | P1154 | CNG Bus Overhaul (New Flyer XN40 - SR 1982) | $12,116,517 | $3,261,941 | $15,378,458 | Planning for the midlife overhaul of 175 40-foot New Flyer CNG buses delivered 2016 to 2017. These buses require overhaul of major systems and components to ensure continued reliable and safe operations and to meet FTA service life requirements. |
$12,116,517 | $31,929,448 | $44,045,965 | |||||
Note: Project descriptions and dollar amounts are preliminary only and are provided for informational purposes.Ā In many cases, the scopes of work and project budgets will become more fully developed as the design process proceeds and is completed.Ā The MBTA may also opt to fund a project from a different FTA funding source based on the timing of projects and the availability of FTA funds. | |||||||
RRIF/TIFIA Financing Program | |||||||
Projects Potentially Funded by Federal RRIF/TIFIA Loans | |||||||
RRIF/TIFIA Financing | P0671a | Quincy Bus Facility Modernization | Potential RRIF/TIFIA loan - amount and timing to be determined | Relocation and replacement of the Quincy Bus Maintenance Facility. The new, modernized facility will expand capacity and includes the infrastructure necessary to support the MBTA's first battery-electric bus (BEB) fleet. | |||
RRIF/TIFIA Financing | P0952 | Widett Layover and Maintenance Facility | Potential RRIF/TIFIA loan - amount and timing to be determined | Preliminary design for a Commuter Rail layover facility at Widett Circle in South Boston. | |||
RRIF/TIFIA Financing | P0018 | North Station Draw 1 Bridge Replacement | Potential RRIF/TIFIA loan - amount and timing to be determined | Replacement of North Station Draw 1 bridge structures and control tower. Includes construction of three new vertical lift bridges, and extension of existing station platform to accommodate track 11 and 12. | |||
RRIF/TIFIA Financing | P0170 | Newton Commuter Rail Stations Design | Potential RRIF/TIFIA loan - amount and timing to be determined | Design of a fully accessible Commuter Rail station in Newton with 400' platform and the potential for either a double-sided or center-running high-level platform. | |||
RRIF/TIFIA Financing | P0178 | South Attleboro Station Improvements | Potential RRIF/TIFIA loan - amount and timing to be determined | Design for the construction of a new South Attleboro station, to include 800-ft. high-level platforms, three elevators, platform access ramps, a bus bay, egress to Newport Ave., additional parking, improved vehicular circulation, updated lighting. | |||
RRIF/TIFIA Financing | P0863 | South-Side Commuter Rail Maintenance Facility | Potential RRIF/TIFIA loan - amount and timing to be determined | Assessment and design for a new Commuter Rail maintenance and layover facility at Readville. Includes design for future construction of multiple maintenance bays within Yard 1 and Upper Yard 2.Ā | |||
Ā | |||||||
Note: The MBTA is exploring the use of federal loans through the Build America Bureau to finance certain capital projects at a lower interest rate than traditional tax-exempt bonds.Ā This includes loans under the Railroad Rehabilitation & Improvement Financing (RRIF) and Transportation Infrastructure Finance and Innovation Act (TIFIA) programs.Ā The projects listed above are being considered for this program, subject to the approval of funding through the CIP process.Ā Ā Additional project and funding information will be provided through a future TIP/Amendment if federal grant funds or loans are utilized. |
Table 3-10
FFYs 2025ā29 TIP Transit Table (MWRTA)
STIP: 2025 - 2029 (D) | ||||||||
Year | Project Number | Program | Project Description | Funding Source | Total Project Cost | Total Programmed Funds | Federal Funds | State Funds |
Federal Fiscal Year 2025 | $16,066,000 | $12,472,000 | $3,594,000 | |||||
MetroWest Regional Transit Authority | $16,066,000 | $12,472,000 | $3,594,000 | |||||
2025 | MWRTA011699 | RTA Fleet Upgrades | 5307 FORMULA- ACQUIRE REVENUE VEHICLE- TROLLEY CNG QTY 4 | 5307 | $1,000,000 | $500,000 | $500,000 | |
2025 | MWRTA011699 | RTA Fleet Upgrades | 5307 FORMULA- ACQUIRE REVENUE VEHICLE- TROLLEY CNG QTY 4 | RTACAP | $1,000,000 | $500,000 | $500,000 | |
2025 | MWRTA011700 | RTA Fleet Upgrades | METROWEST RTAĀ 5307 CARBON REDUCTION- ACQUIRE EV REVENUE TROLLEY | 5307CR | $1,250,000 | $1,250,000 | $1,250,000 | |
2025 | MWRTA011701 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY SMART EV SOLAR INFRASTRUCTURE PROJECT | DOF | $15,000,000 | $2,000,000 | $2,000,000 | |
2025 | MWRTA011701 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY SMART EV SOLAR INFRASTRUCTURE PROJECT | DRTACAP | $15,000,000 | $500,000 | $500,000 | |
2025 | MWRTA011709 | RTA Fleet Upgrades | METROWEST RTA- ACQUIRE HEAVY DUTY CNG 29FT TRANSIT BUS | 5307 | $1,980,000 | $1,584,000 | $1,584,000 | |
2025 | MWRTA011709 | RTA Fleet Upgrades | METROWEST RTA- ACQUIRE HEAVY DUTY CNG 29FT TRANSIT BUS | RTACAP | $1,980,000 | $396,000 | $396,000 | |
2025 | MWRTA011814 | RTA Fleet Upgrades | MetroWest RTA - Procurement of 3 29 Foot Buses | 5307 | $2,376,000 | $1,980,000 | $1,980,000 | |
2025 | MWRTA011814 | RTA Fleet Upgrades | MetroWest RTA - Procurement of 3 29 Foot Buses | TDC | $2,376,000 | $396,000 | $396,000 | |
2025 | MWRTA011815 | RTA Facility & System Modernization | MetroWest RTA - Blandin Hub Equitable Redesign Initiative | 5307 | $3,000,000 | $1,750,000 | $1,750,000 | |
2025 | MWRTA011815 | RTA Facility & System Modernization | MetroWest RTA - Blandin Hub Equitable Redesign Initiative | TDC | $3,000,000 | $350,000 | $350,000 | |
2025 | RTD0011109 | RTA Facility & Vehicle Maintenance | MetroWest RTA - ACQUISITION OF BUS SUPPORT EQUIP/FACILITIES | 5307 | $300,000 | $240,000 | $240,000 | |
2025 | RTD0011109 | RTA Facility & Vehicle Maintenance | MetroWest RTA - ACQUISITION OF BUS SUPPORT EQUIP/FACILITIES | RTACAP | $300,000 | $60,000 | $60,000 | |
2025 | RTD0011110 | RTA Facility & System Modernization | MetroWest Regional Transit Authority - TECHNOLOGY SUPPORT/CAPITAL OUTREACH | 5307 | $300,000 | $150,000 | $150,000 | |
2025 | RTD0011110 | RTA Facility & System Modernization | MetroWest Regional Transit Authority - TECHNOLOGY SUPPORT/CAPITAL OUTREACH | RTACAP | $300,000 | $150,000 | $150,000 | |
2025 | RTD0011111 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | 5307 | $700,000 | $560,000 | $560,000 | |
2025 | RTD0011111 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | RTACAP | $700,000 | $140,000 | $140,000 | |
2025 | RTD0011121 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - Framingham Commuter Rail Station (FCRS) | 5307 | $10,000 | $8,000 | $8,000 | |
2025 | RTD0011121 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - Framingham Commuter Rail Station (FCRS) | RTACAP | $10,000 | $2,000 | $2,000 | |
2025 | RTD0011124 | RTA Fleet Upgrades | MetroWest RTA - 5307 FORMULA 2025 ELECTRIC VEHICLE (EV) ADDTL ELECTRIFICATION INFRASTRUCTURE COSTS - DISCRETIONARY | 5307 | $500,000 | $250,000 | $250,000 | |
2025 | RTD0011124 | RTA Fleet Upgrades | MetroWest RTA - 5307 FORMULA 2025 ELECTRIC VEHICLE (EV) ADDTL ELECTRIFICATION INFRASTRUCTURE COSTS - DISCRETIONARY | DRTACAP | $500,000 | $250,000 | $250,000 | |
2025 | RTD0011134 | RTA Facility & Vehicle Maintenance | MetroWest RTA - PUBLIC RESTROOMS AT BLANDIN & FCRS HUBS - 5307 | 5307 | $500,000 | $200,000 | $200,000 | |
2025 | RTD0011134 | RTA Facility & Vehicle Maintenance | MetroWest RTA - PUBLIC RESTROOMS AT BLANDIN & FCRS HUBS - 5307 | RTACAP | $500,000 | $50,000 | $50,000 | |
2025 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | 5307 | $4,000,000 | $113,172 | $113,172 | |
2025 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | 5339 | $4,000,000 | $286,828 | $286,828 | |
2025 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | RTACAP | $4,000,000 | $400,000 | $400,000 | |
2025 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | 5307 | $10,000,000 | $1,600,000 | $1,600,000 | |
2025 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | SCA | $10,000,000 | $400,000 | $400,000 | |
Federal Fiscal Year 2026 | $20,483,436 | $15,786,748 | $4,696,688 | |||||
MetroWest Regional Transit Authority | $20,483,436 | $15,786,748 | $4,696,688 | |||||
2026 | MWRTA011701 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY SMART EV SOLAR INFRASTRUCTURE PROJECT | DOF | $15,000,000 | $8,000,000 | $8,000,000 | |
2026 | MWRTA011701 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY SMART EV SOLAR INFRASTRUCTURE PROJECT | DRTACAP | $15,000,000 | $2,000,000 | $2,000,000 | |
2026 | MWRTA011707 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY 5339 BACK ENTRANCE PROJECT BLANDIN | 5339D | $7,000,000 | $2,800,000 | $2,800,000 | |
2026 | MWRTA011707 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY 5339 BACK ENTRANCE PROJECT BLANDIN | DRTACAP | $7,000,000 | $700,000 | $700,000 | |
2026 | MWRTA011815 | RTA Facility & System Modernization | MetroWest RTA - Blandin Hub Equitable Redesign Initiative | 5307 | $3,000,000 | $750,000 | $750,000 | |
2026 | MWRTA011815 | RTA Facility & System Modernization | MetroWest RTA - Blandin Hub Equitable Redesign Initiative | TDC | $3,000,000 | $150,000 | $150,000 | |
2026 | RTD0011117 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | 5307 | $700,000 | $560,000 | $560,000 | |
2026 | RTD0011117 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | RTACAP | $700,000 | $140,000 | $140,000 | |
2026 | RTD0011118 | RTA Facility & System Modernization | MetroWest Regional Transit Authority - TECHNOLOGY SUPPORT/CAPITAL OUTREACH | 5307 | $300,000 | $150,000 | $150,000 | |
2026 | RTD0011118 | RTA Facility & System Modernization | MetroWest Regional Transit Authority - TECHNOLOGY SUPPORT/CAPITAL OUTREACH | RTACAP | $300,000 | $150,000 | $150,000 | |
2026 | RTD0011119 | RTA Facility & Vehicle Maintenance | MetroWest RTA - ACQUISITION OF BUS SUPPORT EQUIP/FACILITIES | 5307 | $450,000 | $360,000 | $360,000 | |
2026 | RTD0011119 | RTA Facility & Vehicle Maintenance | MetroWest RTA - ACQUISITION OF BUS SUPPORT EQUIP/FACILITIES | RTACAP | $450,000 | $90,000 | $90,000 | |
2026 | RTD0011120 | RTA Facility & Vehicle Maintenance | MetroWest Regional Transit Authority - TERMINAL, INTERMODAL (TRANSIT) - Framingham Commuter Rail Station | 5307 | $10,000 | $8,000 | $8,000 | |
2026 | RTD0011120 | RTA Facility & Vehicle Maintenance | MetroWest Regional Transit Authority - TERMINAL, INTERMODAL (TRANSIT) - Framingham Commuter Rail Station | RTACAP | $10,000 | $2,000 | $2,000 | |
2026 | RTD0011125 | RTA Fleet Upgrades | MetroWest RTA - 2026 ELECTRIC VEHICLE (EV) ADDTL ELECTRIFICATION COSTS | 5339 | $1,000,000 | $500,000 | $500,000 | |
2026 | RTD0011125 | RTA Fleet Upgrades | MetroWest RTA - 2026 ELECTRIC VEHICLE (EV) ADDTL ELECTRIFICATION COSTS | RTACAP | $1,000,000 | $500,000 | $500,000 | |
2026 | RTD0011134 | RTA Facility & Vehicle Maintenance | MetroWest RTA - PUBLIC RESTROOMS AT BLANDIN & FCRS HUBS - 5307 | 5307 | $500,000 | $200,000 | $200,000 | |
2026 | RTD0011134 | RTA Facility & Vehicle Maintenance | MetroWest RTA - PUBLIC RESTROOMS AT BLANDIN & FCRS HUBS - 5307 | RTACAP | $500,000 | $50,000 | $50,000 | |
2026 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | 5307 | $4,000,000 | $400,000 | $400,000 | |
2026 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | RTACAP | $4,000,000 | $400,000 | $400,000 | |
2026 | RTD0011138 | RTA Vehicle Replacement | MetroWest RTA - 5339 DISCRETIONARY VEHICLE REPLACEMENT - CUTAWAYS TYPE D CNG | 5339D | $2,293,744 | $458,748 | $458,748 | |
2026 | RTD0011138 | RTA Vehicle Replacement | MetroWest RTA - 5339 DISCRETIONARY VEHICLE REPLACEMENT - CUTAWAYS TYPE D CNG | RTACAP | $2,293,744 | $114,688 | $114,688 | |
2026 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | 5307 | $10,000,000 | $1,600,000 | $1,600,000 | |
2026 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | SCA | $10,000,000 | $400,000 | $400,000 | |
Federal Fiscal Year 2027 | $15,505,353 | $11,610,537 | $3,894,816 | |||||
MetroWest Regional Transit Authority | $15,505,353 | $11,610,537 | $3,894,816 | |||||
2027 | MWRTA011701 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY SMART EV SOLAR INFRASTRUCTURE PROJECT | DOF | $15,000,000 | $2,000,000 | $2,000,000 | |
2027 | MWRTA011701 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY SMART EV SOLAR INFRASTRUCTURE PROJECT | DRTACAP | $15,000,000 | $500,000 | $500,000 | |
2027 | MWRTA011707 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY 5339 BACK ENTRANCE PROJECT BLANDIN | 5339D | $7,000,000 | $2,800,000 | $2,800,000 | |
2027 | MWRTA011707 | RTA Facility & System Modernization | METROWEST RTA- DISCRETIONARY 5339 BACK ENTRANCE PROJECT BLANDIN | DRTACAP | $7,000,000 | $700,000 | $700,000 | |
2027 | MWRTA011708 | RTA Facility & System Modernization | METROWEST RTA- TECHNICAL ASSISTANCE HYDROGEN DEPLOYMENT | RTACAP | $1,000,000 | $500,000 | $500,000 | |
2027 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | 5307 | $4,000,000 | $400,000 | $400,000 | |
2027 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | RTACAP | $4,000,000 | $400,000 | $400,000 | |
2027 | RTD0011138 | RTA Vehicle Replacement | MetroWest RTA - 5339 DISCRETIONARY VEHICLE REPLACEMENT - CUTAWAYS TYPE D CNG | 5339D | $2,293,744 | $458,748 | $458,748 | |
2027 | RTD0011138 | RTA Vehicle Replacement | MetroWest RTA - 5339 DISCRETIONARY VEHICLE REPLACEMENT - CUTAWAYS TYPE D CNG | RTACAP | $2,293,744 | $114,688 | $114,688 | |
2027 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | 5307 | $10,000,000 | $1,600,000 | $1,600,000 | |
2027 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | SCA | $10,000,000 | $400,000 | $400,000 | |
2027 | RTD0011196 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | 5307 | $2,600,000 | $960,000 | $960,000 | |
2027 | RTD0011196 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | RTACAP | $2,600,000 | $240,000 | $240,000 | |
2027 | RTD0011197 | RTA Facility & Vehicle Maintenance | MetroWest Regional Transit Authority - TECHNOLOGY SUPPORT/CAPITAL OUTREACH | 5307 | $900,000 | $150,000 | $150,000 | |
2027 | RTD0011197 | RTA Facility & Vehicle Maintenance | MetroWest Regional Transit Authority - TECHNOLOGY SUPPORT/CAPITAL OUTREACH | RTACAP | $900,000 | $150,000 | $150,000 | |
2027 | RTD0011198 | RTA Facility & Vehicle Maintenance | MetroWest RTA - ACQUISITION OF BUS SUPPORT EQUIP/FACILITIES | 5307 | $1,350,000 | $360,000 | $360,000 | |
2027 | RTD0011198 | RTA Facility & Vehicle Maintenance | MetroWest RTA - ACQUISITION OF BUS SUPPORT EQUIP/FACILITIES | RTACAP | $1,350,000 | $90,000 | $90,000 | |
2027 | RTD0011199 | RTA Facility & Vehicle Maintenance | MetroWest Regional Transit Authority - TERMINAL, INTERMODAL (TRANSIT) - Framingham Commuter Rail StationĀ | 5307 | $30,000 | $8,000 | $8,000 | |
2027 | RTD0011199 | RTA Facility & Vehicle Maintenance | MetroWest Regional Transit Authority - TERMINAL, INTERMODAL (TRANSIT) - Framingham Commuter Rail StationĀ | RTACAP | $30,000 | $2,000 | $2,000 | |
2027 | RTD0011200 | RTA Vehicle Replacement | MetroWest RTA - 5339 COMPETITIVE REVENUE VEHICLE REPLACEMENT - DISCRETIONARY | 5339D | $1,771,917 | $1,653,789 | $1,653,789 | |
2027 | RTD0011200 | RTA Vehicle Replacement | MetroWest RTA - 5339 COMPETITIVE REVENUE VEHICLE REPLACEMENT - DISCRETIONARY | DRTACAP | $1,771,917 | $118,128 | $118,128 | |
2027 | RTD0011201 | RTA Fleet Upgrades | MetroWest Regional Transit Authority - 2027 ELECTRIC VEHICLE (EV) ADDTL ELECTRIFICATION COSTS | 5339D | $1,800,000 | $720,000 | $720,000 | |
2027 | RTD0011201 | RTA Fleet Upgrades | MetroWest Regional Transit Authority - 2027 ELECTRIC VEHICLE (EV) ADDTL ELECTRIFICATION COSTS | DRTACAP | $1,800,000 | $180,000 | $180,000 | |
2027 | RTD0011267 | RTA Fleet Upgrades | MetroWest RTA - 2027 EV - Additional Electrification for Vehicles | 5307 | $3,000,000 | $500,000 | $500,000 | |
2027 | RTD0011267 | RTA Fleet Upgrades | MetroWest RTA - 2027 EV - Additional Electrification for Vehicles | RTACAP | $3,000,000 | $500,000 | $500,000 | |
Federal Fiscal Year 2028 | $19,233,436 | $16,756,748 | $2,476,688 | |||||
MetroWest Regional Transit Authority | $19,233,436 | $16,756,748 | $2,476,688 | |||||
2028 | MWRTA011705 | RTA Facility & System Modernization | METROWEST RTA - PASSENGER TRANSFER STATION | 5339D | $12,000,000 | $12,000,000 | $12,000,000 | |
2028 | MWRTA011708 | RTA Facility & System Modernization | METROWEST RTA- TECHNICAL ASSISTANCE HYDROGEN DEPLOYMENT | RTACAP | $1,000,000 | $500,000 | $500,000 | |
2028 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | 5307 | $4,000,000 | $400,000 | $400,000 | |
2028 | RTD0011137 | RTA Vehicle Replacement | MetroWest RTA - VEHICLE REPLACEMENT - CUTAWAYS 6 Type D with CNG | RTACAP | $4,000,000 | $400,000 | $400,000 | |
2028 | RTD0011138 | RTA Vehicle Replacement | MetroWest RTA - 5339 DISCRETIONARY VEHICLE REPLACEMENT - CUTAWAYS TYPE D CNG | 5339D | $2,293,744 | $458,748 | $458,748 | |
2028 | RTD0011138 | RTA Vehicle Replacement | MetroWest RTA - 5339 DISCRETIONARY VEHICLE REPLACEMENT - CUTAWAYS TYPE D CNG | RTACAP | $2,293,744 | $114,688 | $114,688 | |
2028 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | 5307 | $10,000,000 | $1,600,000 | $1,600,000 | |
2028 | RTD0011195 | Operating | MetroWest Regional Transit Authority - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARA SERV | SCA | $10,000,000 | $400,000 | $400,000 | |
2028 | RTD0011196 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | 5307 | $2,600,000 | $560,000 | $560,000 | |
2028 | RTD0011196 | RTA Facility & Vehicle Maintenance | MetroWest RTA - TERMINAL, INTERMODAL (TRANSIT) - BLANDIN | RTACAP | $2,600,000 | $140,000 | $140,000 | |
2028 | RTD0011197 | RTA Facility & Vehicle Maintenance | MetroWest Regional Transit Authority - TECHNOLOGY SUPPORT/CAPITAL OUTREACH | 5307 | $900,000 | $150,000 | $150,000 | < |